1220 S WELLESLEY AVE 1-9 90025
Certificate Information: 1220 S WELLESLEY AVE 1-9 90025
- Application / Permit
- 17016-10000-00315
- Plan Check / Job No.
- B17LA00211
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT OF THE SOFT/WEAK WALL LINE(S) PER LAMC DIVISION 93.
- Permit Issued
- Issued on 8/4/2023
- Issuing Office
- Current Status
- CofC Issued on 6/11/2025
Permit Application Status History
| Submitted | 1/6/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2017 | EDMOND HAGOPYAN |
| Corrections Issued | 1/17/2017 | EDMOND HAGOPYAN |
| Quality Review Completed | 1/18/2017 | CATHERINE NUEZCA GABA |
| Building Plans Picked Up | 2/2/2017 | APPLICANT |
| Applicant returned to address corrections | 3/29/2017 | EDMOND HAGOPYAN |
| Plan Check Approved | 4/7/2017 | EDMOND HAGOPYAN |
| Issued | 8/4/2023 | APPLICANT |
| OK for CofC | 5/5/2025 | RICARDO ROBLES |
| CofC Issued | 6/11/2025 | DAVID TSAU |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 7/5/2023 | HUGO GARRIDO GARZA |
Contact Information
| Contractor | Sater Development Strategies Inc; Lic. No.: 1074535-B | 9854 NATIONAL BLVD 235 LOS ANGELES, CA 90034 |
| Engineer | Mirmohammadsadeghi, Kamaleddin; Lic. No.: C53468 | 1377 S BEVERLY GLEN BLVD 308 LOS ANGELES, CA 90024 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/15/2023 | Approved | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/1/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 3/1/2024 | Conditional Approval | RICARDO ROBLES |
| Excavation/Setback/Form/Re-Bar | 3/11/2024 | Approved | RICARDO ROBLES |
| Footing/Foundation/Slab | 3/11/2024 | Approved | RICARDO ROBLES |
| Structural Steel Frame | 3/11/2024 | Partial Approval | RICARDO ROBLES |
| Deputy Reinf. Concrete | 3/13/2024 | Conditional Approval | RICARDO ROBLES |
| Deputy Steel/Welding | 4/26/2024 | Conditional Approval | RICARDO ROBLES |
| Floor/Roof Diaphrgm/Shear Wall | 8/7/2024 | Approved | RICARDO ROBLES |
| Structural Steel Frame | 8/7/2024 | Approved | RICARDO ROBLES |
| Wood Frame | 8/7/2024 | Approved | RICARDO ROBLES |
| Deputy Wood Construction | 8/8/2024 | Partial Approval | RICARDO ROBLES |
| Interior/Exterior Lathing | 8/19/2024 | Approved | GRANT WOODS |
| Final | 5/5/2025 | OK for CofC | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 5/5/2025 | Approved | RICARDO ROBLES |