111 S MAPLETON DR 90024

Certificate Information: 111 S MAPLETON DR 90024

Application / Permit
17014-30000-04541
Plan Check / Job No.
B17WL05243
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(23) Accessory Living Quarters
Work Description
new 2-story accessory living quarter
Permit Issued
Issued on 9/12/2019
Issuing Office
West Los Angeles
Current Status
Permit Finaled on 5/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/8/2017 APPLICANT
Assigned to Plan Check Engineer 9/14/2017 TARIK SAOUD
Corrections Issued 9/18/2017 TARIK SAOUD
Green Plans Picked Up 9/19/2017 APPLICANT
Quality Review Completed 9/22/2017 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 9/26/2017 APPLICANT
Plan Check Approved 6/4/2018 TARIK SAOUD
Issued 9/12/2019 LADBS
Permit Finaled 5/15/2024 STEPHANIE SWANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 9/26/2017 STEVE MELGAR
Sewer availability Cleared 9/26/2017 STEVE MELGAR
Low Impact Development Cleared 5/2/2018 RYAN HUDSON
Hydrant and Access approval Cleared 5/4/2018 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 5/4/2018 ADRIAN SANCHEZ
Grading Pre-Inspection Cleared 5/8/2018 TARIK SAOUD
Green Code Cleared 8/5/2019 RICHARD GARCIA

Contact Information

Contractor Sarlan Builders Inc; Lic. No.: 387668-B 9903 SANTA MONICA BLVD #269      BEVERLY HILLS, CA 90212
Engineer Rybak, Richard; Lic. No.: GE2131 20312 TAU PLACE      CHATSWORTH, CA 91311
Engineer Soliman, John; Lic. No.: C80833 13785 PELICAN DR      RANCHO CUCAMONGA, CA 91739

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 2/11/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 2/13/2020 Partial Approval MATT KELLERMAN
Piling/Pier/Caisson 2/18/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 2/24/2020 Partial Approval KENNETH NAGLE
Deputy Reinf. Concrete 2/25/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 2/28/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 3/20/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 3/24/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 4/7/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 4/16/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 4/21/2020 Conditional Approval KEVIN SARGSYAN
Deputy Drilled-In Anchors 4/29/2020 Conditional Approval KEVIN SARGSYAN
Deputy Reinf. Concrete 4/29/2020 Conditional Approval KEVIN SARGSYAN
Underground Mechanical 5/18/2020 Approved KEVIN SARGSYAN
Deputy Wood Construction 6/8/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 6/25/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/25/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 6/26/2020 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 6/30/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 6/30/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 6/30/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/1/2020 Not Ready for Inspection CARLOS MATAMOROS
Deputy Reinf. Concrete 7/2/2020 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 7/8/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 7/14/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 7/15/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 7/22/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Piling/Pier/Caisson 7/23/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 7/27/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 7/28/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 7/30/2020 Partial Approval MATT KELLERMAN
Deputy Wood Construction 8/3/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Reinf. Concrete 8/6/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 8/12/2020 Conditional Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Not Ready for Inspection MATT KELLERMAN
Underground Mechanical 8/12/2020 Not Ready for Inspection MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Approval ANTHONY MCDOWALL
Deputy Wood Construction 9/9/2020 Conditional Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 9/10/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 9/15/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 9/21/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/5/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/13/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 11/6/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Insulation 11/23/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 11/25/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 12/4/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 12/4/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 12/4/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Deputy Wood Construction 12/7/2020 Conditional Approval CARLOS MATAMOROS
Deputy Steel/Welding 12/15/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 1/7/2021 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 2/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 2/8/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 2/8/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 2/11/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 2/11/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 2/25/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/26/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 4/23/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 4/28/2021 Conditional Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 5/4/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 5/12/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Shower Pan 5/12/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 5/14/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 5/14/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/26/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 5/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 5/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 5/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 5/26/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/9/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 7/9/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 7/9/2021 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 7/19/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 7/21/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 8/6/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 5/26/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 9/14/2022 Corrections Issued STEPHANIE SWANSON
Pre-Inspection 9/14/2022 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 9/19/2022 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 10/21/2022 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 10/27/2022 Partial Approval STEPHANIE SWANSON
Interior/Exterior Lathing 12/7/2022 Partial Approval STEPHANIE SWANSON
ELECTRICAL-Final 5/11/2023 Not Ready for Inspection BRENDAN LOONEY
HVAC-Final 6/16/2023 Corrections Issued STEPHANIE SWANSON
PLUMBING-Final 6/16/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 7/19/2023 Corrections Issued STEPHANIE SWANSON
Final 7/19/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Final 7/19/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 7/19/2023 Not Ready for Inspection STEPHANIE SWANSON
ELECTRICAL-Final 8/9/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 8/9/2023 Approved STEPHANIE SWANSON
BUILDING-Rough-Frame 10/16/2023 Approved STEPHANIE SWANSON
Final 10/16/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 10/16/2023 Approved STEPHANIE SWANSON
Green Building Final 10/16/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 10/16/2023 SGSOV Not Ready STEPHANIE SWANSON
Smoke Detectors 10/16/2023 Approved STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 10/20/2023 SGSOV Approved STEPHANIE SWANSON
Final 12/21/2023 Corrections Issued STEPHANIE SWANSON