1050 S GRAND AVE 1-151 90015
Certificate Information: 1050 S GRAND AVE 1-151 90015
- Application / Permit
- 17016-10000-01609
- Plan Check / Job No.
- B17LA01061
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (35) Condo-Multi Family
- Work Description
- CHANGE OF USE FOR A NEW MIXED USE PROJECT FROM 151 APARTMENT UNITS TO 151 CONDO UNITS W/ 5672 SF OF COMMERCIAL SPACE (no physical constructions)
- Permit Issued
- Issued on 3/20/2017
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 10/11/2017
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/25/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 2/2/2017 | SUEN LIEU |
| Plan Check Approved | 3/7/2017 | SUEN LIEU |
| Issued | 3/20/2017 | LADBS |
| Permit Finaled | 10/10/2017 | LESLIE TRUJILLO |
Permit Application Clearance Information
| "D" conditions | Cleared | 2/8/2017 | MARITZA PRZEKOP |
| "Q" conditions | Cleared | 2/8/2017 | MARITZA PRZEKOP |
| Tract Map conditions | Cleared | 2/8/2017 | MARITZA PRZEKOP |
| ZA Case | Cleared | 2/8/2017 | MARITZA PRZEKOP |
| ZA Case | Cleared | 2/8/2017 | MARITZA PRZEKOP |
| Address approval | Cleared | 2/9/2017 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 2/9/2017 | PAMELA TENEZA |
| Highway dedication | Cleared | 2/9/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 2/9/2017 | RAVIL MANAPOV |
Contact Information
| Architect | Metzger, George Russell; Lic. No.: C21930 | 17383 SUNSET BLVD. PACIFIC PALISADES, CA 90272 |
| Contractor | Lend Lease (Us) Construction Inc; Lic. No.: 483550-B | 200 PARK AVENUE 9TH FLOOR ATTN GENERAL COUNSEL NEW YORK, NY 10166 |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BAZERKANIAN, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 10/10/2017 | Permit Finaled | LESLIE TRUJILLO |
| METHANE-Final | 10/10/2017 | Approved | LESLIE TRUJILLO |
| METHANE-Rough | 10/10/2017 | Approved | LESLIE TRUJILLO |
| Reinforced Concrete Frame | 10/10/2017 | Approved | LESLIE TRUJILLO |