14200 W SHERMAN WAY 91405

Certificate Information: 14200 W SHERMAN WAY 91405

Application / Permit
17016-10000-34407
Plan Check / Job No.
B17LA21210
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LAMC DIVISION 93. INSTALL 6 (N) SPECIAL CANTILEVER COLUMN
Permit Issued
Issued on 1/21/2020
Issuing Office
Metro
Current Status
CofC Issued on 7/9/2020

Permit Application Status History

Submitted 11/22/2017 APPLICANT
Assigned to Plan Check Engineer 12/14/2017 VARAND SARKISIAN
Corrections Issued 12/18/2017 VARAND SARKISIAN
Quality Review Completed 12/18/2017 SAI KHUM
Building Plans Picked Up 1/4/2018 APPLICANT
Applicant returned to address corrections 3/28/2018 VARAND SARKISIAN
Plan Check Approved 4/10/2018 VARAND SARKISIAN
Issued 1/21/2020 LADBS
OK for CofC 7/8/2020 VAHE KELEDJIAN
CofC Issued 7/9/2020 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 8/2/2019 MICHAEL GREGERSON

Contact Information

Contractor L A Retrofit Inc; Lic. No.: 1047943-B 818 7TH STREET APARTMENT 2      SANTA MONICA, CA 90403
Engineer Farmand, Anthony E; Lic. No.: C62595 4675 MACARTHUR COURT SUITE 800      NEWPORT BEACH, CA 92660

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/3/2020 Not Ready for Inspection DANIEL VARNUM
Pre-Inspection 4/3/2020 Partial Inspection DANIEL VARNUM
Special/Order Compliance 4/3/2020 Not Ready for Inspection DANIEL VARNUM
Wood Frame 4/3/2020 Not Ready for Inspection DANIEL VARNUM
Deputy Reinf. Concrete 4/21/2020 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 4/21/2020 Conditional Approval JOE VELASQUEZ
Structural Steel Frame 4/23/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 4/23/2020 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 5/5/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 5/5/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 5/7/2020 Approved JOE VELASQUEZ
Interior/Exterior Lathing 5/8/2020 Not Ready for Inspection JOE VELASQUEZ
Interior/Exterior Lathing 5/11/2020 Approved DANIEL VARNUM
Final 5/14/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 5/14/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 5/14/2020 Not Ready for Inspection JOE VELASQUEZ
Pre-Inspection 5/15/2020 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 6/5/2020 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 6/5/2020 Not Ready for Inspection JOE VELASQUEZ
Final 6/9/2020 Not Ready for Inspection JOE VELASQUEZ
SGSOV-Seismic Gas S/O Valve 6/9/2020 SGSOV Not Ready JOE VELASQUEZ
Smoke Detectors 6/9/2020 Not Ready for Inspection JOE VELASQUEZ
Final 7/8/2020 OK for CofC VAHE KELEDJIAN
SGSOV-Seismic Gas S/O Valve 7/8/2020 SGSOV Approved VAHE KELEDJIAN
Smoke Detectors 7/8/2020 Approved VAHE KELEDJIAN