715-717 N VIRGIL AVE 90029
Certificate Information: 715-717 N VIRGIL AVE 90029
- Application / Permit
- 17016-10000-26473
- Plan Check / Job No.
- B17LA16407
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Bakery
- Work Description
- CHANGE OF USE (39' X 45') PORTION FROM RETAIL TO BAKERY/CAFE. Remove bearing wall and add new beam. Remove one parking space to provide an Accessible parking space. Subject to DIR 2018-232-SPP
- Permit Issued
- Issued on 4/20/2018
- Issuing Office
- Metro
- Current Status
- Issued on 4/20/2018
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/12/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/12/2017 | MICHAEL LOPEZ |
| Corrections Issued | 9/12/2017 | MICHAEL LOPEZ |
| Plan Check Approved | 4/20/2018 | JESSE JIMENEZ |
| Issued | 4/20/2018 | LADBS |
| Refund Closed | 8/6/2020 | MARY SUM |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2017 | FATIMA GUERRA |
| Sewer availability | Cleared | 9/12/2017 | FATIMA GUERRA |
| ZI | Cleared | 9/12/2017 | DANALYNN DOMINGUEZ |
| Food Service Establishment | Cleared | 4/12/2018 | KENNETH BROWNE |
| "D" conditions | Cleared | 4/20/2018 | FIPE LEILUA |
| Food establishment approval | Cleared | 4/20/2018 | LACDHS APPROVED |
| Grading Pre-Inspection | Cleared | 4/20/2018 | BARTON HOLMES |
| Specific Plan | Cleared | 4/20/2018 | FIPE LEILUA |
| Hold | Cleared | 3/18/2021 | MARY SUM |
| Hold | Cleared | 4/21/2021 | MARY SUM |
| Hold | Cleared | 4/21/2021 | SELENIA GARCIA |
Contact Information
| Contractor | Hinman Daniel; Lic. No.: 982457-B | 4544 1/2 WILLOW BROOK AVE LOS ANGELES, CA 90029 |
| Engineer | Gorbin, James D; Lic. No.: S5859 | 210 S JUANITA AVE A REDONDO BEACH, CA 90277 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/1/2018 | Partial Inspection | EDWIN GREGORYONA |
| Footing/Foundation/Slab | 5/3/2018 | Approved | EDWIN GREGORYONA |
| Deputy Steel/Welding | 6/26/2018 | Partial Approval | EDWIN GREGORYONA |
| Drywall Nailing | 8/8/2018 | Partial Approval | EDWIN GREGORYONA |
| Light Gage Steel Frame | 8/8/2018 | Partial Inspection | EDWIN GREGORYONA |
| Drywall Nailing | 9/26/2018 | Approved | CHARLENE BUSTAMANTE |
| Footing/Foundation/Slab | 9/26/2019 | Approved | JAMES POWERS |
| Light Gage Steel Frame | 9/26/2019 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/9/2019 | Approved | EDWIN GREGORYONA |
| Interior/Exterior Lathing | 10/31/2019 | Approved | EDWIN GREGORYONA |
| Light Gage Steel Frame | 10/31/2019 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 8/3/2020 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 1/5/2021 | Approved | EDWIN GREGORYONA |
| Final | 1/21/2021 | Partial Inspection | EDWIN GREGORYONA |
| SGSOV-Seismic Gas S/O Valve | 1/21/2021 | SGSOV Not Ready | EDWIN GREGORYONA |
| Smoke Detectors | 1/21/2021 | Approved | EDWIN GREGORYONA |
| Wood Frame | 1/21/2021 | Approved | EDWIN GREGORYONA |
| Pre-Inspection | 3/30/2021 | Partial Inspection | EDWIN GREGORYONA |