10231 W CHARING CROSS ROAD 90024

Certificate Information: 10231 W CHARING CROSS ROAD 90024

Application / Permit
17014-30000-02697
Plan Check / Job No.
B17WL03097
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel and addition to existing 2 story house over basement level.
Permit Issued
Issued on 11/16/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/26/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/7/2017 APPLICANT
Assigned to Plan Check Engineer 6/15/2017 RICARDO RAMIREZ
Corrections Issued 6/18/2017 RICARDO RAMIREZ
Green Plans Picked Up 6/23/2017 APPLICANT
Quality Review Completed 6/30/2017 STEVEN KIM
Building Plans Picked Up 7/5/2017 APPLICANT
Applicant returned to address corrections 9/29/2017 RICARDO RAMIREZ
Applicant returned to address corrections 10/11/2017 RICARDO RAMIREZ
Plan Check Approved 10/13/2017 RICARDO RAMIREZ
Issued 11/16/2017 LADBS
CofO in Progress 6/17/2022 CHRISTOPHER WILSON
No Progress 6/18/2022 MICHAEL PELHAM
CofO in Progress 6/23/2022 MICHAEL PELHAM
Permit Finaled 7/26/2022 KENNETH NAGLE
CofO Issued 7/26/2022 KENNETH NAGLE
Permit Finaled 7/26/2022 KENNETH NAGLE

Permit Application Clearance Information

Hydrant and Access approval Cleared 6/23/2017 GILBERT URREA
Eng Process Fee Ord 176,300 Cleared 6/26/2017 YESENIA DIAZ
Sewer availability Cleared 6/26/2017 YESENIA DIAZ
ZA Case Cleared 6/26/2017 DANIEL SKOLNICK
ZA Case Cleared 6/26/2017 DANIEL SKOLNICK
Low Impact Development Cleared 10/3/2017 IDA MEISAMI-FARD
Roof/Waste drainage to street Cleared 10/3/2017 NAZILA NOORIFAR
Green Code Cleared 10/5/2017 RICHARD GARCIA
Grading Pre-Inspection Cleared 10/13/2017 RICARDO RAMIREZ

