1933 N BEACHWOOD DR 90068
Certificate Information: 1933 N BEACHWOOD DR 90068
- Application / Permit
- 17016-10000-25812
- Plan Check / Job No.
- B17LA16422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIV. 93: INSTALL NEW CANTILEVER COLUMNS, MOMENT FRAME, AND PLYWOOD SHEAR WALL.
- Permit Issued
- Issued on 1/21/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 2/10/2021
Permit Application Status History
| Submitted | 9/12/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 9/21/2017 | MANUEL MONTUFAR |
| Corrections Issued | 9/29/2017 | MANUEL MONTUFAR |
| Quality Review Completed | 9/29/2017 | CELESTE MORRIS |
| Plan Check Approved | 10/17/2017 | MANUEL MONTUFAR |
| Issued | 1/21/2020 | LADBS |
| OK for CofC | 2/9/2021 | JONATHAN QUACH |
| CofC Issued | 2/10/2021 | ERNESTO CORRAL |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 1/15/2020 | STEVEN HOFSTAD |
Contact Information
| Contractor | Henry Rob Construction; Lic. No.: 520770-B | 23655 WILDWOOD CANYON ROAD NEWHALL, CA 91321 |
| Engineer | O'Brien, Michael Ernster; Lic. No.: S4468 | 27 ORCHARD 200 LAKE FOREST, CA 92630 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2020 | Approved | FELIX CEBALLOS |
| Deputy Drilled-In Anchors | 6/11/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Steel/Welding | 6/11/2020 | Partial Approval | FELIX CEBALLOS |
| Deputy Reinf. Concrete | 8/6/2020 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 8/10/2020 | Corrections Issued | VAHE KELEDJIAN |
| Structural Steel Frame | 8/10/2020 | Not Ready for Inspection | VAHE KELEDJIAN |
| Excavation/Setback/Form/Re-Bar | 8/27/2020 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 8/27/2020 | Conditional Approval | MARK FERRARI |
| Deputy Reinf. Concrete | 10/5/2020 | Conditional Approval | FRED WOHLFARTH |
| Wood Frame | 10/19/2020 | Partial Approval | EDWIN GREGORYONA |
| Deputy Wood Construction | 10/27/2020 | Conditional Approval | MARK FERRARI |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2020 | Approved | JONATHAN QUACH |
| Interior/Exterior Lathing | 12/3/2020 | Partial Approval | JONATHAN QUACH |
| Final | 1/29/2021 | Partial Inspection | JONATHAN QUACH |
| SGSOV-Seismic Gas S/O Valve | 1/29/2021 | SGSOV Approved | JONATHAN QUACH |
| Smoke Detectors | 1/29/2021 | Approved | JONATHAN QUACH |
| Final | 2/9/2021 | OK for CofC | JONATHAN QUACH |