342 N CITRUS AVE 90036
Certificate Information: 342 N CITRUS AVE 90036
- Application / Permit
- 17014-30000-03135
- Plan Check / Job No.
- B17WL03615
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel of (E) 1-story SFD to 2-story SFD with detached garage. Remodel includes conversion of attic space to livable space
- Permit Issued
- Issued on 12/21/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 8/10/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Building Plans Picked Up | 6/2/2017 | APPLICANT |
| Submitted | 6/29/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/13/2017 | DIEGO BAUTISTA |
| Corrections Issued | 7/20/2017 | DIEGO BAUTISTA |
| Quality Review Completed | 7/21/2017 | STEVEN KIM |
| Green Plans Picked Up | 8/8/2017 | APPLICANT |
| Plan Check Approved | 8/22/2017 | DIEGO BAUTISTA |
| Issued | 12/21/2017 | LADBS |
| CofO in Progress | 8/5/2021 | ARTHUR SARGSYAN |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
| CofO Issued | 8/10/2021 | DEROLD HAUFF |
| Permit Finaled | 8/10/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 8/10/2017 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 8/10/2017 | ROBERT DUFF |
| Sewer availability | Cleared | 8/10/2017 | RAVIL MANAPOV |
| Green Code | Cleared | 8/17/2017 | DIEGO BAUTISTA |
Contact Information
| Architect | Musolino, John Michael; Lic. No.: C33574 | 217 PALOS VERDES BLVD # 137 REDONDO BEACH, CA 90277 |
| Contractor | Plata Construction Inc; Lic. No.: 1003544-B | 4335 W ROSECRANS AVENUE APARTMENT 2 HAWTHORNE, CA 90250 |
| Engineer | Trevellin, Maurizio; Lic. No.: C71368 | 707 ASHLAND AVE 2 SANTA MONICA, CA 90405 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/1/2018 | Approved | DANNY TOLENTINO |
| Footing/Foundation/Slab | 2/1/2018 | Approved | DANNY TOLENTINO |
| METHANE-Barrier | 2/1/2018 | Approved | DANNY TOLENTINO |
| METHANE-Subgrade | 2/1/2018 | Approved | DANNY TOLENTINO |
| Deputy Drilled-In Anchors | 2/2/2018 | No Access for Inspection | DANNY TOLENTINO |
| PLUMBING-Rough | 5/31/2018 | Partial Approval | DANNY TOLENTINO |
| Shower Pan | 6/12/2018 | Approved | DANNY TOLENTINO |
| BUILDING-Rough-Frame | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| Green Building Rough | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| HVAC-Rough | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| Interior/Exterior Lathing | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| METHANE-Rough | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| PLUMBING-Rough | 6/25/2018 | Not Ready for Inspection | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 6/28/2018 | Not Ready for Inspection | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2018 | Corrections Issued | BRAD BESCOS |
| HVAC-Rough | 6/28/2018 | Corrections Issued | DANNY TOLENTINO |
| PLUMBING-Rough | 6/28/2018 | Corrections Issued | BRAD BESCOS |
| Interior/Exterior Lathing | 7/2/2018 | Partial Approval | BRAD BESCOS |
| Rough-Elec/Plmb/HVAC | 7/2/2018 | Approved | BRAD BESCOS |
| Green Building Rough | 7/17/2018 | Approved | DANNY TOLENTINO |
| Insulation | 7/17/2018 | Partial Approval | DANNY TOLENTINO |
| Drywall Nailing | 8/3/2018 | Approved | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 9/11/2018 | Partial Approval | DANNY TOLENTINO |
| Interior/Exterior Lathing | 9/11/2018 | Corrections Issued | DANNY TOLENTINO |
| Interior/Exterior Lathing | 9/13/2018 | Partial Approval | DANNY TOLENTINO |
| Insulation | 9/19/2018 | Approved | DANNY TOLENTINO |
| Drywall Nailing | 9/27/2018 | Approved | DANNY TOLENTINO |
| ELECTRICAL-Final | 3/26/2019 | Not Ready for Inspection | LUIS BARRALES |
| HVAC-Final | 3/26/2019 | Not Ready for Inspection | LUIS BARRALES |
| PLUMBING-Final | 3/26/2019 | Not Ready for Inspection | LUIS BARRALES |
| SGSOV-Seismic Gas S/O Valve | 4/26/2019 | SGSOV Not Ready | DANIEL GONZALEZ |
| SGSOV-Seismic Gas S/O Valve | 4/30/2019 | SGSOV Not Ready | DANIEL GONZALEZ |
| ELECTRICAL-Final | 5/22/2019 | Corrections Issued | DANIEL GONZALEZ |
| Final | 5/22/2019 | Corrections Issued | DANIEL GONZALEZ |
| HVAC-Final | 5/22/2019 | Corrections Issued | DANIEL GONZALEZ |
| PLUMBING-Final | 5/22/2019 | Corrections Issued | DANIEL GONZALEZ |
| BUILDING-Rough-Frame | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| Final | 7/23/2020 | Not Ready for Inspection | ARTHUR SARGSYAN |
| Green Building Final | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Final | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Final | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Final | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/23/2020 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 7/23/2020 | Approved | ARTHUR SARGSYAN |
| Final | 8/4/2021 | OK to Issue CofO | ARTHUR SARGSYAN |