1925 1/2 N VAN NESS AVE 90068
Certificate Information: 1925 1/2 N VAN NESS AVE 90068
- Application / Permit
- 17016-10000-29078
- Plan Check / Job No.
- B17LA18081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 15'6"x15' addition to existing carriage house/garage for (N) accessory dwelling unit per AB 2299 & SB 1069.
- Permit Issued
- Issued on 10/28/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/15/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/19/2017 | TU HUA |
| Corrections Issued | 10/26/2017 | TU HUA |
| Quality Review Completed | 10/27/2017 | ALLEN MANALANSAN |
| Building Plans Picked Up | 10/31/2017 | APPLICANT |
| Applicant returned to address corrections | 2/27/2018 | TU HUA |
| Green Plans Picked Up | 2/27/2018 | APPLICANT |
| Plan Check Approved | 3/27/2019 | TU HUA |
| Issued | 10/28/2019 | LADBS |
| CofO in Progress | 7/14/2021 | BRAD BESCOS |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
| CofO Issued | 7/15/2021 | DEROLD HAUFF |
| Permit Finaled | 7/15/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/27/2018 | NAZILA NOORIFAR |
| Address approval | Cleared | 2/27/2018 | NAZILA NOORIFAR |
| Eng Process Fee Ord 176,300 | Cleared | 2/27/2018 | NAZILA NOORIFAR |
| Sewer availability | Cleared | 2/27/2018 | NAZILA NOORIFAR |
| HPOZ | Cleared | 2/26/2019 | AMANDA KAINER |
| Miscellaneous | Cleared | 2/26/2019 | AMANDA KAINER |
| Grading Pre-Inspection | Cleared | 3/26/2019 | BARTON HOLMES |
| Green Code | Cleared | 3/27/2019 | NEGAR NEJAD |
| Green Code | Cleared | 3/27/2019 | TU HUA |
| Roof/Waste drainage to street | Cleared | 3/27/2019 | ERIK BEASLEY |
Contact Information
| Contractor | Salgado Design & Construction Inc; Lic. No.: 1011670-B | 4230 CENTER STREET BALDWIN PARK, CA 91706 |
| Engineer | Rigsbee,, Ryan Karl; Lic. No.: C85450 | 12881 BROWNING AVE SANTA ANA, CA 92705 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/18/2019 | Corrections Issued | ROBERT CORNELL |
| Pre-Inspection | 11/18/2019 | Approved | ROBERT CORNELL |
| PLUMBING-Rough | 12/3/2019 | Not Ready for Inspection | BRIAN SULLIVAN |
| Underground Mechanical | 12/11/2019 | Approved | ROBERT CORNELL |
| Footing/Foundation/Slab | 1/3/2020 | Corrections Issued | RAUL BARAJAS |
| Footing/Foundation/Slab | 1/9/2020 | Not Ready for Inspection | ROBERT CORNELL |
| Special/Order Compliance | 2/6/2020 | Corrections Issued | ROBERT CORNELL |
| Footing/Foundation/Slab | 2/18/2020 | Approved | ROBERT CORNELL |
| BUILDING-Rough-Frame | 7/13/2020 | Partial Approval | BRIAN SULLIVAN |
| Green Building Rough | 7/13/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 8/18/2020 | Approved | BRIAN SULLIVAN |
| HVAC-Rough | 9/3/2020 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/3/2020 | Conditional Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/21/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/21/2020 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 9/21/2020 | Approved | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/21/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/6/2020 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/6/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 10/13/2020 | Approved | BRIAN SULLIVAN |
| Green Building Final | 10/13/2020 | Not Ready for Inspection | BRIAN SULLIVAN |
| PLUMBING-Rough | 10/13/2020 | Approved | BRIAN SULLIVAN |
| Insulation | 10/16/2020 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 11/4/2020 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 11/4/2020 | Approved | BRIAN SULLIVAN |
| Service/Power Release | 11/30/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Service/Power Release | 1/15/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 1/27/2021 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 1/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2021 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 1/27/2021 | Not Ready for Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 3/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Final | 3/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 3/4/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 3/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 3/4/2021 | Corrections Issued | JOSEPH MCGARRY |
| Smoke Detectors | 3/4/2021 | Approved | JOSEPH MCGARRY |
| Final | 3/18/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2021 | SGSOV Not Ready | BRIAN SULLIVAN |
| Final | 4/6/2021 | Not Ready for Inspection | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 4/6/2021 | SGSOV Approved | BRIAN SULLIVAN |
| Final | 5/3/2021 | Conditional Approval | BRIAN SULLIVAN |