1618 S DURANGO AVE 90035

Certificate Information: 1618 S DURANGO AVE 90035

Application / Permit
17014-30002-02281
Plan Check / Job No.
B21WL04288
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 17014-30000-02281, to remove 1st floor addition and add 2nd floor addition. Recheck plans due to lost approved set.
Permit Issued
Issued on 8/10/2022
Issuing Office
Current Status
Permit Finaled on 1/29/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 ALFREDO JARA
Corrections Issued 10/12/2021 ALFREDO JARA
Quality Review Completed 10/19/2021 TARIK SAOUD
Applicant returned to address corrections 5/18/2022 ALFREDO JARA
Applicant returned to address corrections 6/8/2022 ALFREDO JARA
Applicant returned to address corrections 7/19/2022 ALFREDO JARA
Plan Check Approved 8/4/2022 ALFREDO JARA
Issued 8/10/2022 APPLICANT
Building Plans Picked Up 8/12/2022 APPLICANT
Permit Finaled 1/29/2025 MEL KHACHATOURIAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/9/2022 CINDY QI
Grading Pre-Inspection Cleared 5/9/2022 KIRK LINKLATER
Sewer availability Cleared 5/9/2022 CINDY QI
Low Impact Development Cleared 6/2/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/9/2022 STEVE MELGAR
GPI Written Notices Cleared 7/13/2022 ALFREDO JARA

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2022 Approved EVAN COOPER
Footing/Foundation/Slab 9/19/2022 Approved ANDREW NAVE
METHANE-Barrier 9/19/2022 Approved ANDREW NAVE
METHANE-Subgrade 9/19/2022 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Conditional Approval JEREMY TODD
PLUMBING-Rough 1/27/2023 Partial Approval JEREMY TODD
Rough-Elec/Plmb/HVAC 1/27/2023 Partial Approval JEREMY TODD
Shower Pan 2/9/2023 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/23/2023 Partial Approval JEREMY TODD
Green Building Rough 2/23/2023 Partial Approval JEREMY TODD
Interior/Exterior Lathing 2/23/2023 Partial Approval JEREMY TODD
Rough-Elec/Plmb/HVAC 2/23/2023 Partial Approval JEREMY TODD
Pre-Inspection 3/8/2023 Partial Approval JEREMY TODD
PLUMBING-Rough 3/20/2023 Partial Approval JEREMY TODD
Rough-Elec/Plmb/HVAC 5/12/2023 Approved JEREMY TODD
Shower Pan 5/12/2023 Corrections Issued JEREMY TODD
Deputy Drilled-In Anchors 5/23/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 6/15/2023 Corrections Issued JEREMY TODD
Shower Pan 6/15/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 6/16/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/16/2023 Approved JEREMY TODD
Green Building Rough 6/16/2023 Approved JEREMY TODD
METHANE-Rough 6/16/2023 Approved JEREMY TODD
BUILDING-Rough-Frame 6/23/2023 Approved JEREMY TODD
Floor/Roof Diaphrgm/Shear Wall 6/23/2023 Approved JEREMY TODD
Green Building Rough 6/23/2023 Approved JEREMY TODD
METHANE-Rough 6/23/2023 Approved JEREMY TODD
Interior/Exterior Lathing 6/27/2023 Corrections Issued JEREMY TODD
Insulation 6/30/2023 Corrections Issued JEREMY TODD
Interior/Exterior Lathing 7/5/2023 Partial Approval ARAM AVEDISIAN
Insulation 7/11/2023 Approved ARAM AVEDISIAN
Drywall Nailing 7/17/2023 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 7/31/2023 Partial Approval ARAM AVEDISIAN
Drywall Nailing 3/5/2024 Approved JESUS PINEDA
Final 1/8/2025 Corrections Issued ARAM AVEDISIAN
Green Building Final 1/8/2025 Approved ARAM AVEDISIAN
Smoke Detectors 1/8/2025 Approved ARAM AVEDISIAN