947 S TIVERTON AVE 90024

Certificate Information: 947 S TIVERTON AVE 90024

Application / Permit
17016-10000-27541
Plan Check / Job No.
B17LA17085
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment Hotel
Work Description
Renovation of an existing 14 story tower and underground parking to comply with Non-Ductile Concrete Ordinance. No change of use. Refer to comment field for additional clarifications.
Permit Issued
Issued on 12/21/2018
Issuing Office
Metro
Current Status
CofO Issued on 10/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/21/2017 APPLICANT
Assigned to Plan Check Engineer 9/28/2017 SUEN LIEU
Corrections Issued 10/24/2017 SUEN LIEU
Quality Review Completed 10/30/2017 BILL STUTSMAN
Building Plans Picked Up 11/7/2017 APPLICANT
Applicant returned to address corrections 11/30/2017 SUEN LIEU
Applicant returned to address corrections 12/5/2017 SUEN LIEU
Applicant returned to address corrections 1/4/2018 SUEN LIEU
Applicant returned to address corrections 1/18/2018 SUEN LIEU
Applicant returned to address corrections 1/25/2018 SUEN LIEU
Applicant returned to address corrections 1/30/2018 SUEN LIEU
Applicant returned to address corrections 2/27/2018 SUEN LIEU
Applicant returned to address corrections 3/12/2018 SUEN LIEU
Applicant returned to address corrections 6/7/2018 SUEN LIEU
Applicant returned to address corrections 6/18/2018 SUEN LIEU
Applicant returned to address corrections 7/3/2018 SUEN LIEU
Applicant returned to address corrections 7/12/2018 SUEN LIEU
Applicant returned to address corrections 7/19/2018 SUEN LIEU
Applicant returned to address corrections 7/26/2018 SUEN LIEU
Applicant returned to address corrections 7/30/2018 SUEN LIEU
Applicant returned to address corrections 8/1/2018 SUEN LIEU
Applicant returned to address corrections 8/2/2018 SUEN LIEU
Applicant returned to address corrections 8/7/2018 SUEN LIEU
Applicant returned to address corrections 8/8/2018 SUEN LIEU
Applicant returned to address corrections 8/10/2018 SUEN LIEU
Applicant returned to address corrections 8/14/2018 SUEN LIEU
Applicant returned to address corrections 9/20/2018 SUEN LIEU
Applicant returned to address corrections 9/21/2018 SUEN LIEU
Applicant returned to address corrections 9/27/2018 SUEN LIEU
Applicant returned to address corrections 10/4/2018 SUEN LIEU
Applicant returned to address corrections 10/10/2018 SUEN LIEU
Applicant returned to address corrections 10/11/2018 SUEN LIEU
Applicant returned to address corrections 10/17/2018 SUEN LIEU
Applicant returned to address corrections 10/19/2018 SUEN LIEU
Applicant returned to address corrections 11/8/2018 SUEN LIEU
Applicant returned to address corrections 11/9/2018 SUEN LIEU
Applicant returned to address corrections 12/6/2018 SUEN LIEU
Plan Check Approved 12/18/2018 SUEN LIEU
Issued 12/21/2018 LADBS
TCO Issued (Expire Date: 09-04-2021) 3/8/2021 HENRY BAGHDASSARIAN
CofO in Progress 9/29/2021 DERRICK SPENCER
Permit Finaled 10/4/2021 TED RIES
CofO Issued 10/4/2021 TED RIES
Permit Finaled 10/4/2021 TED RIES

Permit Application Clearance Information

Housing rent stabilization Cleared 10/31/2017 JAMES MCDEVITT
Stormwater Pollution Mitigatn Cleared 3/20/2018 AMMAR ELTAWIL
Abandoned oil well Cleared 6/14/2018 JOHN CONNEALLY
Abandoned oil well approval Cleared 6/14/2018 JOHN CONNEALLY
Address approval Cleared 6/14/2018 MICHAEL CASTILLO
Eng Process Fee Ord 176,300 Cleared 6/14/2018 MICHAEL CASTILLO
Specific Plan Cleared 7/31/2018 JOHNATHAN YU
Specific Plan Cleared 7/31/2018 JOHNATHAN YU
Work Adjacent to Public Way Cleared 8/1/2018 BOK GOH
Sewer availability Cleared 8/2/2018 CARLA VALLADARES
Grading Pre-Inspection Cleared 8/7/2018 PATRICK MISCHLICH
Food Service Establishment Cleared 8/9/2018 KENNETH BROWNE
Encroachment in public way Cleared 8/28/2018 KRISTEN LY
Green Code Cleared 11/6/2018 DONALD CRICHLOW
Green Code Cleared 11/6/2018 SEAN DANG
DAS Clearance Cleared 11/8/2018 SUEN LIEU
Residential hotels Cleared 11/8/2018 MARITES CUNANAN
Demo/Removal of Rental Units Cleared 12/7/2018 EMMA GARCIA
Demo/Removal of Rental Units Cleared 12/11/2018 EMMA GARCIA
"D" conditions Cleared 12/12/2018 KIT AWAKUNI
Miscellaneous Cleared 12/12/2018 KIT AWAKUNI
Miscellaneous Cleared 12/12/2018 KIT AWAKUNI
Miscellaneous Cleared 12/12/2018 KIT AWAKUNI
Miscellaneous Cleared 12/12/2018 KIT AWAKUNI
Specific Plan Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZA Case Cleared 12/12/2018 KIT AWAKUNI
ZI Cleared 12/12/2018 KIT AWAKUNI
ZI Cleared 12/12/2018 KIT AWAKUNI
Asbestos removal Cleared 12/13/2018 MENOA AGHAJANI
Fire Marshall Fire Life Safety Cleared 12/13/2018 MENOA AGHAJANI
Food establishment approval Cleared 12/18/2018 LACDHS APPROVED
Internal combustion engine Cleared 12/18/2018 SCAQMD APPROVED

