Application / Permit
17016-10000-03153
Plan Check / Job No.
B17LA02063
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT PER LABC CHAPTER 93. INSTALL STEEL MOMENT FRAME.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofC Issued on 5/20/2021

Permit Application Status History

Submitted 2/10/2017 APPLICANT
Assigned to Plan Check Engineer 2/16/2017 MANUEL MONTUFAR
Corrections Issued 2/22/2017 MANUEL MONTUFAR
Quality Review Completed 2/24/2017 CELESTE MORRIS
Building Plans Picked Up 3/20/2017 APPLICANT
Plan Check Approved 12/31/2018 MANUEL MONTUFAR
Plan Check Approved 10/29/2020 JESSE VIDUYA
Issued 11/24/2020 APPLICANT
OK for CofC 5/17/2021 MARK FERRARI
CofC Issued 5/20/2021 ERNESTO CORRAL

Permit Application Clearance Information

Housing rent stabilization Cleared 11/18/2020 STEVEN HOFSTAD

Contact Information

Contractor Titan Contracting Services Inc; Lic. No.: 976552-B 13434 RAYMER STREET      NORTH HOLLYWOOD, CA 91605
Engineer Ni,, Zhang Yuan; Lic. No.: C68149 743 S SIERRA VISTA AVE C      ALHAMBRA, CA 91801

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2021 Approved MARK FERRARI
Deputy Drilled-In Anchors 2/26/2021 Conditional Approval MARK FERRARI
Footing/Foundation/Slab 3/3/2021 Approved MARK FERRARI
Structural Steel Frame 3/3/2021 Partial Approval MARK FERRARI
Wood Frame 3/3/2021 Not Ready for Inspection MARK FERRARI
Structural Steel Frame 3/11/2021 Approved MARK FERRARI
Wood Frame 3/11/2021 Approved MARK FERRARI
Drywall Nailing 3/16/2021 Corrections Issued MARK FERRARI
Final 4/29/2021 Corrections Issued DARRYL ARNOLD
METHANE-Final 4/29/2021 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 4/29/2021 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 4/29/2021 Conditional Approval DARRYL ARNOLD
Final 5/17/2021 OK for CofC MARK FERRARI
METHANE-Final 5/17/2021 Approved MARK FERRARI
SGSOV-Seismic Gas S/O Valve 5/17/2021 SGSOV Approved MARK FERRARI