1716 S 3RD AVE 90019
Certificate Information: 1716 S 3RD AVE 90019
- Application / Permit
- 17016-10000-35404
- Plan Check / Job No.
- B17LA21872
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT AT REAR OF LOT.
- Permit Issued
- Issued on 2/15/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/29/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 12/19/2017 | YOUNG KIM |
| Corrections Issued | 12/19/2017 | YOUNG KIM |
| Applicant returned to address corrections | 1/26/2018 | PAUL PIERRE |
| Plan Check Approved | 2/12/2018 | MICHAEL LOPEZ |
| Issued | 2/15/2018 | LADBS |
| CofO in Progress | 12/2/2019 | AJA COLLAY |
| CofO Issued | 2/13/2020 | DEROLD HAUFF |
| Permit Finaled | 2/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/24/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 1/24/2018 | NAZILA NOORIFAR |
| ZI | Cleared | 2/12/2018 | STACY FARFAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/8/2018 | Corrections Issued | SALVADOR GONZALEZ |
| Footing/Foundation/Slab | 9/13/2018 | Corrections Issued | AJA COLLAY |
| Pre-Inspection | 10/3/2018 | Approved | AJA COLLAY |
| Footing/Foundation/Slab | 11/6/2018 | Partial Approval | AJA COLLAY |
| Special/Order Compliance | 11/15/2018 | Not Ready for Inspection | AJA COLLAY |
| PLUMBING-Rough | 1/30/2019 | Partial Approval | AJA COLLAY |
| BUILDING-Rough-Frame | 2/15/2019 | Corrections Issued | AJA COLLAY |
| Footing/Foundation/Slab | 2/15/2019 | Approved | AJA COLLAY |
| Insulation | 2/15/2019 | Approved | AJA COLLAY |
| METHANE-Rough | 2/15/2019 | Approved | AJA COLLAY |
| Rough-Elec/Plmb/HVAC | 2/15/2019 | Partial Approval | AJA COLLAY |
| BUILDING-Rough-Frame | 3/21/2019 | Approved | AJA COLLAY |
| Drywall Nailing | 3/21/2019 | Approved | AJA COLLAY |
| ELECTRICAL-Final | 3/21/2019 | Approved | AJA COLLAY |
| Insulation | 3/21/2019 | Approved | AJA COLLAY |
| PLUMBING-Final | 3/21/2019 | Approved | AJA COLLAY |
| Final | 12/2/2019 | OK to Issue CofO | AJA COLLAY |
| SGSOV-Seismic Gas S/O Valve | 12/2/2019 | SGSOV Approved | AJA COLLAY |
| Smoke Detectors | 12/2/2019 | Approved | AJA COLLAY |