2586 N ROSCOMARE ROAD 90077

Certificate Information: 2586 N ROSCOMARE ROAD 90077

Application / Permit
17014-30000-03249
Plan Check / Job No.
B17WL03729
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition of 366 s.f. to an existing SFD
Permit Issued
Issued on 7/21/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 1/19/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/6/2017 APPLICANT
Assigned to Plan Check Engineer 7/6/2017 KAVIAN REFAHI
Corrections Issued 7/6/2017 KAVIAN REFAHI
Applicant returned to address corrections 7/17/2017 KAVIAN REFAHI
Plan Check Approved 7/21/2017 SERGIO SILVA
Issued 7/21/2017 LADBS
CofO in Progress 1/3/2022 CHRISTOPHER WILSON
Permit Finaled 1/19/2022 DANIEL ORRANTE
CofO Issued 1/19/2022 DANIEL ORRANTE
Permit Finaled 1/19/2022 DANIEL ORRANTE

Permit Application Clearance Information

CPC Cleared 7/7/2017 SARAH GOLDMAN
Eng Process Fee Ord 176,300 Cleared 7/7/2017 ALFREDO JARA
Low Impact Development Cleared 7/7/2017 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/18/2017 HISASHI KOBAYAKAWA
Specific Plan Cleared 7/19/2017 WILLIAM HUGHEN

Contact Information

Contractor Gary Silverston Homes; Lic. No.: 488695-B 3480 LOS FLORES CYN      MALIBU, CA 90265
Engineer Erdelyi, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/8/2017 Corrections Issued ANTHONY ANDERSON
Deputy Drilled-In Anchors 8/11/2017 Conditional Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 8/11/2017 Conditional Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 8/11/2017 Conditional Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 8/29/2017 Partial Inspection ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 9/1/2017 Corrections Issued ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 9/6/2017 Partial Approval ANTHONY ANDERSON
Deputy Reinf. Concrete 9/7/2017 Conditional Approval ANTHONY ANDERSON
ELECTRICAL-Rough 9/21/2017 Partial Approval ANTHONY ANDERSON
Excavation/Setback/Form/Re-Bar 9/21/2017 Approved ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/19/2018 Partial Inspection ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 1/30/2018 Approved ANTHONY ANDERSON
BUILDING-Rough-Frame 2/8/2018 Approved ANTHONY ANDERSON
ELECTRICAL-Rough 2/8/2018 Approved ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/8/2018 Approved ANTHONY ANDERSON
Green Building Rough 2/8/2018 Approved ANTHONY ANDERSON
ELECTRICAL-Rough 2/21/2018 Approved ANTHONY ANDERSON
Floor/Roof Diaphrgm/Shear Wall 2/21/2018 Partial Inspection ANTHONY ANDERSON
Insulation 2/21/2018 Approved ANTHONY ANDERSON
Interior/Exterior Lathing 2/21/2018 Approved ANTHONY ANDERSON
Light Gage Steel Frame 2/21/2018 Approved ANTHONY ANDERSON
Structural Steel Frame 2/21/2018 Approved ANTHONY ANDERSON
Drywall Nailing 2/23/2018 Approved ANTHONY ANDERSON
SGSOV-Seismic Gas S/O Valve 12/3/2018 SGSOV Not Ready DANIEL ORRANTE
Final 3/6/2019 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 3/6/2019 Approved CHRISTOPHER WILSON
Green Building Final 3/6/2019 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/6/2019 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 3/6/2019 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 4/27/2019 Partial Inspection CHRISTOPHER WILSON
Final 5/17/2019 Conditional Approval CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/17/2019 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 5/17/2019 Approved CHRISTOPHER WILSON