947 S TIVERTON AVE 90024
Certificate Information: 947 S TIVERTON AVE 90024
- Application / Permit
- 17016-10000-27541
- Plan Check / Job No.
- B17LA17085
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment Hotel
- Work Description
- Renovation of an existing 14 story tower and underground parking to comply with Non-Ductile Concrete Ordinance. No change of use. Refer to comment field for additional clarifications.
- Permit Issued
- Issued on 12/21/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/28/2017 | SUEN LIEU |
| Corrections Issued | 10/24/2017 | SUEN LIEU |
| Quality Review Completed | 10/30/2017 | BILL STUTSMAN |
| Building Plans Picked Up | 11/7/2017 | APPLICANT |
| Applicant returned to address corrections | 11/30/2017 | SUEN LIEU |
| Applicant returned to address corrections | 12/5/2017 | SUEN LIEU |
| Applicant returned to address corrections | 1/4/2018 | SUEN LIEU |
| Applicant returned to address corrections | 1/18/2018 | SUEN LIEU |
| Applicant returned to address corrections | 1/25/2018 | SUEN LIEU |
| Applicant returned to address corrections | 1/30/2018 | SUEN LIEU |
| Applicant returned to address corrections | 2/27/2018 | SUEN LIEU |
| Applicant returned to address corrections | 3/12/2018 | SUEN LIEU |
| Applicant returned to address corrections | 6/7/2018 | SUEN LIEU |
| Applicant returned to address corrections | 6/18/2018 | SUEN LIEU |
| Applicant returned to address corrections | 7/3/2018 | SUEN LIEU |
| Applicant returned to address corrections | 7/12/2018 | SUEN LIEU |
| Applicant returned to address corrections | 7/19/2018 | SUEN LIEU |
| Applicant returned to address corrections | 7/26/2018 | SUEN LIEU |
| Applicant returned to address corrections | 7/30/2018 | SUEN LIEU |
| Applicant returned to address corrections | 8/1/2018 | SUEN LIEU |
| Applicant returned to address corrections | 8/2/2018 | SUEN LIEU |
| Applicant returned to address corrections | 8/7/2018 | SUEN LIEU |
| Applicant returned to address corrections | 8/8/2018 | SUEN LIEU |
| Applicant returned to address corrections | 8/10/2018 | SUEN LIEU |
| Applicant returned to address corrections | 8/14/2018 | SUEN LIEU |
| Applicant returned to address corrections | 9/20/2018 | SUEN LIEU |
| Applicant returned to address corrections | 9/21/2018 | SUEN LIEU |
| Applicant returned to address corrections | 9/27/2018 | SUEN LIEU |
| Applicant returned to address corrections | 10/4/2018 | SUEN LIEU |
| Applicant returned to address corrections | 10/10/2018 | SUEN LIEU |
| Applicant returned to address corrections | 10/11/2018 | SUEN LIEU |
| Applicant returned to address corrections | 10/17/2018 | SUEN LIEU |
| Applicant returned to address corrections | 10/19/2018 | SUEN LIEU |
| Applicant returned to address corrections | 11/8/2018 | SUEN LIEU |
| Applicant returned to address corrections | 11/9/2018 | SUEN LIEU |
| Applicant returned to address corrections | 12/6/2018 | SUEN LIEU |
| Plan Check Approved | 12/18/2018 | SUEN LIEU |
| Issued | 12/21/2018 | LADBS |
| TCO Issued (Expire Date: 09-04-2021) | 3/8/2021 | HENRY BAGHDASSARIAN |
| CofO in Progress | 9/29/2021 | DERRICK SPENCER |
| Permit Finaled | 10/4/2021 | TED RIES |
| CofO Issued | 10/4/2021 | TED RIES |
| Permit Finaled | 10/4/2021 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 10/31/2017 | JAMES MCDEVITT |
| Stormwater Pollution Mitigatn | Cleared | 3/20/2018 | AMMAR ELTAWIL |
| Abandoned oil well | Cleared | 6/14/2018 | JOHN CONNEALLY |
| Abandoned oil well approval | Cleared | 6/14/2018 | JOHN CONNEALLY |
| Address approval | Cleared | 6/14/2018 | MICHAEL CASTILLO |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2018 | MICHAEL CASTILLO |
| Specific Plan | Cleared | 7/31/2018 | JOHNATHAN YU |
| Specific Plan | Cleared | 7/31/2018 | JOHNATHAN YU |
| Work Adjacent to Public Way | Cleared | 8/1/2018 | BOK GOH |
| Sewer availability | Cleared | 8/2/2018 | CARLA VALLADARES |
| Grading Pre-Inspection | Cleared | 8/7/2018 | PATRICK MISCHLICH |
| Food Service Establishment | Cleared | 8/9/2018 | KENNETH BROWNE |
| Encroachment in public way | Cleared | 8/28/2018 | KRISTEN LY |
| Green Code | Cleared | 11/6/2018 | DONALD CRICHLOW |
| Green Code | Cleared | 11/6/2018 | SEAN DANG |
| DAS Clearance | Cleared | 11/8/2018 | SUEN LIEU |
| Residential hotels | Cleared | 11/8/2018 | MARITES CUNANAN |
| Demo/Removal of Rental Units | Cleared | 12/7/2018 | EMMA GARCIA |
| Demo/Removal of Rental Units | Cleared | 12/11/2018 | EMMA GARCIA |
| "D" conditions | Cleared | 12/12/2018 | KIT AWAKUNI |
| Miscellaneous | Cleared | 12/12/2018 | KIT AWAKUNI |
| Miscellaneous | Cleared | 12/12/2018 | KIT AWAKUNI |
| Miscellaneous | Cleared | 12/12/2018 | KIT AWAKUNI |
| Miscellaneous | Cleared | 12/12/2018 | KIT AWAKUNI |
