6624 W MOORE DR 90048

Certificate Information: 6624 W MOORE DR 90048

Application / Permit
17016-10000-15518
Plan Check / Job No.
B17LA09951
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 30'1"x21'10" garage to accessory dwelling unit per GCS 65852.2(e)(1)(A) by adding partitions. No change in building footprint. See comments.
Permit Issued
Issued on 6/8/2021
Issuing Office
Current Status
CofO Issued on 10/6/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/9/2017 APPLICANT
Assigned to Plan Check Engineer 6/9/2017 TU HUA
Corrections Issued 6/9/2017 TU HUA
Plan Check Approved 5/11/2021 RAHEL BEYENE
Issued 6/8/2021 APPLICANT
Building Plans Picked Up 6/10/2021 APPLICANT
CofO in Progress 12/8/2021 ARTHUR SARGSYAN
CofO in Progress 12/8/2021 ARTHUR SARGSYAN
Permit Finaled 10/6/2022 DEROLD HAUFF
CofO Issued 10/6/2022 DEROLD HAUFF
Permit Finaled 10/6/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/20/2017 ADRIAN SANCHEZ
Address approval Cleared 6/20/2017 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 6/20/2017 ADRIAN SANCHEZ
Sewer availability Cleared 6/20/2017 ADRIAN SANCHEZ
HPOZ Cleared 10/28/2020 JONATHAN KAPLAN
ZI Cleared 10/28/2020 JONATHAN KAPLAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/20/2021 Partial Approval JOSEPH MCGARRY
Pre-Inspection 10/18/2021 Partial Inspection ARTHUR SARGSYAN
Footing/Foundation/Slab 11/9/2021 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 11/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
Drywall Nailing 11/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
ELECTRICAL-Rough 11/18/2021 Approved ARTHUR SARGSYAN
METHANE-Final 11/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
METHANE-Rough 11/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 11/18/2021 SGSOV Not Ready ARTHUR SARGSYAN
Smoke Detectors 11/18/2021 Not Ready for Inspection ARTHUR SARGSYAN
BUILDING-Rough-Frame 12/7/2021 Approved ARTHUR SARGSYAN
Drywall Nailing 12/7/2021 Approved ARTHUR SARGSYAN
Final 12/7/2021 OK to Issue CofO ARTHUR SARGSYAN
METHANE-Final 12/7/2021 Approved ARTHUR SARGSYAN
METHANE-Rough 12/7/2021 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 12/7/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 12/7/2021 Approved ARTHUR SARGSYAN
Special/Order Compliance 7/29/2022 Approved JOSEPH MCGARRY
Special/Order Compliance 9/13/2022 Approved JOSEPH MCGARRY