2006 S CLYDE AVE 90016

Certificate Information: 2006 S CLYDE AVE 90016

Application / Permit
17014-30000-02006
Plan Check / Job No.
B17WL02354
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 story addition to existing 1 story single family dwelling.
Permit Issued
Issued on 5/1/2018
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2017 APPLICANT
Assigned to Plan Check Engineer 5/19/2017 RICARDO RAMIREZ
Corrections Issued 5/22/2017 RICARDO RAMIREZ
Quality Review Completed 5/30/2017 STEVEN KIM
Building Plans Picked Up 6/8/2017 APPLICANT
Green Plans Picked Up 6/8/2017 APPLICANT
Applicant returned to address corrections 7/19/2017 RICARDO RAMIREZ
Applicant returned to address corrections 8/4/2017 RICARDO RAMIREZ
Plan Check Approved 8/31/2017 RICARDO RAMIREZ
Plan Check Approved 1/11/2018 RICARDO RAMIREZ
Plan Check Approved 3/6/2018 RICARDO RAMIREZ
Issued 5/1/2018 LADBS
CofO in Progress 11/10/2021 STUART CHAPMAN
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Low Impact Development Cleared 8/4/2017 MATTHEW JIMENEZ
Eng Process Fee Ord 176,300 Cleared 8/8/2017 ROSE MARIE SMITH
Roof/Waste drainage to street Cleared 8/8/2017 ROSE MARIE SMITH
Sewer availability Cleared 8/8/2017 ROSE MARIE SMITH
Green Code Cleared 8/17/2017 RICHARD GARCIA

Contact Information

Architect Khoudikian, Kaaren G; Lic. No.: C13183 221 E GLENOAKS BLVD # 230      GLENDALE, CA 91207
Contractor Owner-Builder       ,
Engineer Yenjai, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/30/2018 Corrections Issued AJA COLLAY
Footing/Foundation/Slab 9/6/2018 Approved KATHRYN BUTTERWORTH
Deputy Drilled-In Anchors 10/10/2018 Conditional Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/24/2018 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 10/24/2018 Not Ready for Inspection KATHRYN BUTTERWORTH
Green Building Rough 10/24/2018 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 10/24/2018 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 10/24/2018 Partial Approval KATHRYN BUTTERWORTH
Floor/Roof Diaphrgm/Shear Wall 11/2/2018 Approved KATHRYN BUTTERWORTH
Green Building Rough 11/2/2018 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 11/15/2018 Partial Approval KATHRYN BUTTERWORTH
Green Building Rough 11/15/2018 Not Ready for Inspection KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 5/16/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/16/2019 Approved KATHRYN BUTTERWORTH
Green Building Rough 5/16/2019 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 5/16/2019 Approved KATHRYN BUTTERWORTH
PLUMBING-Rough 5/16/2019 Approved KATHRYN BUTTERWORTH
Insulation 6/4/2019 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 6/4/2019 Partial Approval KATHRYN BUTTERWORTH
Drywall Nailing 7/8/2019 Approved KATHRYN BUTTERWORTH
Interior/Exterior Lathing 8/26/2019 Approved KATHRYN BUTTERWORTH
Shower Pan 8/26/2019 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/25/2020 Corrections Issued DAVID CHAN
Gas Test 3/25/2020 Not Ready for Inspection DAVID CHAN
Green Building Rough 3/25/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 5/11/2020 No Access for Inspection MATTHEW NUCKOLLS
Drywall Nailing 5/12/2020 Approved SABAS ALONSO
Insulation 5/12/2020 Approved SABAS ALONSO
ELECTRICAL-Final 7/19/2021 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 7/19/2021 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/11/2021 Approved FREDDIE RIVERA
HVAC-Final 8/11/2021 Approved FREDDIE RIVERA
PLUMBING-Final 8/11/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/28/2021 Approved STUART CHAPMAN
Final 9/28/2021 Conditional Approval STUART CHAPMAN
Green Building Final 9/28/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 9/28/2021 Approved STUART CHAPMAN