9725 W CHARNOCK AVE 90034
Certificate Information: 9725 W CHARNOCK AVE 90034
- Application / Permit
- 17016-10000-37716
- Plan Check / Job No.
- B17LA23208
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story seismic retrofit per LAMC 93: (1) Cantilever Column
- Permit Issued
- Issued on 3/18/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 3/21/2022
Permit Application Status History
| Submitted | 12/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | HERNAN ARREOLA |
| Corrections Issued | 1/8/2018 | HERNAN ARREOLA |
| Quality Review Completed | 1/12/2018 | SAI KHUM |
| Building Plans Picked Up | 1/17/2018 | APPLICANT |
| Plan Check Approved | 2/1/2018 | HERNAN ARREOLA |
| Issued | 3/18/2020 | LADBS |
| OK for CofC | 3/18/2022 | GRANT WOODS |
| CofC Issued | 3/21/2022 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 3/17/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 6900 CANBY AVE #108 RESEDA, CA 91335 |
| Engineer | Labib, Youhanna T; Lic. No.: S4549 | 209 E EL SEGUNDO BLVD EL SEGUNDO, CA 90245 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/30/2021 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 1/20/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 1/25/2022 | Conditional Approval | GRANT WOODS |
| Deputy Reinf. Concrete | 1/25/2022 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 2/4/2022 | Approved | PAUL DAVIDSON |
| Structural Steel Frame | 2/4/2022 | Approved | PAUL DAVIDSON |
| Wood Frame | 2/4/2022 | Approved | PAUL DAVIDSON |
| Deputy Reinf. Concrete | 2/8/2022 | Conditional Approval | PAUL DAVIDSON |
| Interior/Exterior Lathing | 3/4/2022 | Approved | PAUL DAVIDSON |
| Final | 3/14/2022 | Partial Inspection | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/14/2022 | SGSOV Not Ready | GRANT WOODS |
| Smoke Detectors | 3/14/2022 | Approved | GRANT WOODS |
| Final | 3/18/2022 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 3/18/2022 | SGSOV Approved | GRANT WOODS |