3930 S ROXANNE AVE 90008

Certificate Information: 3930 S ROXANNE AVE 90008

Application / Permit
17016-10000-24130
Plan Check / Job No.
B17LA15002
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 1 ORDINARY MOMENT FRAME SYSTEMS (OMF) WITH CONCRETE TIE BEAM AT REAR (EAST). INSTALLATION OF WOOD SHEAR WALLS AT NORTH SIDE. WORKS ARE AT REAR TUCK-UNDER PARKING AREA AND EXTERIOR SIDE OF WALL AT NORTH SIDE NOT ON TENANTS' UNITS.
Permit Issued
Issued on 8/11/2020
Issuing Office
Current Status
CofC Issued on 3/5/2021

Permit Application Status History

Submitted 8/21/2017 APPLICANT
Assigned to Plan Check Engineer 9/7/2017 ERWIN PASCUA
Corrections Issued 9/18/2017 ERWIN PASCUA
Quality Review Completed 9/27/2017 CELESTE MORRIS
Building Plans Picked Up 10/2/2017 APPLICANT
Plan Check Approved 11/9/2017 ERWIN PASCUA
Issued 8/11/2020 APPLICANT
OK for CofC 3/1/2021 MARK FERRARI
CofC Issued 3/5/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 8/3/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer , ; Lic. No.: C82891 23022 SAMUEL ST   APT 36    TORRANCE, CA 90505

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/4/2020 Corrections Issued DARRYL ARNOLD
Deputy Other (see comments) 10/22/2020 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 10/22/2020 Conditional Approval DARRYL ARNOLD
Deputy Reinf. Concrete 10/26/2020 Conditional Approval MARK FERRARI
Interior/Exterior Lathing 12/3/2020 Conditional Approval DARRYL ARNOLD
Final 1/11/2021 Not Ready for Inspection DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 1/11/2021 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 1/11/2021 Conditional Approval DARRYL ARNOLD
Final 2/2/2021 Conditional Approval JONATHAN QUACH
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Approved JONATHAN QUACH
Smoke Detectors 2/2/2021 Approved JONATHAN QUACH
Final 2/23/2021 Corrections Issued MARK FERRARI
Final 3/1/2021 OK for CofC MARK FERRARI