Contact Information

Architect St, Amand, Daun Paul; Lic. No.: C13000 RTKL ASSOCIATES INC   333 S. HOPE ST    LOS ANGELES, CA 90071
Contractor Bernards Builders Inc; Lic. No.: 977134-B 555 FIRST STREET      SAN FERNANDO, CA 91340
Engineer Cretu,, Ion; Lic. No.: C71513 16358 FLANDERS STREET      GRANADA HILLS, CA 91344
Engineer Funk, David Lyle; Lic. No.: S5421 619 BERYL ST      REDONDO BEACH, CA 90277
Engineer Hushmand,, Behnam; Lic. No.: C44777 19 BERNAY      LAGUNA NIGUEL, CA 92677
Landscape Architect Schattinger,, Mark Alan; Lic. No.: LA3235 511 30TH STREET      NEWPORT BEACH, CA 92663

Inspector Information

DERRICK SPENCER, (310) 914-3919 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/4/2019 Approved DERRICK SPENCER
Pre-Inspection 1/4/2019 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 1/23/2019 Partial Approval SORIN CIRSTOIU
Drywall Nailing 1/24/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/14/2019 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 2/20/2019 Approved DERRICK SPENCER
Green Building Rough 2/20/2019 Not Ready for Inspection DERRICK SPENCER
Pre-Inspection 2/20/2019 Approved DERRICK SPENCER
Reinforced Concrete Frame 2/20/2019 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 3/11/2019 Partial Approval SORIN CIRSTOIU
Green Building Rough 3/11/2019 Partial Inspection SORIN CIRSTOIU
Reinforced Concrete Frame 3/11/2019 Partial Approval SORIN CIRSTOIU
Deputy Drilled-In Anchors 3/12/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/12/2019 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/13/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/14/2019 Conditional Approval SORIN CIRSTOIU
Deputy Shotcrete 3/14/2019 Conditional Approval SORIN CIRSTOIU
Deputy Reinf. Concrete 3/15/2019 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/15/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/18/2019 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/18/2019 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 3/18/2019 Not Ready for Inspection DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 3/18/2019 Not Ready for Inspection DERRICK SPENCER
Deputy Reinf. Concrete 3/19/2019 Approved DERRICK SPENCER
Deputy Shotcrete 3/19/2019 Approved DERRICK SPENCER
Deputy Shotcrete 3/19/2019 Approved SORIN CIRSTOIU
Excavation/Setback/Form/Re-Bar 3/19/2019 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 3/19/2019 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 3/20/2019 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/20/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/21/2019 Approved SORIN CIRSTOIU
Deputy Reinf. Concrete 3/22/2019 Approved SORIN CIRSTOIU
Deputy Shotcrete 3/22/2019 Approved DERRICK SPENCER
Deputy Reinf. Concrete 3/28/2019 Approved DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 3/29/2019 Partial Approval DERRICK SPENCER
Green Building Rough 3/29/2019 Not Ready for Inspection DERRICK SPENCER
Reinforced Concrete Frame 3/29/2019 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 4/8/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/8/2019 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 4/8/2019 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/9/2019 Partial Approval DERRICK SPENCER
Floor/Roof Diaphrgm/Shear Wall 4/9/2019 Not Ready for Inspection DERRICK SPENCER
Deputy Reinf. Concrete 4/10/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/11/2019 Approved SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 4/11/2019 Approved SORIN CIRSTOIU
Light Gage Steel Frame 4/18/2019 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 4/22/2019 Partial Approval DERRICK SPENCER
Wall Anchors 4/22/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/25/2019 Partial Approval DERRICK SPENCER
Drywall Nailing 4/26/2019 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 4/30/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 5/10/2019 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 5/16/2019 Approved SORIN CIRSTOIU
Reinforced Masonry Frame 5/16/2019 Approved SORIN CIRSTOIU
Insulation 5/24/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 5/24/2019 Partial Approval DERRICK SPENCER
Insulation 5/28/2019 Partial Approval DERRICK SPENCER
