1508 W BAXTER ST 90026

Certificate Information: 1508 W BAXTER ST 90026

Application / Permit
17016-10000-33328
Plan Check / Job No.
B17LA20535
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL OF EXISTING SINGLE FAMILY DWELLING AND NEW STAIRS.
Permit Issued
Issued on 2/8/2018
Issuing Office
Metro
Current Status
Permit Finaled on 12/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/9/2017 APPLICANT
Assigned to Plan Check Engineer 11/20/2017 PAUL PIERRE
Corrections Issued 11/20/2017 PAUL PIERRE
Applicant returned to address corrections 12/22/2017 TROY DEGUZMAN
Plan Check Approved 1/9/2018 JOHNNY WU
Issued 2/8/2018 LADBS
Permit Finaled-Status Void 11/15/2019 AJA COLLAY
Re-Activate Permit 12/4/2025 AJA COLLAY
Permit Finaled 12/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 11/20/2017 PAUL PIERRE

Contact Information

Contractor Owner-Builder       ,
Contractor Pacific Construction & Home Improvement; Lic. No.: 970576-B 12226 VALLEY VIEW AVE      WHITTIER, CA 90604
Engineer Dinos, George Ioannis; Lic. No.: C78814 24-29 26 ST      ASTORIA, NY 11102
Engineer Mansuri, Mehran; Lic. No.: C78614 14050 MAGNOLIA BLVD 302      SHERMAN OAKS, CA 91423

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/22/2018 Not Ready for Inspection DAVID CHAN
Excavation/Setback/Form/Re-Bar 2/26/2018 Partial Approval DAVID CHAN
Deputy Reinf. Concrete 3/2/2018 Conditional Approval DAVID CHAN
Footing/Foundation/Slab 3/9/2018 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 3/12/2018 Approved DAVID CHAN
Footing/Foundation/Slab 3/13/2018 Approved DAVID CHAN
ELECTRICAL-Rough 4/20/2018 Not Ready for Inspection DAVID CHAN
HVAC-Rough 4/20/2018 Approved DAVID CHAN
PLUMBING-Rough 4/20/2018 Approved DAVID CHAN
BUILDING-Rough-Frame 4/26/2018 Partial Approval DAVID CHAN
ELECTRICAL-Rough 4/26/2018 Approved DAVID CHAN
Wood Frame 5/1/2018 Approved DAVID CHAN
Insulation 5/10/2018 Approved DAVID CHAN
Drywall Nailing 5/18/2018 Approved DAVID CHAN
Interior/Exterior Lathing 8/2/2018 Approved DAVID CHAN
Final 11/15/2019 Not Ready for Inspection AJA COLLAY
SGSOV-Seismic Gas S/O Valve 11/15/2019 SGSOV Approved AJA COLLAY
Smoke Detectors 11/15/2019 Approved AJA COLLAY