19505 W SHERMAN WAY 91335
Certificate Information: 19505 W SHERMAN WAY 91335
- Application / Permit
- 17016-10000-36590
- Plan Check / Job No.
- B17LA22558
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LAMC DIVISION 93. INSTALL THREE (N) OMF
- Permit Issued
- Issued on 8/11/2020
- Issuing Office
- Current Status
- CofC Issued on 2/1/2021
Permit Application Status History
| Submitted | 12/11/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/28/2017 | VARAND SARKISIAN |
| Corrections Issued | 1/2/2018 | VARAND SARKISIAN |
| Quality Review Completed | 1/2/2018 | SAI KHUM |
| Building Plans Picked Up | 1/4/2018 | APPLICANT |
| Plan Check Approved | 1/18/2018 | VARAND SARKISIAN |
| Issued | 8/11/2020 | APPLICANT |
| OK for CofC | 1/5/2021 | DANIEL VARNUM |
| CofC Issued | 2/1/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/5/2020 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Optimum Seismic Inc; Lic. No.: 1012702-B | 5508 S SANTA FE AVENUE VERNON, CA 90058 |
| Engineer | Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2020 | Partial Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 9/21/2020 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 9/29/2020 | Approved | DANIEL VARNUM |
| Structural Steel Frame | 9/29/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 9/29/2020 | Corrections Issued | DANIEL VARNUM |
| Deputy Reinf. Concrete | 9/30/2020 | Conditional Approval | KENNETH ROBERTS |
| Special/Order Compliance | 11/6/2020 | Approved | JEFFREY DURAN |
| Structural Steel Frame | 11/6/2020 | Approved | DANIEL VARNUM |
| Wood Frame | 11/6/2020 | Approved | DANIEL VARNUM |
| Interior/Exterior Lathing | 11/13/2020 | Approved | DANIEL VARNUM |
| Final | 12/30/2020 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 12/30/2020 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 12/30/2020 | Not Ready for Inspection | DANIEL VARNUM |
| Final | 1/5/2021 | OK for CofC | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 1/5/2021 | SGSOV Approved | DANIEL VARNUM |
| Smoke Detectors | 1/5/2021 | Approved | DANIEL VARNUM |