3448-3450 W 75TH ST 90043
Certificate Information: 3448-3450 W 75TH ST 90043
- Application / Permit
- 17016-10000-00052
- Plan Check / Job No.
- B17LA00024
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- CONVERT SINGLE FAMILY TO DUPLEX (ATTACHED ACCESSORY DWELLING UNIT IN R1 ZONE)
- Permit Issued
- Issued on 5/25/2017
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/3/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 2/23/2017 | ALBERT SERVIN |
| Corrections Issued | 3/3/2017 | ALBERT SERVIN |
| Quality Review Completed | 3/8/2017 | CHAD DOI |
| Building Plans Picked Up | 3/15/2017 | APPLICANT |
| Plan Check Approved | 5/24/2017 | ALBERT SERVIN |
| Issued | 5/25/2017 | LADBS |
| CofO in Progress | 4/22/2021 | FREDDIE RIVERA |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
| CofO Issued | 5/1/2021 | DEROLD HAUFF |
| Permit Finaled | 5/1/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2017 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 5/24/2017 | FATIMA GUERRA |
| Sewer availability | Cleared | 5/24/2017 | CELINA MORENO |
| Street width determination | Cleared | 5/24/2017 | CELINA MORENO |
Contact Information
| Contractor | Duhon Construction Co; Lic. No.: 401447-B | 515 WEST GARDENA BLVD #27 GARDENA, CA 90248 |
| Engineer | Wong, Jim Chu Man; Lic. No.: C69393 | PO BOX 91522 PASADENA, CA 91109 |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/29/2018 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 2/6/2019 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/2/2019 | Not Ready for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 5/2/2019 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/16/2019 | No Access for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 5/22/2019 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 5/22/2019 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 5/22/2019 | Approved | FREDDIE RIVERA |
| Insulation | 8/5/2019 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 10/4/2019 | Approved | FREDDIE RIVERA |
| Insulation | 11/1/2019 | Approved | FREDDIE RIVERA |
| Drywall Nailing | 11/22/2019 | Approved | FREDDIE RIVERA |
| Gas Test | 1/16/2020 | Corrections Issued | FREDDIE RIVERA |
| ELECTRICAL-Final | 7/14/2020 | Partial Approval | FREDDIE RIVERA |
| Final | 8/11/2020 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/11/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Smoke Detectors | 8/11/2020 | Approved | FREDDIE RIVERA |
| Final | 8/24/2020 | Corrections Issued | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 8/24/2020 | SGSOV Not Ready | FREDDIE RIVERA |
| Final | 9/29/2020 | Conditional Approval | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/29/2020 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 9/29/2020 | Approved | FREDDIE RIVERA |
| Final | 4/22/2021 | OK to Issue CofO | FREDDIE RIVERA |