723 S HARVARD BLVD 90005
Certificate Information: 723 S HARVARD BLVD 90005
- Application / Permit
- 17016-10000-07092
- Plan Check / Job No.
- B17LA04617
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-story retrofit of the tuck under regions of an apartment building per LAMC Division 93. Install new steel moment frame.
- Permit Issued
- Issued on 2/28/2020
- Issuing Office
- Metro
- Current Status
- Issued on 2/28/2020
Permit Application Status History
| Submitted | 3/23/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 4/20/2017 | MANUEL MONTUFAR |
| Corrections Issued | 5/2/2017 | MANUEL MONTUFAR |
| Quality Review Completed | 5/2/2017 | CELESTE MORRIS |
| Building Plans Picked Up | 5/17/2017 | APPLICANT |
| Applicant returned to address corrections | 7/28/2017 | MANUEL MONTUFAR |
| Plan Check Approved | 8/1/2017 | MANUEL MONTUFAR |
| Issued | 2/28/2020 | LADBS |
Permit Application Clearance Information
| Project located in CRA area | Cleared | 2/25/2020 | GRACIELA ACOSTA |
| Housing rent stabilization | Cleared | 2/28/2020 | MICHAEL GREGERSON |
Contact Information
| Contractor | Cha Kyungmin; Lic. No.: 1018067-B | 917 S NEW HAMPSHIRE AVENUE 103 LOS ANGELES, CA 90006 |
| Engineer | Lara, Arath Saude; Lic. No.: C68626 | 12329 SILVER SADDLE RANCHO CUCAMONGA, CA 91739 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/7/2020 | Partial Approval | DARRYL ARNOLD |
| Pre-Inspection | 5/14/2021 | Approved | MARK FERRARI |
| Footing/Foundation/Slab | 5/28/2021 | Approved | DARRYL ARNOLD |
| Deputy Steel/Welding | 6/7/2021 | Conditional Approval | DARRYL ARNOLD |
| Deputy Drilled-In Anchors | 6/11/2021 | Conditional Approval | MARK FERRARI |
| Footing/Foundation/Slab | 6/14/2021 | Approved | BRUCE CAMPBELL |
| Wood Frame | 6/14/2021 | Approved | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 7/2/2021 | Corrections Issued | BRUCE CAMPBELL |
| Interior/Exterior Lathing | 7/7/2021 | Corrections Issued | BRUCE CAMPBELL |
| Final | 7/30/2021 | Corrections Issued | BRUCE CAMPBELL |
| SGSOV-Seismic Gas S/O Valve | 7/30/2021 | SGSOV Approved | BRUCE CAMPBELL |
| Smoke Detectors | 7/30/2021 | Approved | BRUCE CAMPBELL |