Contact Information

Engineer Daugherty, Daniel Thomas; Lic. No.: C76588 31129 VIA COLINAS STE 707      WESTLAKE VILLAGE, CA 91362
Engineer Garcia, Lionel Jesus; Lic. No.: S4653 23890 HAWTHORNE BLVD      TORRANCE, CA 90505
Geologist Daugherty, Daniel Thomas; Lic. No.: EG2569 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Deputy Steel/Welding 5/22/2018 Conditional Approval JOEL LAUNCHBAUGH
Footing/Foundation/Slab 6/28/2018 Partial Approval JOEL LAUNCHBAUGH
Footing/Foundation/Slab 7/16/2018 Partial Approval JOEL LAUNCHBAUGH
Deputy Steel/Welding 7/20/2018 Approved MATT KELLERMAN
Reinforced Concrete Frame 7/31/2018 Partial Approval JOEL LAUNCHBAUGH
Structural Steel Frame 7/31/2018 Partial Approval JOEL LAUNCHBAUGH
Footing/Foundation/Slab 8/21/2018 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 8/29/2018 Partial Approval JOHN LUMB
Footing/Foundation/Slab 9/17/2018 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 9/17/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 9/19/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 9/20/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/15/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/19/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 10/19/2018 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/19/2018 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 10/22/2018 Conditional Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 10/25/2018 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 10/26/2018 Corrections Issued CHRISTOPHER WILSON
Reinforced Concrete Frame 10/30/2018 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 11/2/2018 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/9/2018 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 11/16/2018 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/4/2018 Partial Approval CARLOS MATAMOROS
Deputy Drilled-In Anchors 12/13/2018 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 12/18/2018 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 1/7/2019 Partial Approval MATT KELLERMAN
Wood Frame 1/7/2019 Partial Approval MATT KELLERMAN
Deputy Wood Construction 2/19/2019 Conditional Approval CHRISTOPHER WILSON
Sewer 2/19/2019 Partial Approval CHRISTOPHER WILSON
Wood Frame 2/26/2019 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/14/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/14/2019 Partial Inspection CHRISTOPHER WILSON
Wood Frame 3/14/2019 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/18/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 3/26/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/26/2019 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 4/1/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/18/2019 Partial Approval MICHAEL TEMPLE
Deputy Reinf. Concrete 4/19/2019 Conditional Approval MICHAEL TEMPLE
Deputy Drilled-In Anchors 4/22/2019 Conditional Approval MICHAEL TEMPLE
Footing/Foundation/Slab 4/23/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 4/25/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 4/25/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/1/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/2/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/3/2019 Partial Approval CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/6/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/6/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/6/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/6/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 5/17/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/20/2019 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/20/2019 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 5/23/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Reinf. Concrete 5/24/2019 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/24/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 5/29/2019 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 5/30/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 5/31/2019 Conditional Approval ANTHONY MCDOWALL
BUILDING-Rough-Frame 6/3/2019 Partial Approval CHRISTOPHER WILSON
Deputy Wood Construction 6/3/2019 Partial Approval CHRISTOPHER WILSON
Green Building Rough 6/3/2019 Partial Inspection CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/7/2019 Conditional Approval CHRISTOPHER WILSON
Deputy Steel/Welding 6/7/2019 Conditional Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 6/10/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/11/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/11/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/12/2019 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/12/2019 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 6/18/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 6/18/2019 Partial Approval CHRISTOPHER WILSON
Wood Frame 6/19/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 6/21/2019 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/26/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/27/2019 Conditional Approval MICHAEL TEMPLE
Deputy Drilled-In Anchors 6/28/2019 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 6/28/2019 Conditional Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 6/28/2019 Partial Approval CHRISTOPHER WILSON
Deputy Drilled-In Anchors 7/26/2019 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 7/29/2019 Partial Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 7/29/2019 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 8/2/2019 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 8/8/2019 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 8/16/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/16/2019 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 8/21/2019 Corrections Issued MICHAEL TEMPLE
Deputy Drilled-In Anchors 9/3/2019 Partial Approval CHRISTOPHER WILSON
Deputy Steel/Welding 9/3/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/3/2019 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/5/2019 Partial Approval ANTHONY MCDOWALL
Interior/Exterior Lathing 9/5/2019 Partial Approval ANTHONY MCDOWALL
Deputy Wood Construction 9/11/2019 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 9/11/2019 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/17/2019 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 9/17/2019 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/18/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/18/2019 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/19/2019 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/25/2019 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/26/2019 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 9/27/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 9/30/2019 Partial Approval ANTHONY MCDOWALL
BUILDING-Rough-Frame 10/7/2019 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 10/7/2019 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 10/7/2019 Partial Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 10/8/2019 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 10/8/2019 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/16/2019 Not Ready for Inspection MATT KELLERMAN
PLUMBING-Rough 10/16/2019 Partial Approval MATT KELLERMAN
Floor/Roof Diaphrgm/Shear Wall 10/18/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 10/18/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 10/22/2019 Not Ready for Inspection MATT KELLERMAN
Wood Frame 10/22/2019 Not Ready for Inspection MATT KELLERMAN
Interior/Exterior Lathing 10/28/2019 Partial Approval DANNY TOLENTINO
Insulation 10/29/2019 Partial Approval ANTHONY MCDOWALL
Wood Frame 10/29/2019 Partial Approval ANTHONY MCDOWALL
Pool Piping 10/31/2019 Partial Approval ANTHONY MCDOWALL
Structural Steel Frame 10/31/2019 Partial Approval ANTHONY MCDOWALL
Deputy Reinf. Concrete 11/1/2019 Conditional Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 11/4/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 11/6/2019 Partial Approval ANTHONY MCDOWALL
Shower Pan 11/6/2019 Not Ready for Inspection ANTHONY MCDOWALL
Shower Pan 11/8/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 11/14/2019 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/14/2019 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 11/18/2019 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/18/2019 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 11/20/2019 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 11/20/2019 Corrections Issued CHRISTOPHER WILSON
