7620 W WILLOW GLEN ROAD 90046
Certificate Information: 7620 W WILLOW GLEN ROAD 90046
- Application / Permit
- 17014-30000-02833
- Plan Check / Job No.
- B17WL03243
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2 story ground floor addition to existing 2 story single family dwelling with attached garage.
- Permit Issued
- Issued on 6/14/2018
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/14/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 7/6/2017 | RICARDO RAMIREZ |
| Green Plans Picked Up | 7/7/2017 | APPLICANT |
| Corrections Issued | 7/17/2017 | RICARDO RAMIREZ |
| Quality Review Completed | 7/21/2017 | STEVEN KIM |
| Building Plans Picked Up | 8/3/2017 | APPLICANT |
| Applicant returned to address corrections | 9/6/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 10/13/2017 | RICARDO RAMIREZ |
| Plan Check Approved | 1/17/2018 | RICARDO RAMIREZ |
| Plan Check Approved | 4/17/2018 | RICARDO RAMIREZ |
| Plan Check Approved | 6/1/2018 | RICARDO RAMIREZ |
| Issued | 6/14/2018 | LADBS |
| CofO in Progress | 1/31/2023 | STUART CHAPMAN |
| Permit Finaled | 3/25/2023 | DANIEL ORRANTE |
| CofO Issued | 3/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/29/2017 | RAVIL MANAPOV |
| BHO/Hillside ordinance | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Hydrant and Access approval | Cleared | 8/29/2017 | ROBERT DUFF |
| Low Impact Development | Cleared | 8/29/2017 | SAM NAVID |
| Roof/Waste drainage to street | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Sewer availability | Cleared | 8/29/2017 | RAVIL MANAPOV |
| Grading Pre-Inspection | Cleared | 9/6/2017 | RICARDO RAMIREZ |
| Green Code | Cleared | 9/7/2017 | RICHARD GARCIA |
| BHO/Hillside ordinance | Cleared | 9/13/2017 | ROCHELLE DUNGCA |
Contact Information
| Contractor | Specialized Home Builders Inc; Lic. No.: 903190-B | 2355 WESTWOOD BLVD #388 LOS ANGELES, CA 90064 |
| Engineer | Azizisefat, Solayman; Lic. No.: C57840 | 19510 VENTURA BLVD STE 110 TARZANA, CA 91356 |
| Engineer | Balshem, Efim Bercovich; Lic. No.: C34313 | 1125 16TH ST UNIT 5 SANTA MONICA, CA 90403 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Steel/Welding | 11/6/2019 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/8/2019 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 11/18/2019 | Partial Approval | RAUL BARAJAS |
| Deputy Wood Construction | 12/10/2019 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 12/12/2019 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 12/18/2019 | Approved | RAUL BARAJAS |
| Structural Steel Frame | 1/16/2020 | Conditional Approval | RAUL BARAJAS |
| PLUMBING-Rough | 1/30/2020 | Partial Approval | RAUL BARAJAS |
| Structural Steel Frame | 1/30/2020 | Approved | RAUL BARAJAS |
| Deputy Wood Construction | 1/31/2020 | Conditional Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2020 | Partial Approval | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 4/27/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2020 | Corrections Issued | RAUL BARAJAS |
| Green Building Rough | 4/27/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 4/27/2020 | Partial Approval | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 4/27/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 4/30/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/25/2020 | Approved | RAUL BARAJAS |
| Gas Test | 6/25/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 8/21/2020 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/3/2020 | Approved | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/3/2020 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 1/13/2021 | Approved | RAUL BARAJAS |
| Green Building Rough | 1/13/2021 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 1/13/2021 | Approved | RAUL BARAJAS |
| Shower Pan | 6/10/2021 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/23/2021 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 12/1/2022 | Approved | RAUL BARAJAS |
| Final | 12/1/2022 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 12/1/2022 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/1/2022 | Approved | RAUL BARAJAS |
| Final | 12/29/2022 | OK for TCO | STUART CHAPMAN |
| Service/Power Release | 12/29/2022 | Approved | STUART CHAPMAN |
| Final | 1/31/2023 | OK to Issue CofO | STUART CHAPMAN |