1124 N LAS PULGAS ROAD 90272
Certificate Information: 1124 N LAS PULGAS ROAD 90272
- Application / Permit
- 17014-30000-05435
- Plan Check / Job No.
- B17WL06189
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) BASEMENT AND GROUND FLOOR ADDITION TO (E) 1-STORY SFD. INTERIOR STRUCTURAL ALTERATION OF EXISTING SPACE.
- Permit Issued
- Issued on 9/18/2018
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/24/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 11/2/2017 | KAVIAN REFAHI |
| Corrections Issued | 11/29/2017 | BRYAN OSORIO |
| Green Plans Picked Up | 12/5/2017 | APPLICANT |
| Quality Review Completed | 12/7/2017 | JOSE RODRIGUEZ |
| Building Plans Picked Up | 12/12/2017 | APPLICANT |
| Applicant returned to address corrections | 1/11/2018 | BRYAN OSORIO |
| Applicant returned to address corrections | 3/28/2018 | BRYAN OSORIO |
| Applicant returned to address corrections | 6/26/2018 | KAVIAN REFAHI |
| Applicant returned to address corrections | 7/11/2018 | KAVIAN REFAHI |
| Applicant returned to address corrections | 8/23/2018 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/6/2018 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 9/12/2018 | KAVIAN REFAHI |
| Issued | 9/18/2018 | LADBS |
| CofO in Progress | 4/19/2024 | EVAN COOPER |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
| CofO Issued | 5/4/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/4/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 12/15/2017 | STEVE MELGAR |
| BHO/Hillside ordinance | Cleared | 1/16/2018 | MARYAM AZARBAYJANI |
| BHO/Hillside ordinance | Cleared | 1/16/2018 | MARYAM AZARBAYJANI |
| BHO/Hillside ordinance | Cleared | 1/16/2018 | MARYAM AZARBAYJANI |
| Sewer availability | Cleared | 1/16/2018 | MARYAM AZARBAYJANI |
| Work Adjacent to Public Way | Cleared | 1/16/2018 | MARYAM AZARBAYJANI |
| Coastal Zone | Cleared | 6/15/2018 | TREVOR MARTIN |
| Eng Process Fee Ord 176,300 | Cleared | 6/18/2018 | STEVEN JIN |
| Landscape for retaining wall | Cleared | 6/18/2018 | TREVOR MARTIN |
| Green Code | Cleared | 7/6/2018 | BRYAN MEYER |
| Low Impact Development | Cleared | 7/6/2018 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 7/6/2018 | ADRIAN SANCHEZ |
| Excavation more than 5-ft deep | Cleared | 9/11/2018 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 9/11/2018 | KAVIAN REFAHI |
| Grading Pre-Inspection | Cleared | 9/11/2018 | KAVIAN REFAHI |
Contact Information
| Architect | Zaghi, Fardad; Lic. No.: C35102 | 20416 OXNARD ST WOODLAND HILLS, CA 91367 |
| Engineer | Berkoz, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
| Engineer | Yenjai, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
| Geologist | Schick, John Wayne; Lic. No.: EG1300 | 7650 HASKELL AVENUE STE D VAN NUYS, CA 91406 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/19/2018 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 1/30/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 2/5/2019 | Partial Approval | ANDREW NAVE |
| Sewer | 2/5/2019 | Partial Approval | ANDREW NAVE |
| Grounding or Bonding | 3/27/2019 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 4/12/2019 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/1/2019 | Partial Approval | ANDREW NAVE |
| Structural Steel Frame | 5/1/2019 | Not Ready for Inspection | ANDREW NAVE |
| Deputy Wood Construction | 5/29/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 5/31/2019 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2019 | Partial Approval | ANDREW NAVE |
| PLUMBING-Rough | 6/18/2019 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 6/25/2019 | Partial Approval | ANDREW NAVE |
| Deputy Wood Construction | 8/9/2019 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 8/12/2019 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 10/7/2019 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 10/15/2019 | Partial Approval | DAVID FEILER |
| HVAC-Rough | 10/18/2019 | Corrections Issued | ANDREW NAVE |
| HVAC-Rough | 11/4/2019 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 11/6/2019 | Corrections Issued | ANDREW NAVE |
| BUILDING-Rough-Frame | 11/8/2019 | Approved | ANDREW NAVE |
| Green Building Rough | 11/8/2019 | Approved | ANDREW NAVE |
| Interior/Exterior Lathing | 11/8/2019 | Partial Approval | ANDREW NAVE |
| Shower Pan | 11/8/2019 | Approved | ANDREW NAVE |
| Verify Sprinkler Sign Off | 11/8/2019 | Approved | ANDREW NAVE |
| Insulation | 11/13/2019 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 11/13/2019 | Approved | ANDREW NAVE |
| Insulation | 11/18/2019 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/25/2019 | Approved | ANDREW NAVE |
| Deputy Shotcrete | 12/17/2019 | Conditional Approval | ANDREW NAVE |
| Interior/Exterior Lathing | 12/31/2019 | Approved | ANDREW NAVE |
| Special/Order Compliance | 8/18/2021 | Approved | ANDREW NAVE |
| Shower Pan | 11/10/2021 | Corrections Issued | ANDREW NAVE |
| Pre-Inspection | 7/22/2022 | Partial Inspection | BRENDAN LOONEY |
| Special/Order Compliance | 7/22/2022 | Corrections Issued | BRENDAN LOONEY |
| Special/Order Compliance | 7/25/2022 | Approved | BRENDAN LOONEY |
| Gas Test | 10/7/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 10/20/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 10/28/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 10/28/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 12/8/2022 | Corrections Issued | BRENDAN LOONEY |
| HVAC-Final | 12/20/2022 | Approved | BRENDAN LOONEY |
| Special/Order Compliance | 12/20/2022 | Partial Inspection | BRENDAN LOONEY |
| Piling/Pier/Caisson | 8/1/2023 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Final | 11/30/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 11/30/2023 | Approved | EVAN COOPER |
| Reinforced Concrete Frame | 11/30/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 11/30/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 11/30/2023 | Approved | EVAN COOPER |
| Final | 12/13/2023 | Conditional Approval | EVAN COOPER |
| Final | 12/14/2023 | OK to Issue CofO | EVAN COOPER |