226 E 1ST ST 90012

Certificate Information: 226 E 1ST ST 90012

Application / Permit
17016-10000-34116
Plan Check / Job No.
B17LA20983
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(17) Restaurant
Work Description
Change of use from Retail to Restaurant (20.5' x 60.5').
Permit Issued
Issued on 5/30/2018
Issuing Office
Metro
Current Status
CofO Issued on 5/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/20/2017 APPLICANT
Assigned to Plan Check Engineer 11/28/2017 SALVADOR QUINTANILLA
Corrections Issued 11/28/2017 JASON HEALEY
Plan Check Approved 12/26/2017 SALVADOR QUINTANILLA
Plan Check Approved 5/29/2018 JAYDON NGUYEN
Issued 5/30/2018 LADBS
CofO in Progress 5/28/2020 DANIEL COLLINS
CofO Issued 5/29/2020 DAVID TSAU
Permit Finaled 5/29/2020 DAVID TSAU

Permit Application Clearance Information

"Q" conditions Cleared 11/20/2017 BRIDGETTE WOOTEN
Eng Process Fee Ord 176,300 Cleared 11/20/2017 CELINA MORENO
Sewer availability Cleared 11/20/2017 CELINA MORENO
Supp. Use District POD/CDO/TDO Cleared 11/20/2017 YOVANA PEREZ
ZA Case Cleared 11/20/2017 BRIDGETTE WOOTEN
Food Service Establishment Cleared 12/18/2017 KENNETH BROWNE
Food establishment approval Cleared 12/26/2017 LACDHS APPROVED
Food establishment approval Cleared 5/29/2018 LACDHS APPROVED

Contact Information

Contractor Calasia Construction Inc; Lic. No.: 938255-B 3050 FLETCHER DRIVE      LOS ANGELES, CA 90065

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/6/2018 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 12/7/2018 Partial Inspection WINSTON DUNNING
Pre-Inspection 12/7/2018 Partial Inspection WINSTON DUNNING
SGSOV-Seismic Gas S/O Valve 12/7/2018 SGSOV Approved WINSTON DUNNING
Wood Frame 12/7/2018 Partial Inspection WINSTON DUNNING
Light Gage Steel Frame 1/18/2019 Conditional Approval DANIEL COLLINS
Drywall Nailing 1/23/2019 Approved DANIEL COLLINS
Insulation 1/23/2019 Approved DANIEL COLLINS
T-Bar Ceiling 8/8/2019 Approved FELIX CEBALLOS
Final 8/30/2019 OK to Issue CofO DANIEL COLLINS
METHANE-Final 8/30/2019 Approved DANIEL COLLINS
Smoke Detectors 8/30/2019 Approved DANIEL COLLINS