17854 W CASTELLAMMARE DR 90272

Certificate Information: 17854 W CASTELLAMMARE DR 90272

Application / Permit
17014-30001-06354
Plan Check / Job No.
B19WL04421
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental to 17014-30000-06354 to add open latice trellis attached to SFD.
Permit Issued
Issued on 6/25/2020
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 10/19/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/6/2019 APPLICANT
Assigned to Plan Check Engineer 9/5/2019 MANUEL GARCIA
Corrections Issued 9/25/2019 MANUEL GARCIA
Quality Review Completed 9/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/21/2019 MANUEL GARCIA
Applicant returned to address corrections 3/19/2020 MANUEL GARCIA
Applicant returned to address corrections 3/20/2020 MANUEL GARCIA
Plan Check Approved 6/18/2020 MANUEL GARCIA
Issued 6/25/2020 LADBS
Building Plans Picked Up 6/25/2020 APPLICANT
Permit Finaled 10/19/2020 ANDREW NAVE

Permit Application Clearance Information

Coastal Zone Cleared 3/23/2020 MARITZA PRZEKOP
Miscellaneous Cleared 3/23/2020 MARITZA PRZEKOP
Green Code Cleared 3/25/2020 DONALD CRICHLOW
Eng Process Fee Ord 176,300 Cleared 4/22/2020 OSCAR GUTIERREZ
Roof/Waste drainage to street Cleared 5/5/2020 OSCAR GUTIERREZ
Grading Pre-Inspection Cleared 5/8/2020 KIRK LINKLATER
Hydrant and Access approval Cleared 6/11/2020 KURT CORRAL
GPI Written Notices Cleared 6/18/2020 MANUEL GARCIA

Contact Information

Contractor Owner-Builder       ,
Engineer Sheikh, Ijaz Ahmed; Lic. No.: S2392 5505 LAKEVIEW CANYON RD      WESTLAKE VILLAGE, CA 91362

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 9/30/2020 Corrections Issued ANDREW NAVE
Excavation/Setback/Form/Re-Bar 10/5/2020 Approved ANDREW NAVE
Final 10/19/2020 Permit Finaled ANDREW NAVE
Footing/Foundation/Slab 10/19/2020 Approved ANDREW NAVE
Green Building Final 10/19/2020 Approved ANDREW NAVE
Green Building Rough 10/19/2020 Approved ANDREW NAVE
Smoke Detectors 10/19/2020 Approved ANDREW NAVE
Wood Frame 10/19/2020 Approved ANDREW NAVE