2365 N NALIN DR 90077
Certificate Information: 2365 N NALIN DR 90077
- Application / Permit
- 17014-30007-02028
- Plan Check / Job No.
- B21WL04569
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental Permit Ref. to PCIS#: 17014-10000-02028 for Remodel, 1st and 2nd Story Addition to an (E) 2-Story S.F.D w/Attached Garage
- Permit Issued
- Issued on 6/2/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | DAVID CASTILLO |
| Corrections Issued | 11/9/2021 | DAVID CASTILLO |
| Quality Review Completed | 11/17/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 12/1/2021 | DAVID CASTILLO |
| Applicant returned to address corrections | 1/26/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 5/6/2022 | DAVID CASTILLO |
| Plan Check Approved | 6/2/2022 | DAVID CASTILLO |
| Issued | 6/2/2022 | APPLICANT |
| Building Plans Picked Up | 6/3/2022 | APPLICANT |
| Permit Finaled | 6/18/2022 | CARLOS MATAMOROS |
Permit Application Clearance Information
| Miscellaneous | Cleared | 2/1/2022 | LOUIS ORTEGA |
| Miscellaneous | Cleared | 2/1/2022 | LOUIS ORTEGA |
| Roof/Waste drainage to street | Cleared | 2/28/2022 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 3/14/2022 | KIRK LINKLATER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cattan,, Christian George; Lic. No.: C82566 | 8444 OWENSMOUTH AVE CANOGA PARK, CA 91304 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Drywall Nailing | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Final | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/9/2022 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Smoke Detectors | 6/9/2022 | Approved | CHRISTOPHER WILSON |