17854 W CASTELLAMMARE DR 90272

Certificate Information: 17854 W CASTELLAMMARE DR 90272

Application / Permit
17014-30000-06354
Plan Check / Job No.
B17WL07242
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1ST FLOOR ADDITION, 2-STORY GROUND FLOOR ADDITION, AND INTERIOR ALTERATION TO (E) 2-STORY SFD WITH ATTACHED GARAGE.
Permit Issued
Issued on 6/18/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/23/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/12/2017 APPLICANT
Assigned to Plan Check Engineer 1/4/2018 MANUEL GARCIA
Corrections Issued 1/23/2018 BRYAN OSORIO
Quality Review Completed 2/1/2018 JOSE RODRIGUEZ
Building Plans Picked Up 2/2/2018 APPLICANT
Green Plans Picked Up 2/2/2018 APPLICANT
Applicant returned to address corrections 5/31/2018 BRYAN OSORIO
Applicant returned to address corrections 6/12/2018 BRYAN OSORIO
Plan Check Approved 6/14/2018 BRYAN OSORIO
Issued 6/18/2018 LADBS
CofO in Progress 12/18/2020 ANDREW NAVE
Permit Finaled 12/23/2020 VINCENT COTTON
CofO Issued 12/23/2020 VINCENT COTTON
Permit Finaled 12/23/2020 VINCENT COTTON

Permit Application Clearance Information

Grading Pre-Inspection Cleared 1/23/2018 JEFFREY DURAN
Coastal Zone Cleared 5/4/2018 JESSE RAMOS
Roof/Waste drainage to street Cleared 5/4/2018 ADRIAN SANCHEZ
Sewer availability Cleared 5/4/2018 ADRIAN SANCHEZ
Eng Process Fee Ord 176,300 Cleared 5/7/2018 JAMES KHO
Work Adjacent to Public Way Cleared 5/22/2018 HISASHI KOBAYAKAWA
Miscellaneous Cleared 5/31/2018 SUSAN WHISNANT
Green Code Cleared 6/13/2018 BRYAN MEYER

Contact Information

Contractor Pacific Coast Design Group Construction Management & Development; Lic. No.: 1003008-B 16700 BOLLINGER DRIVE      PACIFIC PALISADES, CA 90272
Engineer Sheikh, Ijaz Ahmed; Lic. No.: S2392 5505 LAKEVIEW CANYON RD      WESTLAKE VILLAGE, CA 91362

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2018 Not Ready for Inspection JOHN LUMB
Footing/Foundation/Slab 9/7/2018 Partial Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/12/2018 Partial Approval MICHAEL PELHAM
Excavation/Setback/Form/Re-Bar 9/26/2018 Approved MICHAEL PELHAM
PLUMBING-Rough 9/26/2018 Partial Approval MICHAEL PELHAM
PLUMBING-Rough 2/25/2019 Partial Approval ANDREW NAVE
Sewer 2/25/2019 Not Ready for Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 2/28/2019 Corrections Issued ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 3/5/2019 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/5/2019 Partial Approval ANDREW NAVE
Gas Test 4/5/2019 Approved ANDREW NAVE
ELECTRICAL-Rough 10/10/2019 Approved ANDREW NAVE
PLUMBING-Rough 10/10/2019 Approved ANDREW NAVE
BUILDING-Rough-Frame 10/22/2019 Corrections Issued ANDREW NAVE
Green Building Rough 10/22/2019 Approved ANDREW NAVE
BUILDING-Rough-Frame 10/23/2019 Approved ANDREW NAVE
HVAC-Rough 10/23/2019 Approved ANDREW NAVE
Insulation 11/18/2019 Approved ANDREW NAVE
Interior/Exterior Lathing 11/18/2019 Not Ready for Inspection ANDREW NAVE
Shower Pan 11/18/2019 Approved ANDREW NAVE
Drywall Nailing 12/4/2019 Approved DAVID FEILER
Interior/Exterior Lathing 12/4/2019 Partial Approval DAVID FEILER
Interior/Exterior Lathing 1/9/2020 Approved ANDREW NAVE
HVAC-Final 7/27/2020 Corrections Issued ANDREW NAVE
PLUMBING-Final 7/27/2020 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 9/11/2020 Corrections Issued ANDREW NAVE
Final 9/11/2020 Corrections Issued ANDREW NAVE
HVAC-Final 9/11/2020 Approved ANDREW NAVE
PLUMBING-Final 9/11/2020 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 9/11/2020 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 9/11/2020 Approved ANDREW NAVE
BUILDING-Rough-Frame 10/19/2020 Approved ANDREW NAVE
ELECTRICAL-Final 10/19/2020 Approved ANDREW NAVE
Final 10/19/2020 Corrections Issued ANDREW NAVE
Footing/Foundation/Slab 10/19/2020 Approved ANDREW NAVE
Green Building Final 10/19/2020 Approved ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 10/19/2020 SGSOV Approved ANDREW NAVE
Final 12/18/2020 Conditional Approval ANDREW NAVE