3715 S JASMINE AVE 1-9 90034
Certificate Information: 3715 S JASMINE AVE 1-9 90034
- Application / Permit
- 17016-10000-37718
- Plan Check / Job No.
- B17LA23213
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story seismic retrofit per LAMC 93: (2) Cantilever Columns and Shear Wall
- Permit Issued
- Issued on 8/17/2021
- Issuing Office
- Current Status
- CofC Issued on 11/9/2021
Permit Application Status History
| Submitted | 12/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | HERNAN ARREOLA |
| Corrections Issued | 1/12/2018 | HERNAN ARREOLA |
| Quality Review Completed | 1/12/2018 | SAI KHUM |
| Building Plans Picked Up | 1/17/2018 | APPLICANT |
| Plan Check Approved | 2/1/2018 | HERNAN ARREOLA |
| Issued | 8/17/2021 | APPLICANT |
| OK for CofC | 11/4/2021 | GRANT WOODS |
| CofC Issued | 11/9/2021 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/11/2021 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Everest Construct Inc; Lic. No.: 1075122-B | 1171 S ROBETSON BLVD #395 LOS ANGELES, CA 90035 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2021 | Approved | PAUL DAVIDSON |
| Deputy Drilled-In Anchors | 9/13/2021 | Conditional Approval | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 9/21/2021 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Steel/Welding | 9/21/2021 | Conditional Approval | PAUL DAVIDSON |
| Footing/Foundation/Slab | 9/22/2021 | Approved | JOHN DODGE |
| Deputy Reinf. Concrete | 9/23/2021 | Conditional Approval | GRANT WOODS |
| Structural Steel Frame | 10/20/2021 | Approved | DERRICK SPENCER |
| Wood Frame | 10/20/2021 | Approved | DERRICK SPENCER |
| Insulation | 10/21/2021 | Approved | GRANT WOODS |
| Deputy Wood Construction | 10/22/2021 | Conditional Approval | GRANT WOODS |
| Wood Frame | 10/26/2021 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 10/29/2021 | Approved | GRANT WOODS |
| Final | 11/4/2021 | OK for CofC | GRANT WOODS |
| METHANE-Final | 11/4/2021 | Approved | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 11/4/2021 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 11/4/2021 | Approved | GRANT WOODS |