650 E SUNSET AVE 90291

Certificate Information: 650 E SUNSET AVE 90291

Application / Permit
17014-30000-05836
Plan Check / Job No.
B17WL06708
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO AND CHANGE OF USE OF (E) DUPLEX TO SFD WITH ATTACHED GARAGE AT REAR OF LOT.
Permit Issued
Issued on 3/9/2021
Issuing Office
West Los Angeles
Current Status
CofO Issued on 9/29/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/15/2017 APPLICANT
Assigned to Plan Check Engineer 11/21/2017 JAHANSHAH POURHASSAN
Corrections Issued 11/27/2017 BRYAN OSORIO
Green Plans Picked Up 12/1/2017 APPLICANT
Quality Review Completed 12/7/2017 JOSE RODRIGUEZ
Building Plans Picked Up 12/8/2017 APPLICANT
Applicant returned to address corrections 9/14/2018 JAHANSHAH POURHASSAN
Applicant returned to address corrections 5/7/2019 JAHANSHAH POURHASSAN
Plan Check Approved 5/10/2019 JAHANSHAH POURHASSAN
No Progress 5/15/2019 JAHANSHAH POURHASSAN
Plan Check Approved 2/25/2021 JAHANSHAH POURHASSAN
Issued 3/9/2021 APPLICANT
CofO in Progress 9/26/2022 DAVID FEILER
Permit Finaled 9/29/2022 DANIEL ORRANTE
CofO Issued 9/29/2022 DANIEL ORRANTE
Permit Finaled 9/29/2022 DANIEL ORRANTE

Permit Application Clearance Information

Demo/Removal of Rental Units Cleared 2/22/2018 MATTHEW CABRERA
Eng Process Fee Ord 176,300 Cleared 4/3/2018 ADRIAN SANCHEZ
Sewer availability Cleared 4/3/2018 ADRIAN SANCHEZ
Low Impact Development Cleared 5/4/2018 IDA MEISAMI-FARD
Work Adjacent to Public Way Cleared 5/24/2018 BOK GOH
Specific Plan Cleared 5/30/2018 EDER ROMERO
Specific Plan Cleared 5/30/2018 EDER ROMERO
Miscellaneous Cleared 5/31/2018 EDBER MACEDO
Miscellaneous Cleared 5/31/2018 EDBER MACEDO
Miscellaneous Cleared 5/31/2018 EDBER MACEDO
Miscellaneous Cleared 5/31/2018 EDBER MACEDO
ZA Case Cleared 5/31/2018 EDBER MACEDO
ZA Case Cleared 5/31/2018 EDBER MACEDO
Coastal Zone Cleared 1/11/2019 NOAH MCCOY
Frnt yard landscape/Water mgmt Cleared 1/11/2019 NOAH MCCOY
Miscellaneous Cleared 1/11/2019 NOAH MCCOY
Address approval Cleared 5/3/2019 ZIXUAN CHEN
Roof/Waste drainage to street Cleared 1/22/2021 DINAH GARIN
Specific Plan Cleared 1/22/2021 NOAH MCCOY

Contact Information

Architect Daham, Ramsey Walid; Lic. No.: C34257 109 EUCALYPTUS DRIVE      EL SEGUNDO, CA 90245
Architect Mineau,, Kenneth William; Lic. No.: C19133 APPLETON PARTNERS   911 CHAPALA STREET    SANTA BARBARA, CA 93101
Contractor Curb Appeal Construction; Lic. No.: 650380-B 5445 MEADOW VISTA WAY      AGOURA HILLS, CA 91301
Engineer Alexander, Andy Joseph; Lic. No.: C84086 1730 E HOLLY AVE   STE 107    EL SEGUNDO, CA 90245
Engineer Nazari,, Arthur; Lic. No.: C53497 PO BOX 7112      NORTHRIDGE, CA 91327

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 4/15/2021 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 4/15/2021 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 4/16/2021 Conditional Approval JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/30/2021 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 4/30/2021 Partial Approval JOHNNY MIRANDA
Deputy Reinf. Concrete 5/25/2021 Partial Approval PIERRE VEGA
Footing/Foundation/Slab 6/17/2021 Partial Approval JOHNNY MIRANDA
Deputy Steel/Welding 7/1/2021 Conditional Approval AMY COLIN
Deputy Steel/Welding 7/2/2021 No Access for Inspection ADAM ESCOTO
Footing/Foundation/Slab 7/9/2021 Partial Approval JOHNNY MIRANDA
Deputy Wood Construction 8/23/2021 Conditional Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/23/2021 Corrections Issued KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 10/28/2021 Partial Approval BOBBY KEY
Special/Order Compliance 10/28/2021 Partial Inspection DAVID FEILER
Insulation 11/16/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 11/23/2021 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/2/2021 Approved ENRIQUE MIRELES
Green Building Rough 12/2/2021 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/23/2021 Approved ENRIQUE MIRELES
HVAC-Rough 1/18/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 1/20/2022 Partial Approval DAVID FEILER
Sewer 1/20/2022 Partial Approval DAVID FEILER
ELECTRICAL-Rough 2/8/2022 Not Ready for Inspection RYAN SALAZAR
Underground Mechanical 2/8/2022 Partial Approval RYAN SALAZAR
HVAC-Rough 2/16/2022 Approved DAVID FEILER
PLUMBING-Rough 2/16/2022 Approved DAVID FEILER
Shower Pan 3/4/2022 Approved ENRIQUE MIRELES
Underground Mechanical 3/4/2022 Approved ENRIQUE MIRELES
ELECTRICAL-Rough 3/23/2022 Partial Approval RYAN SALAZAR
Wood Frame 3/25/2022 Conditional Approval PATRICK QUALEY
Interior/Exterior Lathing 4/4/2022 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 4/8/2022 Approved DAVID FEILER
Green Building Rough 4/8/2022 Approved DAVID FEILER
Verify Sprinkler Sign Off 4/8/2022 Approved DAVID FEILER
Insulation 4/15/2022 Approved DAVID FEILER
Drywall Nailing 5/9/2022 Approved DAVID FEILER
Gas Test 8/4/2022 Approved STEPHANIE SWANSON
ELECTRICAL-Final 8/31/2022 Corrections Issued DAVID FEILER
PLUMBING-Final 8/31/2022 Approved DAVID FEILER
ELECTRICAL-Final 9/2/2022 Corrections Issued DAVID FEILER
Footing/Foundation/Slab 9/6/2022 Approved DAVID FEILER
HVAC-Final 9/6/2022 Corrections Issued DAVID FEILER
Final 9/7/2022 Corrections Issued DAVID FEILER
Green Building Final 9/7/2022 Approved DAVID FEILER
SGSOV-Seismic Gas S/O Valve 9/7/2022 SGSOV Approved DAVID FEILER
Smoke Detectors 9/7/2022 Approved DAVID FEILER
HVAC-Final 9/8/2022 No Access for Inspection DAVID FEILER
ELECTRICAL-Final 9/9/2022 Not Ready for Inspection DAVID FEILER
HVAC-Final 9/9/2022 Approved DAVID FEILER
Final 9/20/2022 Partial Inspection DAVID FEILER
ELECTRICAL-Final 9/22/2022 Not Ready for Inspection DAVID FEILER
Final 9/22/2022 Partial Inspection DAVID FEILER
ELECTRICAL-Final 9/23/2022 Approved DAVID FEILER
Final 9/23/2022 OK to Issue CofO DAVID FEILER