225 S OLIVE ST 90012

Certificate Information: 225 S OLIVE ST 90012

Application / Permit
17016-10000-28027
Plan Check / Job No.
B17LA17385
Group
Building
Type
Bldg-Addition
Sub-Type
Commercial
Primary Use
(5) Apartment
Work Description
CONVERT EXISTING MECHANICAL ROOM TO REC. ROOM, TRELLIS ADDITION AND RENOVATE EXISTING ROOF DECK . NEW ELEVATOR TO CONNECT 20TH FLOOR AND ROOF DECK. RECONFIGURE AND RENOVATE PARTIAL RESID UNITS ON 19TH AND 20TH FLOOR TO ACCOMMODODATE THE NEW ELEVATOR.
Permit Issued
Issued on 4/11/2018
Issuing Office
Metro
Current Status
CofO Issued on 4/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/25/2017 APPLICANT
Assigned to Plan Check Engineer 10/12/2017 SHANGQIN XIE
Disabled Access Plans Picked Up 10/20/2017 APPLICANT
Green Plans Picked Up 10/20/2017 APPLICANT
Corrections Issued 10/24/2017 SHANGQIN XIE
Quality Review Completed 11/1/2017 ARMEN JIVALAGIAN
Building Plans Picked Up 11/7/2017 APPLICANT
Applicant returned to address corrections 12/15/2017 SHANGQIN XIE
Applicant returned to address corrections 2/7/2018 SHANGQIN XIE
Applicant returned to address corrections 2/27/2018 SHANGQIN XIE
Plan Check Approved 3/7/2018 SHANGQIN XIE
Issued 4/11/2018 LADBS
TCO Issued (Expire Date: 08-08-2021) 2/9/2021 DAVID TSAU
CofO in Progress 4/7/2021 KATY RAMIREZ
Permit Finaled 4/7/2021 DAVID TSAU
CofO Issued 4/7/2021 DAVID TSAU
Permit Finaled 4/7/2021 DAVID TSAU

Permit Application Clearance Information

"D" conditions Cleared 12/4/2017 SEAN VEAL
CPC Cleared 12/4/2017 SEAN VEAL
CPC Cleared 12/4/2017 SEAN VEAL
Eng Process Fee Ord 176,300 Cleared 12/4/2017 STEVE MELGAR
Sewer availability Cleared 12/4/2017 STEVE MELGAR
Site Plan review Cleared 12/4/2017 SEAN VEAL
ZA Case Cleared 12/4/2017 SEAN VEAL
ZA Case Cleared 12/4/2017 SEAN VEAL
ZA Case Cleared 12/4/2017 SEAN VEAL
ZI Cleared 12/4/2017 SEAN VEAL
Highway dedication Cleared 12/6/2017 RAVIL MANAPOV
Housing rent stabilization Cleared 12/6/2017 STEVEN HOFSTAD
Low Impact Development Cleared 12/6/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 12/6/2017 RAVIL MANAPOV
Specific Plan Cleared 12/6/2017 CHI DANG
Green Code Cleared 12/13/2017 NEGAR NEJAD
Fire Marshall Fire Life Safety Cleared 3/2/2018 DOMINIQUE MEDINA
DAS Clearance Cleared 3/5/2018 ELIZABETH TOMS
Building over 3-story or 36-ft Cleared 3/6/2018 CALOSHA APPROVED
GPI Written Notices Cleared 3/6/2018 SHANGQIN XIE

Contact Information

Architect Winters, Patrick Charles; Lic. No.: C22032 11410 BIONA DRIVE      LOS ANGELES, CA 90066
Contractor Prestige Homes Inc; Lic. No.: 313423-B 5150 OVERLAND AVE      CULVER CITY, CA 90230
Engineer Labib, Youhanna T; Lic. No.: S4549 209 E EL SEGUNDO BLVD      EL SEGUNDO, CA 90245

