2602 N NORTH BROADWAY 90031
Certificate Information: 2602 N NORTH BROADWAY 90031
- Application / Permit
- 17016-10000-37001
- Plan Check / Job No.
- B17LA22750
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- CHANGE OF USE FROM RETAIL TO BAKERY. NON-STRUCTURAL INTERIOR TENANT IMPROVEMENT FOR A BAKERY SHOP. SCOPE INCLUDE NEW INTERIOR NON-BEARING PARTITION, MILLWOKS, CEILINGS, AND FINISHES.
- Permit Issued
- Issued on 1/29/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/28/2018
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/13/2017 | JAYDON NGUYEN |
| Corrections Issued | 12/13/2017 | JAYDON NGUYEN |
| Plan Check Approved | 1/19/2018 | JAYDON NGUYEN |
| Issued | 1/29/2018 | LADBS |
| CofO in Progress | 12/26/2018 | JEFFREY FULTON |
| CofO Issued | 12/28/2018 | DAVID TSAU |
| Permit Finaled | 12/28/2018 | DAVID TSAU |
Permit Application Clearance Information
| "Q" conditions | Cleared | 1/5/2018 | EDBER MACEDO |
| Supp. Use District POD/CDO/TDO | Cleared | 1/16/2018 | NICOLE SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2018 | JACOB BIGLER |
| Food Service Establishment | Cleared | 1/18/2018 | PAWAN VERMA |
| Food establishment approval | Cleared | 1/19/2018 | LACDHS APPROVED |
| Sewer availability | Cleared | 1/19/2018 | CARLA VALLADARES |
Contact Information
| Contractor | Dorado Design And Construction Inc; Lic. No.: 778969-B | 1607 EAST WALNUT STREET PASADENA, CA 91106 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2018 | Partial Approval | FELIX CEBALLOS |
| Light Gage Steel Frame | 3/20/2018 | Partial Approval | FELIX CEBALLOS |
| Drywall Nailing | 3/27/2018 | Approved | FELIX CEBALLOS |
| T-Bar Ceiling | 5/14/2018 | Partial Approval | KATY RAMIREZ |
| Final | 6/15/2018 | Not Ready for Inspection | FELIX CEBALLOS |
| Reinforced Masonry Frame | 6/15/2018 | Approved | FELIX CEBALLOS |
| SGSOV-Seismic Gas S/O Valve | 6/15/2018 | SGSOV Approved | FELIX CEBALLOS |
| Smoke Detectors | 6/15/2018 | Approved | FELIX CEBALLOS |
| Pre-Inspection | 6/18/2018 | Partial Approval | FELIX CEBALLOS |
| Final | 6/19/2018 | Conditional Approval | FELIX CEBALLOS |