Piling/Pier/Caisson
|
10/18/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
10/24/2019
|
No Access for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
10/25/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Deputy Drilled-In Anchors
|
11/18/2019
|
Conditional Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
11/18/2019
|
Conditional Approval
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
11/25/2019
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/2/2019
|
Corrections Issued
|
CARLOS MATAMOROS
|
|
Deputy Steel/Welding
|
12/16/2019
|
Conditional Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
12/17/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Footing/Foundation/Slab
|
12/30/2019
|
Not Ready for Inspection
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
1/3/2020
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Deputy Steel/Welding
|
1/10/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
1/13/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
1/13/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Drilled-In Anchors
|
1/14/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
1/15/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
1/16/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Special/Order Compliance
|
1/16/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Drilled-In Anchors
|
1/17/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
1/23/2020
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Deputy Drilled-In Anchors
|
1/24/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
1/24/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Drilled-In Anchors
|
1/29/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
1/29/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Drilled-In Anchors
|
2/12/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
2/14/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Footing/Foundation/Slab
|
2/20/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Drilled-In Anchors
|
2/26/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
3/3/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
3/10/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
3/16/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
3/18/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
3/19/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
4/3/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/6/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Drilled-In Anchors
|
4/8/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
4/16/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Excavation/Setback/Form/Re-Bar
|
4/17/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/20/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
4/27/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/27/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
4/27/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
4/27/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/4/2020
|
Partial Approval
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
5/4/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
5/4/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
5/5/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Footing/Foundation/Slab
|
5/14/2020
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Deputy Reinf. Concrete
|
5/15/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
5/18/2020
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
10/26/2020
|
Corrections Issued
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
10/26/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
10/26/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
11/20/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/20/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
11/20/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
11/20/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
BUILDING-Rough-Frame
|
12/1/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/1/2020
|
Approved
|
ANTHONY MCDOWALL
|
|
Green Building Rough
|
12/1/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Verify Sprinkler Sign Off
|
12/1/2020
|
Not Ready for Inspection
|
ANTHONY MCDOWALL
|
|
Deputy Steel/Welding
|
4/13/2021
|
Conditional Approval
|
ANTHONY MCDOWALL
|
|
Shower Pan
|
5/21/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
9/17/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Pre-Inspection
|
9/17/2021
|
Approved
|
GERMAN RODRIGUEZ MENDOZA
|
|
Gas Test
|
9/21/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Underground Mechanical
|
9/21/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
9/30/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Pre-Inspection
|
10/5/2021
|
Approved
|
CARLOS MATAMOROS
|
|
BUILDING-Rough-Frame
|
10/7/2021
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Green Building Rough
|
10/7/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Verify Sprinkler Sign Off
|
10/7/2021
|
Approved
|
CARLOS MATAMOROS
|
|
Sewer
|
10/12/2021
|
No Access for Inspection
|
CARLOS MATAMOROS
|
|
Insulation
|
10/21/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Drywall Nailing
|
10/26/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Drywall Nailing
|
11/8/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
11/8/2021
|
Corrections Issued
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
11/15/2021
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Drywall Nailing
|
11/22/2021
|
Partial Approval
|
RYAN SALAZAR
|
|
Drywall Nailing
|
11/30/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Insulation
|
11/30/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Drywall Nailing
|
12/7/2021
|
Conditional Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Interior/Exterior Lathing
|
12/7/2021
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|