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/9/2018 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/13/2018 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 11/26/2018 Partial Approval JAMES POWERS
Excavation/Setback/Form/Re-Bar 1/10/2019 Partial Approval LARRY ARNICK
Deputy Reinf. Concrete 1/11/2019 Conditional Approval KATY RAMIREZ
Deputy Pre-Stress Concrete 1/14/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 1/14/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 1/17/2019 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 1/18/2019 Conditional Approval KATY RAMIREZ
Deputy Pre-Stress Concrete 1/18/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 1/18/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 2/15/2019 Conditional Approval DANIEL COLLINS
Excavation/Setback/Form/Re-Bar 2/19/2019 Partial Approval KATY RAMIREZ
Structural Steel Frame 2/19/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 2/20/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 2/22/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 2/25/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 2/26/2019 Conditional Approval DANIEL COLLINS
Deputy Drilled-In Anchors 3/4/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 3/4/2019 Conditional Approval DANIEL COLLINS
Light Gage Steel Frame 3/4/2019 Partial Inspection KATY RAMIREZ
Deputy Reinf. Concrete 3/5/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 3/5/2019 Conditional Approval DANIEL COLLINS
Drywall Nailing 3/5/2019 Not Ready for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 3/5/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 3/6/2019 Conditional Approval KATY RAMIREZ
Drywall Nailing 3/8/2019 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 3/28/2019 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 4/9/2019 Corrections Issued KATY RAMIREZ
Light Gage Steel Frame 4/23/2019 Partial Inspection KATY RAMIREZ
Drywall Nailing 5/2/2019 Partial Approval KATY RAMIREZ
Deputy Steel/Welding 5/6/2019 Conditional Approval KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 5/20/2019 Partial Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/22/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/23/2019 Conditional Approval KATY RAMIREZ
Deputy Reinf. Concrete 5/30/2019 Conditional Approval DANIEL COLLINS
Deputy Reinf. Concrete 6/6/2019 Approved DANIEL COLLINS
Deputy Drilled-In Anchors 6/7/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 6/18/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/25/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/27/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 6/28/2019 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 7/1/2019 Conditional Approval DANIEL COLLINS
Deputy Steel/Welding 7/2/2019 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 7/24/2019 Partial Approval DANIEL COLLINS
Deputy Drilled-In Anchors 8/2/2019 Conditional Approval DAVID TSAU
Deputy Drilled-In Anchors 8/9/2019 Conditional Approval DANIEL COLLINS
Drywall Nailing 8/9/2019 Approved HAMID PISHEHVAR
Drywall Nailing 8/21/2019 Approved HAMID PISHEHVAR
Interior/Exterior Lathing 8/23/2019 Partial Approval JOEY BUCHANAN
Deputy Drilled-In Anchors 12/9/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/10/2019 Conditional Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/11/2019 Conditional Approval KATY RAMIREZ
Light Gage Steel Frame 12/17/2019 Partial Inspection KATY RAMIREZ
Drywall Nailing 12/18/2019 Partial Approval KATY RAMIREZ
Deputy Drilled-In Anchors 12/27/2019 Conditional Approval KATY RAMIREZ
Drywall Nailing 1/7/2020 Not Ready for Inspection KATY RAMIREZ
Light Gage Steel Frame 1/7/2020 Partial Inspection KATY RAMIREZ
Drywall Nailing 1/8/2020 Partial Approval KATY RAMIREZ
Special/Order Compliance 1/31/2020 Approved KATY RAMIREZ
Deputy Steel/Welding 4/17/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 4/30/2020 Conditional Approval DANIEL COLLINS
Special/Order Compliance 5/4/2020 Approved DANIEL COLLINS
Deputy Steel/Welding 6/25/2020 Conditional Approval KATY RAMIREZ
Deputy Steel/Welding 8/18/2020 Conditional Approval KATY RAMIREZ
Final 10/27/2020 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 10/27/2020 Partial Inspection KATY RAMIREZ
Green Building Final 10/27/2020 Not Ready for Inspection KATY RAMIREZ
Green Building Rough 10/27/2020 Approved KATY RAMIREZ
Reinforced Concrete Frame 10/27/2020 Partial Inspection KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 10/27/2020 SGSOV Not Ready KATY RAMIREZ
Smoke Detectors 10/27/2020 Not Ready for Inspection KATY RAMIREZ
Verify Sprinkler Sign Off 10/27/2020 Approved KATY RAMIREZ
Final 11/5/2020 Not Ready for Inspection KATY RAMIREZ
Footing/Foundation/Slab 11/5/2020 Approved KATY RAMIREZ
Green Building Final 11/5/2020 Not Ready for Inspection KATY RAMIREZ
Reinforced Concrete Frame 11/5/2020 Approved KATY RAMIREZ
SGSOV-Seismic Gas S/O Valve 11/5/2020 SGSOV Approved KATY RAMIREZ
Smoke Detectors 11/5/2020 Partial Approval KATY RAMIREZ
Final 11/12/2020 Partial Inspection KATY RAMIREZ
Green Building Final 11/12/2020 Not Ready for Inspection KATY RAMIREZ
Smoke Detectors 11/12/2020 Approved KATY RAMIREZ
Final 12/4/2020 Off-Hour Fees Due
Green Building Final 12/4/2020 Off-Hour Fees Due
Drywall Nailing 1/7/2021 Approved EDWIN GREGORYONA
Final 2/9/2021 Partial Inspection KATY RAMIREZ
Green Building Final 2/9/2021 Approved KATY RAMIREZ
Final 3/18/2021 Conditional Approval DANIEL COLLINS
Final 4/7/2021 OK to Issue CofO KATY RAMIREZ