2938 S VICTORIA AVE 90016

Certificate Information: 2938 S VICTORIA AVE 90016

Application / Permit
17014-70000-06042
Plan Check / Job No.
B17SL01482
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REAR ADDITION AND INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING
Permit Issued
Issued on 1/24/2018
Issuing Office
South Los Angeles
Current Status
CofO Corrected on 9/6/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/28/2017 APPLICANT
Assigned to Plan Check Engineer 11/28/2017 JOSHUA DIAZ
Corrections Issued 11/28/2017 JOSHUA DIAZ
Applicant returned to address corrections 12/27/2017 WESLEY FARRELL
Issued 1/24/2018 LADBS
CofO in Progress 3/9/2019 BOB DUNN
CofO Issued-Status Void 3/12/2019 RONALD MYRICK
Permit Finaled-Status Void 3/12/2019 RONALD MYRICK
Re-Activate Permit 9/5/2023 DEROLD HAUFF
Permit Finaled 9/6/2023 DEROLD HAUFF
CofO Corrected 9/6/2023 DEROLD HAUFF
Permit Finaled 9/6/2023 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/30/2017 ADRIAN SANCHEZ
Roof/Waste drainage to street Cleared 11/30/2017 ADRIAN SANCHEZ
Sewer availability Cleared 11/30/2017 ADRIAN SANCHEZ

Contact Information

Contractor Golden Point Construction; Lic. No.: 965193-B 731 EAST 75TH STREET      LOS ANGELES, CA 90001
Engineer Cooke, Conway Cecil; Lic. No.: S5524 34658 LINDA ROSEA RD      TEMECULA, CA 92592

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/8/2018 Approved BOB GOBUTY
PLUMBING-Rough 2/21/2018 Partial Approval BOB GOBUTY
ELECTRICAL-Rough 3/14/2018 Not Ready for Inspection CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 3/14/2018 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Rough 3/20/2018 Partial Approval BOB GOBUTY
Floor/Roof Diaphrgm/Shear Wall 3/20/2018 Partial Approval BOB GOBUTY
PLUMBING-Rough 3/20/2018 Partial Approval BOB GOBUTY
BUILDING-Rough-Frame 3/21/2018 Approved ROBERT MCDOWELL
ELECTRICAL-Rough 3/21/2018 Approved ROBERT MCDOWELL
Green Building Rough 3/21/2018 Approved ROBERT MCDOWELL
PLUMBING-Rough 3/21/2018 Approved ROBERT MCDOWELL
Insulation 3/27/2018 Partial Approval BOB GOBUTY
Insulation 4/2/2018 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 4/2/2018 Approved KATHRYN BUTTERWORTH
Drywall Nailing 4/9/2018 Partial Inspection BOB GOBUTY
Drywall Nailing 4/11/2018 Approved KATHRYN BUTTERWORTH
Final 9/27/2018 Not Ready for Inspection LUIS ALVAREZ
Footing/Foundation/Slab 9/27/2018 Approved LUIS ALVAREZ
Green Building Final 9/27/2018 Approved LUIS ALVAREZ
SGSOV-Seismic Gas S/O Valve 9/27/2018 SGSOV Not Ready LUIS ALVAREZ
Smoke Detectors 9/27/2018 Approved LUIS ALVAREZ
Final 11/5/2018 Corrections Issued LUIS ALVAREZ
SGSOV-Seismic Gas S/O Valve 11/5/2018 SGSOV Approved LUIS ALVAREZ
Final 11/15/2018 No Access for Inspection LUIS ALVAREZ
Final 11/20/2018 Not Ready for Inspection LUIS ALVAREZ
Final 12/11/2018 Corrections Issued LUIS ALVAREZ
Final 12/21/2018 Not Ready for Inspection LUIS ALVAREZ
Final 1/17/2019 Corrections Issued LUIS ALVAREZ
Final 2/11/2019 Corrections Issued LUIS ALVAREZ
Final 2/19/2019 Corrections Issued ALEJANDRO DE ARTOLA
Final 3/6/2019 Corrections Issued SCOTT FINNILA
Final 3/7/2019 OK to Issue CofO BOB DUNN