9849 W TABOR ST 90034
Certificate Information: 9849 W TABOR ST 90034
- Application / Permit
- 17016-10000-12744
- Plan Check / Job No.
- B17LA08103
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT-STORY SEISMIC RETROFIT PER LAMC DIVISION 93. INSTALLATION OF 1 HARDY FRAME SHEAR WALL AT SOUTH SIDE (FRONT). INSTALLATION OF 4 WOOD SHEAR WALLS AT WEST SIDE, 1 AT NORTH SIDE (REAR) AND 1 AT EAST SIDE. WORKS ARE ONLY AT REAR TUCK-UNDER PARKING AREAS AND EXTERIOR SIDES OF WALLS NOT ON TENANTS' UNITS.
- Permit Issued
- Issued on 1/13/2020
- Issuing Office
- Metro
- Current Status
- CofC Issued on 8/31/2020
Permit Application Status History
| Submitted | 5/15/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 6/22/2017 | ERWIN PASCUA |
| Corrections Issued | 7/6/2017 | ERWIN PASCUA |
| Quality Review Completed | 7/10/2017 | CELESTE MORRIS |
| Building Plans Picked Up | 7/14/2017 | APPLICANT |
| Plan Check Approved | 9/29/2017 | ERWIN PASCUA |
| Issued | 1/13/2020 | LADBS |
| OK for CofC | 8/27/2020 | GRANT WOODS |
| CofC Issued | 8/31/2020 | TED RIES |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 12/5/2019 | STEVEN HOFSTAD |
Contact Information
| Contractor | Basseri Engineering & Construction; Lic. No.: 724559-B | 5250 W CENTRY BLVD #300 LOS ANGELES, CA 90045 |
| Engineer | Basseri, Siavash; Lic. No.: C45487 | 1205 MAPLE ST SANTA MONICA, CA 90405 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/13/2020 | Approved | GRANT WOODS |
| Wood Frame | 6/24/2020 | Partial Inspection | GRANT WOODS |
| Footing/Foundation/Slab | 6/29/2020 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 6/29/2020 | Partial Approval | SORIN CIRSTOIU |
| Wood Frame | 7/7/2020 | Approved | GRANT WOODS |
| Deputy Drilled-In Anchors | 7/16/2020 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 7/16/2020 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 7/16/2020 | Approved | GRANT WOODS |
| Wood Frame | 7/16/2020 | Approved | GRANT WOODS |
| Deputy Reinf. Concrete | 7/17/2020 | Conditional Approval | GRANT WOODS |
| Wood Frame | 7/22/2020 | Approved | GRANT WOODS |
| Deputy Wood Construction | 7/23/2020 | Approved | GRANT WOODS |
| Wood Frame | 7/23/2020 | Partial Approval | GRANT WOODS |
| Interior/Exterior Lathing | 7/29/2020 | Approved | PAUL DAVIDSON |
| Final | 8/27/2020 | OK for CofC | GRANT WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/27/2020 | SGSOV Approved | GRANT WOODS |
| Smoke Detectors | 8/27/2020 | Approved | GRANT WOODS |