| Specific Plan | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZA Case | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZI | Cleared | 12/12/2018 | KIT AWAKUNI |
| ZI | Cleared | 12/12/2018 | KIT AWAKUNI |
| Asbestos removal | Cleared | 12/13/2018 | MENOA AGHAJANI |
| Fire Marshall Fire Life Safety | Cleared | 12/13/2018 | MENOA AGHAJANI |
| Food establishment approval | Cleared | 12/18/2018 | LACDHS APPROVED |
| Internal combustion engine | Cleared | 12/18/2018 | SCAQMD APPROVED |
Contact Information
| Architect | St, Amand, Daun Paul; Lic. No.: C13000 | RTKL ASSOCIATES INC 333 S. HOPE ST LOS ANGELES, CA 90071 |
| Contractor | Bernards Builders Inc; Lic. No.: 977134-B | 555 FIRST STREET SAN FERNANDO, CA 91340 |
| Engineer | Cretu,, Ion; Lic. No.: C71513 | 16358 FLANDERS STREET GRANADA HILLS, CA 91344 |
| Engineer | Funk, David Lyle; Lic. No.: S5421 | 619 BERYL ST REDONDO BEACH, CA 90277 |
| Engineer | Hushmand,, Behnam; Lic. No.: C44777 | 19 BERNAY LAGUNA NIGUEL, CA 92677 |
| Landscape Architect | Schattinger,, Mark Alan; Lic. No.: LA3235 | 511 30TH STREET NEWPORT BEACH, CA 92663 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2019 | Approved | DERRICK SPENCER |
| Pre-Inspection | 1/4/2019 | Partial Inspection | SORIN CIRSTOIU |
| Drywall Nailing | 1/23/2019 | Partial Approval | SORIN CIRSTOIU |
| Drywall Nailing | 1/24/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 2/14/2019 | Partial Approval | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 2/20/2019 | Approved | DERRICK SPENCER |
| Green Building Rough | 2/20/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Pre-Inspection | 2/20/2019 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 2/20/2019 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 3/11/2019 | Partial Approval | SORIN CIRSTOIU |
| Green Building Rough | 3/11/2019 | Partial Inspection | SORIN CIRSTOIU |
| Reinforced Concrete Frame | 3/11/2019 | Partial Approval | SORIN CIRSTOIU |
| Deputy Drilled-In Anchors | 3/12/2019 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 3/12/2019 | Approved | SORIN CIRSTOIU |
| Deputy Shotcrete | 3/13/2019 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 3/14/2019 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Shotcrete | 3/14/2019 | Conditional Approval | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 3/15/2019 | Approved | SORIN CIRSTOIU |
| Deputy Shotcrete | 3/15/2019 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 3/18/2019 | Approved | SORIN CIRSTOIU |
| Deputy Shotcrete | 3/18/2019 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 3/18/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/19/2019 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 3/19/2019 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 3/19/2019 | Approved | SORIN CIRSTOIU |
| Excavation/Setback/Form/Re-Bar | 3/19/2019 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2019 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/20/2019 | Approved | SORIN CIRSTOIU |
| Deputy Shotcrete | 3/20/2019 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 3/21/2019 | Approved | SORIN CIRSTOIU |
| Deputy Reinf. Concrete | 3/22/2019 | Approved | SORIN CIRSTOIU |
| Deputy Shotcrete | 3/22/2019 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 3/28/2019 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2019 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 3/29/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Reinforced Concrete Frame | 3/29/2019 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/8/2019 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 4/8/2019 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2019 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 4/9/2019 | Partial Approval | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 4/9/2019 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Reinf. Concrete | 4/10/2019 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 4/11/2019 | Approved | SORIN CIRSTOIU |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2019 | Approved | SORIN CIRSTOIU |
| Light Gage Steel Frame | 4/18/2019 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 4/22/2019 | Partial Approval | DERRICK SPENCER |
| Wall Anchors | 4/22/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 4/25/2019 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 4/26/2019 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 4/30/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 5/10/2019 | Partial Approval | DERRICK SPENCER |
| Masonry Wall/Backfill | 5/16/2019 | Approved | SORIN CIRSTOIU |
| Reinforced Masonry Frame | 5/16/2019 | Approved | SORIN CIRSTOIU |
