632 N MANHATTAN PL 90004
Certificate Information: 632 N MANHATTAN PL 90004
- Application / Permit
- 17016-10000-35108
- Plan Check / Job No.
- B17LA21678
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT PER LAMC DIV. 93. (1) NEW STEEL CANTILEVERD COLUMN AND (2) NEW SHEAR WALL
- Permit Issued
- Issued on 4/27/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 12/4/2020
Permit Application Status History
| Submitted | 11/28/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/30/2017 | VARAND SARKISIAN |
| Corrections Issued | 12/4/2017 | VARAND SARKISIAN |
| Quality Review Completed | 12/7/2017 | SAI KHUM |
| Building Plans Picked Up | 12/14/2017 | APPLICANT |
| Applicant returned to address corrections | 1/24/2018 | VARAND SARKISIAN |
| Plan Check Approved | 1/24/2018 | VARAND SARKISIAN |
| Issued | 4/27/2020 | LADBS |
| OK for CofC | 10/28/2020 | MARK FERRARI |
| CofC Issued | 12/4/2020 | ERNESTO CORRAL |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 1/24/2018 | JIM URQUHART |
| Housing rent stabilization | Cleared | 3/26/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Mae Cm Services; Lic. No.: 886471-B | 6137 WILSHIRE BLVD LOS ANGELES, CA 90048 |
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/5/2020 | Approved | MARK FERRARI |
| Deputy Steel/Welding | 7/9/2020 | Conditional Approval | FRED WOHLFARTH |
| Excavation/Setback/Form/Re-Bar | 7/24/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 7/24/2020 | Conditional Approval | MARK FERRARI |
| Structural Steel Frame | 7/24/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 7/24/2020 | Corrections Issued | MARK FERRARI |
| Wood Frame | 7/29/2020 | Partial Approval | MARK FERRARI |
| Wood Frame | 8/5/2020 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 8/13/2020 | Approved | VAHE KELEDJIAN |
| Final | 9/11/2020 | Not Ready for Inspection | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 9/11/2020 | SGSOV Approved | MARK FERRARI |
| Smoke Detectors | 9/11/2020 | Approved | MARK FERRARI |
| Final | 10/26/2020 | Conditional Approval | MARK FERRARI |
| Final | 10/28/2020 | OK for CofC | MARK FERRARI |