Deputy Drilled-In Anchors 11/26/2019 Conditional Approval ANTHONY MCDOWALL
HVAC-Rough 11/26/2019 Not Ready for Inspection ANTHONY MCDOWALL
Structural Steel Frame 11/26/2019 Partial Approval ANTHONY MCDOWALL
HVAC-Rough 12/3/2019 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/5/2019 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 12/9/2019 Partial Approval ANTHONY MCDOWALL
PLUMBING-Rough 12/9/2019 Partial Approval ANTHONY MCDOWALL
Drywall Nailing 12/11/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 12/16/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/16/2019 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 12/18/2019 Partial Inspection CHRISTOPHER WILSON
Drywall Nailing 12/19/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 12/19/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 1/3/2020 Corrections Issued CHRISTOPHER WILSON
Insulation 1/6/2020 Partial Approval ANTHONY MCDOWALL
Deputy Steel/Welding 1/7/2020 Conditional Approval ANTHONY MCDOWALL
ELECTRICAL-Rough 1/9/2020 Corrections Issued ANTHONY MCDOWALL
PLUMBING-Rough 1/9/2020 Not Ready for Inspection ANTHONY MCDOWALL
PLUMBING-Rough 1/13/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Deputy Steel/Welding 1/16/2020 Approved MATT KELLERMAN
Deputy Steel/Welding 1/16/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 1/16/2020 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 1/16/2020 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 1/16/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 1/16/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 1/27/2020 Partial Approval MATT KELLERMAN
Deputy Drilled-In Anchors 1/31/2020 Conditional Approval MATT KELLERMAN
Drywall Nailing 1/31/2020 No Access for Inspection MATT KELLERMAN
Drywall Nailing 2/5/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 2/5/2020 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 2/7/2020 Corrections Issued ANTHONY MCDOWALL
HVAC-Rough 2/11/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 2/11/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 2/11/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 2/11/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 2/13/2020 Not Ready for Inspection MATT KELLERMAN
Insulation 2/18/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Deputy Drilled-In Anchors 2/20/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/21/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 2/21/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 2/28/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 3/2/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 3/3/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 3/5/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Insulation 3/9/2020 Approved ANTHONY MCDOWALL
Drywall Nailing 3/20/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 3/20/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 3/20/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 4/1/2020 Partial Inspection ANTHONY MCDOWALL
ELECTRICAL-Rough 4/7/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/7/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/9/2020 Not Ready for Inspection ANTHONY MCDOWALL
ELECTRICAL-Rough 4/10/2020 No Access for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 4/14/2020 Not Ready for Inspection ANTHONY MCDOWALL
HVAC-Rough 4/14/2020 Partial Inspection ANTHONY MCDOWALL
Special/Order Compliance 4/14/2020 Approved MATTHEW NUCKOLLS
Special/Order Compliance 4/15/2020 Corrections Issued ANTHONY MCDOWALL
Pre-Inspection 4/28/2020 Partial Approval MATT KELLERMAN
ELECTRICAL-Rough 5/11/2020 Corrections Issued CHRISTOPHER WILSON
Drywall Nailing 5/14/2020 Partial Approval CARLOS MATAMOROS
ELECTRICAL-Rough 5/14/2020 Partial Approval CARLOS MATAMOROS
Interior/Exterior Lathing 5/28/2020 Partial Approval CARLOS MATAMOROS
Drywall Nailing 6/18/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 6/22/2020 Partial Approval CHRISTOPHER WILSON
Gas Test 7/10/2020 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 7/10/2020 Corrections Issued CARLOS MATAMOROS
Drywall Nailing 7/23/2020 Partial Approval ANTHONY MCDOWALL
Insulation 7/29/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 7/30/2020 Partial Approval ANTHONY MCDOWALL
Drywall Nailing 9/9/2020 Not Ready for Inspection ANTHONY MCDOWALL
Drywall Nailing 9/25/2020 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 9/25/2020 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 10/6/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 10/8/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 10/13/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 10/30/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 1/21/2021 Partial Approval CHRISTOPHER WILSON
Masonry Wall/Backfill 2/5/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/18/2021 Conditional Approval MATT KELLERMAN
Drywall Nailing 2/22/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 2/22/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Underground Mechanical 3/17/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/19/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 4/21/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 5/4/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 5/11/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 5/18/2021 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 5/18/2021 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Rough 5/19/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 5/20/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Gas Test 6/17/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Gas Test 6/24/2021 Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 7/13/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Service/Power Release 7/13/2021 Partial Approval ANTHONY MCDOWALL
Insulation 7/29/2021 Approved DANIEL ORRANTE
Drywall Nailing 8/10/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 8/16/2021 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Sewer 8/16/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 8/19/2021 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 8/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 8/25/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 8/31/2021 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 10/6/2021 Partial Approval MATT KELLERMAN
Service/Power Release 10/7/2021 Approved MATT KELLERMAN
Pre-Inspection 10/26/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Rough 11/23/2021 Not Ready for Inspection CHRISTOPHER WILSON
Pre-Inspection 12/1/2021 Partial Approval CHRISTOPHER WILSON
HVAC-Final 12/6/2021 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 12/8/2021 Partial Approval DEANDRE HOFFMAN
HVAC-Final 1/24/2022 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Final 1/27/2022 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 2/11/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 2/11/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 2/14/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 2/16/2022 Partial Approval CHRISTOPHER WILSON
Gas Test 2/16/2022 Approved CHRISTOPHER WILSON
PLUMBING-Final 2/16/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 2/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 2/25/2022 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 2/25/2022 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 3/2/2022 Approved CHRISTOPHER WILSON
HVAC-Final 3/3/2022 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/17/2022 Approved CHRISTOPHER WILSON
Final 3/17/2022 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 3/17/2022 Approved CHRISTOPHER WILSON
Green Building Rough 3/17/2022 Approved CHRISTOPHER WILSON
HVAC-Final 3/17/2022 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 3/17/2022 SGSOV Not Ready CHRISTOPHER WILSON
Smoke Detectors 3/17/2022 Approved CHRISTOPHER WILSON
HVAC-Final 3/21/2022 Approved CHRISTOPHER WILSON
Final 5/17/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Final 5/17/2022 Corrections Issued CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 5/17/2022 SGSOV Approved CHRISTOPHER WILSON
Final 5/19/2022 Not Ready for Inspection CHRISTOPHER WILSON
Green Building Final 5/19/2022 Approved CHRISTOPHER WILSON
Final 6/13/2022 OK to Issue CofO CHRISTOPHER WILSON
Green Building Final 6/13/2022 Approved CHRISTOPHER WILSON