402 S ROBERTSON BLVD 90048

Certificate Information: 402 S ROBERTSON BLVD 90048

Application / Permit
17016-10000-33897
Plan Check / Job No.
B17LA20858
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 3 SPECIAL CANTILEVERED COLUMN SYSTEMS (SCCS) WITH CONCRETE GRADE BEAM AND 1 WOOD SHEAR WALL. WORKS ARE AT REAR TUCK-UNDER PARKING AREAS, NOT ON TENANTS' UNITS.
Permit Issued
Issued on 1/10/2020
Issuing Office
Metro
Current Status
CofC Issued on 12/2/2022

Permit Application Status History

Submitted 11/14/2017 APPLICANT
Assigned to Plan Check Engineer 12/7/2017 ERWIN PASCUA
Corrections Issued 12/13/2017 ERWIN PASCUA
Quality Review Completed 12/15/2017 CELESTE MORRIS
Building Plans Picked Up 1/3/2018 APPLICANT
Plan Check Approved 3/21/2019 ERWIN PASCUA
Issued 1/10/2020 LADBS
OK for CofC 4/9/2020 DARRYL ARNOLD
OK for CofC 4/9/2020 DARRYL ARNOLD
CofC Issued 12/2/2022 WINSTON DUNNING

Permit Application Clearance Information

Housing rent stabilization Cleared 8/12/2019 ISMAEL HERNANDEZ

Contact Information

Architect Mebasser,, John A; Lic. No.: C19055 2525 PEARL STREET      SANTA MONICA, CA 90405
Contractor Zdx Industries Inc; Lic. No.: 720893-B 1640 5TH ST #216      SANTA MONICA, CA 90401
Engineer Mansouri,, Ali; Lic. No.: C42533 1640 5TH STREET SUITE 216      SANTA MONICA, CA 90401

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/21/2020 Approved DARRYL ARNOLD
Footing/Foundation/Slab 1/23/2020 Approved DARRYL ARNOLD
Footing/Foundation/Slab 1/30/2020 Approved BRUCE CAMPBELL
Deputy Steel/Welding 2/7/2020 Conditional Approval BRUCE CAMPBELL
Footing/Foundation/Slab 2/7/2020 Approved BRUCE CAMPBELL
Deputy Reinf. Concrete 2/11/2020 Partial Approval DARRYL ARNOLD
Footing/Foundation/Slab 2/12/2020 Corrections Issued BRUCE CAMPBELL
Wood Frame 3/13/2020 Approved DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 3/27/2020 Not Ready for Inspection JONATHAN QUACH
Wood Frame 3/27/2020 Approved JONATHAN QUACH
Drywall Nailing 4/1/2020 Approved DARRYL ARNOLD
Drywall Nailing 4/2/2020 Approved DARRYL ARNOLD
Deputy Wood Construction 4/3/2020 Partial Approval DARRYL ARNOLD
Final 4/9/2020 OK for CofC DARRYL ARNOLD
METHANE-Final 4/9/2020 Approved DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/9/2020 SGSOV Approved DARRYL ARNOLD
Smoke Detectors 4/9/2020 Approved DARRYL ARNOLD
Special/Order Compliance 5/23/2022 Corrections Issued DARRYL ARNOLD