8027 N LOUISE AVE 91325
Certificate Information: 8027 N LOUISE AVE 91325
- Application / Permit
- 17014-40000-04943
- Plan Check / Job No.
- B17SP00872
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add master bedroom with 3/4 bathroom and walkin closet; and second bedroom with full bathroom; and family room.
- Permit Issued
- Issued on 1/19/2018
- Issuing Office
- San Pedro
- Current Status
- CofO Issued on 1/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 10/5/2017 | JASON JANGADA |
| Corrections Issued | 10/11/2017 | JASON JANGADA |
| Quality Review Completed | 10/12/2017 | CHIHARU SUZUKI |
| Building Plans Picked Up | 10/18/2017 | APPLICANT |
| Applicant returned to address corrections | 11/17/2017 | JASON JANGADA |
| Applicant returned to address corrections | 1/11/2018 | JASON JANGADA |
| Plan Check Approved | 1/19/2018 | JASON JANGADA |
| Issued | 1/19/2018 | LADBS |
| CofO in Progress | 1/27/2026 | GAREN HAYRAPETYAN |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
| CofO Issued | 1/30/2026 | RUBEN SALAS |
| Permit Finaled | 1/30/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2018 | CARLA VALLADARES |
| Low Impact Development | Cleared | 1/3/2018 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 1/3/2018 | CARLA VALLADARES |
| Sewer availability | Cleared | 1/3/2018 | CARLA VALLADARES |
| Green Code | Cleared | 1/10/2018 | JASON JANGADA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gunal, Nezih M; Lic. No.: C18689 | 5474 GARFORD ST LONG BEACH, CA 90815 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/1/2018 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 3/6/2018 | Partial Approval | JACK KARGODORIAN |
| Footing/Foundation/Slab | 3/8/2018 | Not Ready for Inspection | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 3/9/2018 | Partial Approval | JACK KARGODORIAN |
| Excavation/Setback/Form/Re-Bar | 3/16/2018 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 4/18/2018 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2018 | Corrections Issued | JACK KARGODORIAN |
| Green Building Rough | 4/18/2018 | Not Ready for Inspection | JACK KARGODORIAN |
| Wood Frame | 4/18/2018 | Not Ready for Inspection | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2018 | Partial Approval | JACK KARGODORIAN |
| Wood Frame | 4/20/2018 | Not Ready for Inspection | JACK KARGODORIAN |
| ELECTRICAL-Rough | 5/18/2018 | Approved | JACK KARGODORIAN |
| Gas Test | 5/18/2018 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 5/18/2018 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 5/18/2018 | Approved | JACK KARGODORIAN |
| Rough-Elec/Plmb/HVAC | 5/18/2018 | Approved | JACK KARGODORIAN |
| Smoke Detectors | 5/18/2018 | Not Ready for Inspection | JACK KARGODORIAN |
| Insulation | 9/26/2018 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 10/3/2018 | Approved | GREG ALLTON |
| Green Building Rough | 10/3/2018 | Approved | GREG ALLTON |
| Interior/Exterior Lathing | 10/3/2018 | Partial Approval | GREG ALLTON |
| BUILDING-Rough-Frame | 2/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Final | 2/1/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 2/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 2/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/1/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 2/1/2021 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Interior/Exterior Lathing | 2/4/2021 | Approved | ARTHUR SARGSYAN |
| Special/Order Compliance | 1/2/2026 | Corrections Issued | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | GAREN HAYRAPETYAN |
| Final | 1/27/2026 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Footing/Foundation/Slab | 1/27/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Final | 1/27/2026 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 1/27/2026 | Approved | GAREN HAYRAPETYAN |