1433 N KENTER AVE 90049
Certificate Information: 1433 N KENTER AVE 90049
- Application / Permit
- 17014-30000-03772
- Plan Check / Job No.
- B17WL04337
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 STORY ADDITION TO EXISTING 2 STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE.
- Permit Issued
- Issued on 1/11/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/8/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 8/1/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 8/17/2017 | RICARDO RAMIREZ |
| Corrections Issued | 8/24/2017 | RICARDO RAMIREZ |
| Quality Review Completed | 8/31/2017 | STEVEN KIM |
| Building Plans Picked Up | 9/1/2017 | APPLICANT |
| Green Plans Picked Up | 9/14/2017 | APPLICANT |
| Applicant returned to address corrections | 11/27/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 11/28/2017 | RICARDO RAMIREZ |
| Issued | 1/11/2018 | LADBS |
| CofO in Progress | 11/15/2022 | JUAN VALENZUELA |
| Permit Finaled | 2/8/2023 | DANIEL ORRANTE |
| CofO Issued | 2/8/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/8/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 9/19/2017 | CELINA MORENO |
| Sewer availability | Cleared | 9/19/2017 | CELINA MORENO |
| ZA Case | Cleared | 11/7/2017 | BRIDGETTE WOOTEN |
| Green Code | Cleared | 11/8/2017 | BRYAN MEYER |
| Hydrant and Access approval | Cleared | 11/8/2017 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/8/2017 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 11/8/2017 | JACOB BIGLER |
| BHO/Hillside ordinance | Cleared | 11/28/2017 | ANGEL SALCEDO |
| BHO/Hillside ordinance | Cleared | 11/28/2017 | ANGEL SALCEDO |
| BHO/Hillside ordinance | Cleared | 11/28/2017 | ANGEL SALCEDO |
| Grading Pre-Inspection | Cleared | 11/28/2017 | RICARDO RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Daugherty, Daniel Thomas; Lic. No.: C76588 | 31129 VIA COLINAS STE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Erdelyi, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
| Geologist | Daugherty, Daniel Thomas; Lic. No.: EG2569 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/10/2018 | Corrections Issued | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 4/13/2018 | Partial Approval | KENNETH NAGLE |
| Footing/Foundation/Slab | 4/13/2018 | Partial Approval | KENNETH NAGLE |
| Deputy Reinf. Concrete | 4/20/2018 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/5/2018 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 6/7/2018 | No Access for Inspection | KENNETH NAGLE |
| Footing/Foundation/Slab | 9/26/2018 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 11/28/2018 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 1/24/2020 | Corrections Issued | TIM CHRISTENSEN |
| Green Building Rough | 1/24/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 2/14/2020 | Corrections Issued | TIM CHRISTENSEN |
| Green Building Rough | 2/14/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| BUILDING-Rough-Frame | 5/27/2020 | Corrections Issued | TIM CHRISTENSEN |
| Green Building Rough | 5/27/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 7/1/2020 | Conditional Approval | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 7/23/2020 | Partial Approval | TIM CHRISTENSEN |
| Green Building Rough | 7/23/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 9/4/2020 | Corrections Issued | TIM CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Partial Approval | TIM CHRISTENSEN |
| PLUMBING-Rough | 9/4/2020 | Corrections Issued | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 9/21/2020 | Not Ready for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/21/2020 | Not Ready for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 2/16/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Rough | 2/16/2021 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/24/2021 | Partial Approval | KENNETH NAGLE |
| BUILDING-Rough-Frame | 3/1/2021 | Conditional Approval | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/1/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 3/1/2021 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 3/1/2021 | Approved | JUAN VALENZUELA |
| Insulation | 3/10/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 3/22/2021 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 4/12/2021 | Partial Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Final | 7/21/2022 | Corrections Issued | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Green Building Final | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| HVAC-Final | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 7/21/2022 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 7/21/2022 | Approved | JUAN VALENZUELA |
| Structural Steel Frame | 7/21/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/14/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 11/14/2022 | Approved | JUAN VALENZUELA |
| Final | 11/14/2022 | OK to Issue CofO | JUAN VALENZUELA |
| Footing/Foundation/Slab | 11/14/2022 | Approved | JUAN VALENZUELA |
| Green Building Final | 11/14/2022 | Approved | JUAN VALENZUELA |
| HVAC-Final | 11/14/2022 | Approved | JUAN VALENZUELA |
| PLUMBING-Final | 11/14/2022 | Approved | JUAN VALENZUELA |
| Service/Power Release | 11/14/2022 | Approved | JUAN VALENZUELA |
| Structural Steel Frame | 11/14/2022 | Approved | JUAN VALENZUELA |