903 N HUDSON AVE 90038
Certificate Information: 903 N HUDSON AVE 90038
- Application / Permit
- 17016-10000-13809
- Plan Check / Job No.
- B17LA08809
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft story retrofit per LAMC Div 93: Install (3) steel moment frames
- Permit Issued
- Issued on 11/23/2020
- Issuing Office
- Current Status
- CofC Issued on 7/26/2021
Permit Application Status History
| Submitted | 5/24/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/29/2017 | MANUEL MONTUFAR |
| Corrections Issued | 7/7/2017 | MANUEL MONTUFAR |
| Quality Review Completed | 7/17/2017 | CELESTE MORRIS |
| Building Plans Picked Up | 7/31/2017 | APPLICANT |
| Plan Check Approved | 8/15/2017 | MANUEL MONTUFAR |
| Issued | 11/23/2020 | APPLICANT |
| OK for CofC | 6/7/2021 | BRUCE CAMPBELL |
| CofC Issued | 7/26/2021 | WINSTON DUNNING |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 11/9/2020 | PHILLIP MUNGUIA |
Contact Information
| Contractor | Cal Retrofit; Lic. No.: 1022167-B | 6900 CANBY AVE #108 RESEDA, CA 91335 |
| Engineer | Hosseinzadeh, Jamshid K; Lic. No.: S3761 | 16808 ARMSTRONG AVE WD PARTNERS IRVINE, CA 92606 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/4/2021 | Not Ready for Inspection | JONATHAN QUACH |
| Deputy Steel/Welding | 2/25/2021 | Conditional Approval | JONATHAN QUACH |
| Deputy Drilled-In Anchors | 2/26/2021 | Conditional Approval | FRED WOHLFARTH |
| Deputy Steel/Welding | 3/12/2021 | Conditional Approval | FRED WOHLFARTH |
| Footing/Foundation/Slab | 4/22/2021 | Approved | JONATHAN QUACH |
| Structural Steel Frame | 4/22/2021 | Approved | JONATHAN QUACH |
| Wood Frame | 4/22/2021 | Approved | JONATHAN QUACH |
| Deputy Reinf. Concrete | 4/26/2021 | Conditional Approval | JONATHAN QUACH |
| Interior/Exterior Lathing | 5/18/2021 | Approved | JONATHAN QUACH |
| Final | 6/7/2021 | OK for CofC | BRUCE CAMPBELL |
| METHANE-Final | 6/7/2021 | Approved | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 6/7/2021 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 6/7/2021 | Approved | BRUCE CAMPBELL |