Insulation 5/29/2019 Partial Approval DERRICK SPENCER
Masonry Wall/Backfill 6/13/2019 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 6/17/2019 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 7/1/2019 Approved DERRICK SPENCER
Interior/Exterior Lathing 7/5/2019 Partial Approval DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 7/19/2019 Partial Approval SORIN CIRSTOIU
Light Gage Steel Frame 7/19/2019 Partial Approval SORIN CIRSTOIU
Insulation 7/26/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 8/1/2019 Approved DERRICK SPENCER
Light Gage Steel Frame 8/14/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 8/21/2019 Partial Approval DERRICK SPENCER
Insulation 9/3/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/3/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/5/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/23/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 10/7/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 10/8/2019 Partial Approval DERRICK SPENCER
Insulation 10/9/2019 Partial Approval DERRICK SPENCER
Deputy Drilled-In Anchors 10/10/2019 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 10/18/2019 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 10/30/2019 Partial Approval DERRICK SPENCER
Insulation 10/30/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 10/30/2019 Partial Approval DERRICK SPENCER
Insulation 10/31/2019 Partial Approval DERRICK SPENCER
Deputy Steel/Welding 11/1/2019 Approved DERRICK SPENCER
Deputy Drilled-In Anchors 11/4/2019 Approved DERRICK SPENCER
Drywall Nailing 12/17/2019 Partial Approval DERRICK SPENCER
Insulation 12/17/2019 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 12/17/2019 Partial Approval DERRICK SPENCER
Drywall Nailing 1/31/2020 Partial Approval DERRICK SPENCER
Insulation 1/31/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 1/31/2020 Partial Approval DERRICK SPENCER
Drywall Nailing 2/11/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 2/11/2020 Partial Approval DERRICK SPENCER
Deputy Reinf. Concrete 2/24/2020 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 2/25/2020 Partial Approval DERRICK SPENCER
Insulation 3/5/2020 Partial Approval DERRICK SPENCER
Interior/Exterior Lathing 3/5/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 3/5/2020 Partial Approval DERRICK SPENCER
Insulation 3/9/2020 Partial Approval DERRICK SPENCER
Insulation 4/3/2020 Approved DERRICK SPENCER
Light Gage Steel Frame 4/3/2020 Partial Approval DERRICK SPENCER
Wood Frame 4/6/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 4/7/2020 Partial Approval DERRICK SPENCER
SWPPP-Const. Storm Water 4/8/2020 Completed DERRICK SPENCER
Interior/Exterior Lathing 4/10/2020 Partial Approval DERRICK SPENCER
Wood Frame 6/11/2020 Partial Approval DERRICK SPENCER
Green Building Rough 6/23/2020 Approved DERRICK SPENCER
Reinforced Concrete Frame 6/23/2020 Approved DERRICK SPENCER
T-Bar Ceiling 7/29/2020 Partial Approval DERRICK SPENCER
Light Gage Steel Frame 9/9/2020 Partial Approval DERRICK SPENCER
Green Building Final 9/23/2020 Not Ready for Inspection DERRICK SPENCER
Interior/Exterior Lathing 9/23/2020 Approved DERRICK SPENCER
Light Gage Steel Frame 9/23/2020 Approved DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 9/23/2020 SGSOV Approved DERRICK SPENCER
Smoke Detectors 9/23/2020 Approved DERRICK SPENCER
Light Gage Steel Frame 10/30/2020 Approved DERRICK SPENCER
Special/Order Compliance 11/23/2020 Approved DERRICK SPENCER
Final 12/7/2020 Not Ready for Inspection DERRICK SPENCER
Green Building Final 12/7/2020 Not Ready for Inspection DERRICK SPENCER
Light Gage Steel Frame 12/7/2020 Approved DERRICK SPENCER
Final 2/11/2021 Not Ready for Inspection DERRICK SPENCER
Green Building Final 2/11/2021 Approved DERRICK SPENCER
Special/Order Compliance 2/11/2021 Approved DERRICK SPENCER
Final 2/18/2021 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 2/18/2021 Not Ready for Inspection DERRICK SPENCER
Final 3/4/2021 Not Ready for Inspection DERRICK SPENCER
Special/Order Compliance 4/15/2021 Approved DERRICK SPENCER
Special/Order Compliance 8/11/2021 Approved DERRICK SPENCER
Final 9/22/2021 OK to Issue CofO DERRICK SPENCER