7315 N INDEPENDENCE AVE 91303

Certificate Information: 7315 N INDEPENDENCE AVE 91303

Application / Permit
17016-10000-19682
Plan Check / Job No.
B17LA12633
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LAMC DIV 93. INSTALL (N) SCCS.
Permit Issued
Issued on 5/28/2020
Issuing Office
Current Status
CofC Issued on 4/14/2021

Permit Application Status History

Submitted 7/18/2017 APPLICANT
Assigned to Plan Check Engineer 7/27/2017 VARAND SARKISIAN
Corrections Issued 7/30/2017 VARAND SARKISIAN
Re-Submittal Required 7/31/2017 CATHERINE NUEZCA GABA
Re-Submitted 7/19/2018 VARAND SARKISIAN
Corrections Issued 2 7/19/2018 VARAND SARKISIAN
Submitted for Second Quality Review 7/19/2018 VARAND SARKISIAN
Quality Review Completed 7/19/2018 CELESTE MORRIS
Plan Check Approved 7/19/2018 VARAND SARKISIAN
No Progress 3/2/2020 VARAND SARKISIAN
Plan Check Approved 4/8/2020 VARAND SARKISIAN
Building Plans Picked Up 4/9/2020 APPLICANT
Issued 5/28/2020 APPLICANT
OK for CofC 3/15/2021 FRED WOHLFARTH
CofC Issued 4/14/2021 DAVID TSAU

Permit Application Clearance Information

Housing rent stabilization Cleared 4/23/2020 ISMAEL HERNANDEZ

Contact Information

Contractor Helmandi Roshawn; Lic. No.: 1043209-B 8728 ZELZAH AVE      NORTHRIDGE, CA 91325
Engineer Ebrahimian, Dehaghani, Mahdi; Lic. No.: C86987 8730 COSTA VERDE BLVD APT 2348      SAN DIEGO, CA 92122

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2020 No Access for Inspection DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 8/31/2020 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 8/31/2020 Not Ready for Inspection DANIEL VARNUM
Pre-Inspection 8/31/2020 Partial Approval DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 9/8/2020 SGSOV Not Ready DANIEL VARNUM
Structural Steel Frame 9/8/2020 Conditional Approval DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/9/2020 No Access for Inspection DANIEL VARNUM
Footing/Foundation/Slab 9/9/2020 No Access for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 9/14/2020 SGSOV Not Ready DANIEL VARNUM
Excavation/Setback/Form/Re-Bar 9/15/2020 Approved DANIEL VARNUM
Footing/Foundation/Slab 9/15/2020 Approved DANIEL VARNUM
Wood Frame 9/15/2020 Approved DANIEL VARNUM
Interior/Exterior Lathing 9/25/2020 Approved DANIEL VARNUM
Final 10/8/2020 Partial Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 10/8/2020 SGSOV Approved DANIEL VARNUM
Smoke Detectors 10/8/2020 Approved DANIEL VARNUM
Final 3/15/2021 OK for CofC FRED WOHLFARTH