9204 S CENTRAL AVE 90002
Certificate Information: 9204 S CENTRAL AVE 90002
- Application / Permit
- 17016-10000-36084
- Plan Check / Job No.
- B17LA22305
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Laundry
- Work Description
- CHANGE OF USE FROM (E) RETAIL TO (N) 1-STORY COIN LAUNDRY; RESTRIPE PARKING LOT.
- Permit Issued
- Issued on 12/12/2019
- Issuing Office
- Metro
- Current Status
- Issued on 12/12/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/6/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2017 | DEAN LEE |
| Green Plans Picked Up | 12/15/2017 | APPLICANT |
| Corrections Issued | 12/20/2017 | DEAN LEE |
| Quality Review Completed | 12/27/2017 | ARMEN JIVALAGIAN |
| Building Plans Picked Up | 12/28/2017 | APPLICANT |
| Disabled Access Plans Picked Up | 1/5/2018 | APPLICANT |
| Applicant returned to address corrections | 3/7/2018 | DEAN LEE |
| Applicant returned to address corrections | 7/5/2018 | DEAN LEE |
| Applicant returned to address corrections | 10/22/2018 | DEAN LEE |
| Applicant returned to address corrections | 4/16/2019 | DEAN LEE |
| Plan Check Approved | 9/12/2019 | DEAN LEE |
| Issued | 12/12/2019 | LADBS |
Permit Application Clearance Information
| Green Code | Cleared | 1/26/2018 | NEGAR NEJAD |
| DAS Clearance | Cleared | 7/5/2018 | EDDIE GARIN |
| Specific Plan | Cleared | 7/5/2018 | JOHNATHAN YU |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2019 | JEANETTE VONG |
| Sewer availability | Cleared | 9/9/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Col Construction; Lic. No.: 1053374-B | 123 S FIGUEROA STREET #304 LOS ANGELES, CA 90012 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Green Building Rough | 3/27/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Pre-Inspection | 3/27/2020 | Partial Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 5/12/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Wood Frame | 5/12/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Drywall Nailing | 8/5/2020 | Partial Approval | LEOPOLDO MENDOZA |
| Partition/T-Bar Ceiling | 8/5/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| T-Bar Ceiling | 8/5/2020 | Conditional Approval | LEOPOLDO MENDOZA |
| Masonry Wall/Backfill | 12/16/2020 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Masonry Wall/Backfill | 12/18/2020 | Partial Approval | JONATHAN QUACH |
| Masonry Wall/Backfill | 1/14/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 6/29/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Final | 6/29/2021 | Not Ready for Inspection | LEOPOLDO MENDOZA |
| Green Building Rough | 6/29/2021 | Approved | LEOPOLDO MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 6/29/2021 | SGSOV Approved | LEOPOLDO MENDOZA |
| Smoke Detectors | 6/29/2021 | Approved | LEOPOLDO MENDOZA |
| Wood Frame | 6/29/2021 | Approved | LEOPOLDO MENDOZA |
| Final | 7/7/2021 | Conditional Approval | LEOPOLDO MENDOZA |
| Green Building Final | 7/7/2021 | Approved | LEOPOLDO MENDOZA |
| Special/Order Compliance | 2/16/2024 | No Access for Inspection | LUIS CCAMACHO |