1760 E 107TH ST 90002
Certificate Information: 1760 E 107TH ST 90002
- Application / Permit
- 17014-70000-05341
- Plan Check / Job No.
- B17SL01317
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ONE STORY ADDITION TO (E) SFD TO ENLARGE 2 (E) BEDROOMS AND CREATE 1(N) CLOSET
- Permit Issued
- Issued on 10/30/2017
- Issuing Office
- South Los Angeles
- Current Status
- Issued on 10/30/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/19/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2017 | LUKE GONZALES |
| Corrections Issued | 10/24/2017 | LUKE GONZALES |
| Quality Review Completed | 10/24/2017 | WESLEY FARRELL |
| Plan Check Approved | 10/25/2017 | LUKE GONZALES |
| Issued | 10/30/2017 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2017 | STEVE MELGAR |
| Roof/Waste drainage to street | Cleared | 10/20/2017 | STEVE MELGAR |
Contact Information
| Contractor | Paars Design & Build; Lic. No.: 998847-B | P O BOX 881504 LOS ANGELES, CA 90009 |
| Engineer | , ; Lic. No.: C29787 | PO BOX 17083 LONG BEACH, CA 90807 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 3/8/2018 | Approved | JOHN KLARIN |
| Excavation/Setback/Form/Re-Bar | 3/9/2018 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 4/5/2019 | No Access for Inspection | JOHN KLARIN |
| Green Building Rough | 4/5/2019 | No Access for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/9/2019 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 5/9/2019 | Not Ready for Inspection | DAVID FEILER |
| Green Building Rough | 5/9/2019 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 7/1/2019 | No Access for Inspection | WILLIAM ROSE |
| Reinforced Concrete Frame | 7/1/2019 | No Access for Inspection | WILLIAM ROSE |
| Wood Frame | 7/1/2019 | No Access for Inspection | WILLIAM ROSE |
| ELECTRICAL-Rough | 7/12/2019 | Corrections Issued | WILLIAM ROSE |
| Green Building Final | 8/1/2019 | Corrections Issued | WILLIAM ROSE |
| BUILDING-Rough-Frame | 8/21/2019 | Corrections Issued | WILLIAM ROSE |
| Green Building Rough | 8/21/2019 | Approved | WILLIAM ROSE |
| Interior/Exterior Lathing | 8/21/2019 | Conditional Approval | WILLIAM ROSE |
| Rough-Elec/Plmb/HVAC | 8/21/2019 | Approved | WILLIAM ROSE |
| Wood Frame | 8/21/2019 | Approved | WILLIAM ROSE |
| Insulation | 11/20/2019 | Corrections Issued | WILLIAM ROSE |
| Insulation | 12/19/2019 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 9/29/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Pre-Inspection | 9/29/2020 | Corrections Issued | EUGENE CASSIDY |
| Wood Frame | 9/29/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Drywall Nailing | 11/6/2020 | Approved | EUGENE CASSIDY |