253 S HOBART BLVD 90004
Certificate Information: 253 S HOBART BLVD 90004
- Application / Permit
- 17016-10000-16240
- Plan Check / Job No.
- B17LA10432
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story retrofit of the tuck under regions of an apartment building per LAMC Div 93 using steel moment frame
- Permit Issued
- Issued on 8/31/2021
- Issuing Office
- Current Status
- CofC Issued on 5/9/2025
Permit Application Status History
| Submitted | 6/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2017 | MANUEL MONTUFAR |
| Corrections Issued | 6/27/2017 | MANUEL MONTUFAR |
| Quality Review Completed | 6/27/2017 | CATHERINE NUEZCA GABA |
| Applicant returned to address corrections | 7/19/2017 | MANUEL MONTUFAR |
| Plan Check Approved | 7/21/2017 | MANUEL MONTUFAR |
| Issued | 8/31/2021 | APPLICANT |
| OK for CofC | 3/24/2023 | VAHE KELEDJIAN |
| CofC Issued | 5/9/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 8/19/2021 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Cal - Quake Construction Inc; Lic. No.: 759817-B | 636 NORTH FORMOSA AVENUE LOS ANGELES, CA 90036 |
| Engineer | Tanikella, Narasimha Dikshit Pras; Lic. No.: C81660 | 199 S MADISON AVE 6 PASADENA, CA 91101 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/5/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Steel/Welding | 4/15/2022 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 4/26/2022 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 4/29/2022 | Conditional Approval | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 5/10/2022 | Approved | BRUCE CAMPBELL |
| Structural Steel Frame | 6/24/2022 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/24/2022 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 10/24/2022 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 12/9/2022 | Conditional Approval | VAHE KELEDJIAN |
| Final | 1/23/2023 | Corrections Issued | VAHE KELEDJIAN |
| SGSOV-Seismic Gas S/O Valve | 1/23/2023 | SGSOV Approved | VAHE KELEDJIAN |
| Smoke Detectors | 1/23/2023 | Approved | VAHE KELEDJIAN |
| Final | 3/24/2023 | OK for CofC | VAHE KELEDJIAN |