| Insulation | 5/24/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 5/24/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 5/28/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 5/29/2019 | Partial Approval | DERRICK SPENCER |
| Masonry Wall/Backfill | 6/13/2019 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 6/17/2019 | Partial Approval | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 7/1/2019 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 7/5/2019 | Partial Approval | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 7/19/2019 | Partial Approval | SORIN CIRSTOIU |
| Light Gage Steel Frame | 7/19/2019 | Partial Approval | SORIN CIRSTOIU |
| Insulation | 7/26/2019 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 8/1/2019 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 8/14/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 8/21/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 9/3/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 9/3/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 9/5/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 9/23/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 10/7/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 10/8/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 10/9/2019 | Partial Approval | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 10/10/2019 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 10/18/2019 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 10/30/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 10/30/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 10/30/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 10/31/2019 | Partial Approval | DERRICK SPENCER |
| Deputy Steel/Welding | 11/1/2019 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 11/4/2019 | Approved | DERRICK SPENCER |
| Drywall Nailing | 12/17/2019 | Partial Approval | DERRICK SPENCER |
| Insulation | 12/17/2019 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 12/17/2019 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 1/31/2020 | Partial Approval | DERRICK SPENCER |
| Insulation | 1/31/2020 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 1/31/2020 | Partial Approval | DERRICK SPENCER |
| Drywall Nailing | 2/11/2020 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 2/11/2020 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 2/24/2020 | Approved | DERRICK SPENCER |
| Excavation/Setback/Form/Re-Bar | 2/25/2020 | Partial Approval | DERRICK SPENCER |
| Insulation | 3/5/2020 | Partial Approval | DERRICK SPENCER |
| Interior/Exterior Lathing | 3/5/2020 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 3/5/2020 | Partial Approval | DERRICK SPENCER |
| Insulation | 3/9/2020 | Partial Approval | DERRICK SPENCER |
| Insulation | 4/3/2020 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 4/3/2020 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 4/6/2020 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 4/7/2020 | Partial Approval | DERRICK SPENCER |
| SWPPP-Const. Storm Water | 4/8/2020 | Completed | DERRICK SPENCER |
| Interior/Exterior Lathing | 4/10/2020 | Partial Approval | DERRICK SPENCER |
| Wood Frame | 6/11/2020 | Partial Approval | DERRICK SPENCER |
| Green Building Rough | 6/23/2020 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 6/23/2020 | Approved | DERRICK SPENCER |
| T-Bar Ceiling | 7/29/2020 | Partial Approval | DERRICK SPENCER |
| Light Gage Steel Frame | 9/9/2020 | Partial Approval | DERRICK SPENCER |
| Green Building Final | 9/23/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Interior/Exterior Lathing | 9/23/2020 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 9/23/2020 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 9/23/2020 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 9/23/2020 | Approved | DERRICK SPENCER |
| Light Gage Steel Frame | 10/30/2020 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 11/23/2020 | Approved | DERRICK SPENCER |
| Final | 12/7/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 12/7/2020 | Not Ready for Inspection | DERRICK SPENCER |
| Light Gage Steel Frame | 12/7/2020 | Approved | DERRICK SPENCER |
| Final | 2/11/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 2/11/2021 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 2/11/2021 | Approved | DERRICK SPENCER |
| Final | 2/18/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Special/Order Compliance | 2/18/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 3/4/2021 | Not Ready for Inspection | DERRICK SPENCER |
| Special/Order Compliance | 4/15/2021 | Approved | DERRICK SPENCER |
| Special/Order Compliance | 8/11/2021 | Approved | DERRICK SPENCER |
| Final | 9/22/2021 | OK to Issue CofO | DERRICK SPENCER |