5117 S OCEAN FRONT WALK 90292

Certificate Information: 5117 S OCEAN FRONT WALK 90292

Application / Permit
17014-40000-03672
Plan Check / Job No.
B17SP00665
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Renovation of 3 unit apartment building with the first floor as basement and a recreation room to include 438sf addition on the 2nd story.
Permit Issued
Issued on 8/23/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/27/2017 APPLICANT
Assigned to Plan Check Engineer 8/3/2017 TARIK SAOUD
Corrections Issued 8/8/2017 TARIK SAOUD
Quality Review Completed 8/9/2017 STEVEN KIM
Building Plans Picked Up 8/11/2017 APPLICANT
Green Plans Picked Up 1/29/2018 APPLICANT
Plan Check Approved 8/23/2018 TARIK SAOUD
Issued 8/23/2018 LADBS
CofO in Progress 1/27/2025 FARHAD DADBIN
Permit Finaled 1/27/2025 DAVID TSAU
CofO Issued 1/27/2025 DAVID TSAU
Permit Finaled 1/27/2025 DAVID TSAU

Permit Application Clearance Information

Address approval Cleared 2/8/2018 STEVE MELGAR
Coastal Zone Cleared 2/8/2018 JESSE RAMOS
DAS Clearance Cleared 2/8/2018 WAI LAU
Eng Process Fee Ord 176,300 Cleared 2/8/2018 STEVE MELGAR
Housing rent stabilization Cleared 2/8/2018 STEVEN HOFSTAD
Miscellaneous Cleared 2/8/2018 JESSE RAMOS
Miscellaneous Cleared 2/8/2018 JESSE RAMOS
Miscellaneous Cleared 2/8/2018 JESSE RAMOS
Miscellaneous Cleared 2/8/2018 JESSE RAMOS
Permit Cleared 2/8/2018 STEVE MELGAR
Sewer availability Cleared 2/8/2018 STEVE MELGAR
Specific Plan Cleared 2/8/2018 JESSE RAMOS
Specific Plan Cleared 2/9/2018 CLIVE GRAWE
Roof/Waste drainage to street Cleared 7/19/2018 MICHAEL CASTILLO
Work Adjacent to Public Way Cleared 7/19/2018 BOK GOH
Green Code Cleared 7/20/2018 RICHARD GARCIA
Fire Marshall Fire Life Safety Cleared 8/22/2018 ANDREW KO

Contact Information

Contractor Rock Construction And Management; Lic. No.: 753939-B 10729 FRANCIS PLACE      LOS ANGELES, CA 90034
Engineer Polon, Gordon Leonard; Lic. No.: C28564 709 19TH STREET      SANTA MONICA, CA 90402

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/12/2018 Partial Inspection ALAN NOVAK
Pre-Inspection 9/20/2018 Partial Inspection ALAN NOVAK
Pre-Inspection 10/9/2018 No Access for Inspection ALAN NOVAK
Pre-Inspection 10/18/2018 Partial Inspection ALAN NOVAK
Deputy Drilled-In Anchors 2/7/2019 Conditional Approval ALAN NOVAK
Footing/Foundation/Slab 2/11/2019 Partial Approval ALAN NOVAK
METHANE-Barrier 2/11/2019 Partial Inspection ALAN NOVAK
METHANE-Subgrade 2/11/2019 Partial Inspection ALAN NOVAK
Deputy Reinf. Concrete 2/12/2019 Conditional Approval ALAN NOVAK
Pre-Inspection 5/7/2019 Approved ALAN NOVAK
Footing/Foundation/Slab 6/7/2019 Partial Approval JASON BORUTA
METHANE-Barrier 6/7/2019 Not Ready for Inspection JASON BORUTA
METHANE-Subgrade 6/7/2019 Not Ready for Inspection JASON BORUTA
Deputy Drilled-In Anchors 6/18/2019 Conditional Approval ALAN NOVAK
Footing/Foundation/Slab 6/20/2019 Partial Approval DERRICK SPENCER
METHANE-Barrier 6/20/2019 Approved DERRICK SPENCER
METHANE-Subgrade 6/20/2019 Approved DERRICK SPENCER
Deputy Reinf. Concrete 6/24/2019 Conditional Approval ALAN NOVAK
Deputy Reinf. Concrete 7/22/2019 Conditional Approval ALAN NOVAK
Footing/Foundation/Slab 7/26/2019 Not Ready for Inspection ALAN NOVAK
Excavation/Setback/Form/Re-Bar 8/20/2019 Not Ready for Inspection ALAN NOVAK
Deputy Drilled-In Anchors 9/3/2019 Conditional Approval ALAN NOVAK
Deputy Reinf. Concrete 9/16/2019 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 9/17/2019 Conditional Approval ALAN NOVAK
Wood Frame 11/7/2019 Not Ready for Inspection ALAN NOVAK
Deputy Drilled-In Anchors 12/23/2019 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 12/23/2019 Conditional Approval ALAN NOVAK
Green Building Rough 12/23/2019 Approved ALAN NOVAK
METHANE-Rough 12/23/2019 Approved ALAN NOVAK
Wood Frame 12/23/2019 Partial Inspection ALAN NOVAK
Wood Frame 1/3/2020 Partial Approval ALAN NOVAK
Deputy Drilled-In Anchors 1/14/2020 Conditional Approval ALAN NOVAK
Special/Order Compliance 2/12/2020 Approved ALAN NOVAK
Footing/Foundation/Slab 2/25/2020 Approved ALAN NOVAK
Deputy Reinf. Concrete 2/27/2020 Conditional Approval ALAN NOVAK
Wood Frame 4/15/2020 Partial Approval ALAN NOVAK
Deputy Steel/Welding 6/10/2020 Conditional Approval ALAN NOVAK
Deputy Steel/Welding 6/18/2020 Conditional Approval ALAN NOVAK
Special/Order Compliance 10/22/2020 Approved ALAN NOVAK
Wood Frame 12/21/2020 Partial Inspection SORIN CIRSTOIU
Deputy Steel/Welding 1/13/2021 Conditional Approval ALAN NOVAK
Floor/Roof Diaphrgm/Shear Wall 2/22/2021 Partial Approval LEOPOLDO MENDOZA
Floor/Roof Diaphrgm/Shear Wall 6/11/2021 Partial Approval JEFF BYTHEWAY
Wood Frame 9/14/2021 Partial Inspection SORIN CIRSTOIU
Wood Frame 11/18/2021 Partial Approval NICK LAROCCA
Wood Frame 12/14/2021 Partial Approval NICK LAROCCA
Wood Frame 7/13/2022 Partial Approval NICK LAROCCA
Wood Frame 8/29/2022 Partial Approval GRANT WOODS
Wood Frame 11/10/2022 Partial Approval GRANT WOODS
Special/Order Compliance 11/14/2022 Corrections Issued GRANT WOODS
Pre-Inspection 12/8/2022 Partial Inspection SHAVONNE ESPINOZA
Special/Order Compliance 12/8/2022 Partial Inspection GRANT WOODS
Wood Frame 2/23/2023 Approved FARHAD DADBIN
Insulation 3/9/2023 Approved FARHAD DADBIN
Special/Order Compliance 3/16/2023 Approved FARHAD DADBIN
Drywall Nailing 4/11/2023 Approved FARHAD DADBIN
Special/Order Compliance 3/7/2024 Partial Approval FARHAD DADBIN
Final 1/21/2025 OK to Issue CofO FARHAD DADBIN
Green Building Final 1/21/2025 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 1/21/2025 SGSOV Approved FARHAD DADBIN
Smoke Detectors 1/21/2025 Approved FARHAD DADBIN