2334 N VESTAL AVE 90026

Certificate Information: 2334 N VESTAL AVE 90026

Application / Permit
17014-30000-00991
Plan Check / Job No.
B17WL01247
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition and 2nd floor addition to (E) 2-Story SFD with attached garage. Include interior remodel to kitchen, bathrooms, bedrooms and layout of dwelling.
Permit Issued
Issued on 8/10/2017
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/8/2017 APPLICANT
Assigned to Plan Check Engineer 3/23/2017 KAVIAN REFAHI
Corrections Issued 3/28/2017 DIEGO BAUTISTA
Quality Review Completed 3/29/2017 STEVEN KIM
Building Plans Picked Up 3/31/2017 APPLICANT
Green Plans Picked Up 3/31/2017 APPLICANT
Applicant returned to address corrections 7/25/2017 DIEGO BAUTISTA
Plan Check Approved 8/10/2017 DIEGO BAUTISTA
Issued 8/10/2017 LADBS
CofO in Progress 12/7/2022 THOMAS LOGRASSO
Permit Finaled 12/13/2022 DEROLD HAUFF
CofO Issued 12/13/2022 DEROLD HAUFF
Permit Finaled 12/13/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/28/2017 SEVAK ISAKHAYAN
Hydrant and Access approval Cleared 6/28/2017 JOHN CONNEALLY
Sewer availability Cleared 6/28/2017 SEVAK ISAKHAYAN
Low Impact Development Cleared 7/11/2017 RYAN HUDSON
Roof/Waste drainage to street Cleared 7/11/2017 ADRIAN SANCHEZ
Green Code Cleared 7/13/2017 BRYAN MEYER

Contact Information

Architect Lin, Juintow; Lic. No.: C33054 34586 CALLE NARANJA      CAPISTRANO BEACH, CA 92624
Contractor Create R E Inc; Lic. No.: 999515-B 909 NORTH SEPULVEDA #385      EL SEGUNDO, CA 90245
Engineer Melchor, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/18/2017 Not Ready for Inspection MATTHEW NUCKOLLS
Excavation/Setback/Form/Re-Bar 12/20/2017 Partial Approval DAVID CHAN
PLUMBING-Rough 12/28/2017 Partial Approval DAVID CHAN
Excavation/Setback/Form/Re-Bar 1/3/2018 Corrections Issued DAVID CHAN
PLUMBING-Rough 1/3/2018 Not Ready for Inspection DAVID CHAN
Footing/Foundation/Slab 1/8/2018 Not Ready for Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 1/22/2018 Partial Approval DAVID CHAN
Footing/Foundation/Slab 1/26/2018 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 6/4/2018 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 10/9/2018 Partial Inspection DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 11/19/2018 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 11/21/2018 Partial Approval DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 2/22/2019 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 4/25/2019 Not Ready for Inspection DAVID CHAN
HVAC-Rough 5/20/2019 Conditional Approval DAVID CHAN
PLUMBING-Rough 5/20/2019 Approved DAVID CHAN
BUILDING-Rough-Frame 6/18/2019 Corrections Issued DAVID CHAN
Rough-Elec/Plmb/HVAC 6/18/2019 Corrections Issued DAVID CHAN
Interior/Exterior Lathing 8/23/2019 Partial Approval RUBEN SALAS
Interior/Exterior Lathing 9/3/2019 Not Ready for Inspection DAVID CHAN
Shower Pan 9/3/2019 Not Ready for Inspection DAVID CHAN
Insulation 9/9/2019 Approved DAVID CHAN
Drywall Nailing 10/3/2019 Approved DAVID CHAN
Green Building Rough 10/3/2019 Approved DAVID CHAN
Interior/Exterior Lathing 10/3/2019 Approved DAVID CHAN
ELECTRICAL-Final 2/4/2020 Not Ready for Inspection AJA COLLAY
Special/Order Compliance 3/3/2020 Partial Inspection DAVID CHAN
BUILDING-Rough-Frame 3/19/2020 Not Ready for Inspection RUBEN SALAS
Final 3/19/2020 Not Ready for Inspection RUBEN SALAS
Footing/Foundation/Slab 3/19/2020 Not Ready for Inspection RUBEN SALAS
Green Building Final 3/19/2020 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 3/19/2020 SGSOV Not Ready RUBEN SALAS
Smoke Detectors 3/19/2020 Not Ready for Inspection RUBEN SALAS
Special/Order Compliance 5/19/2020 Corrections Issued DAVID CHAN
Special/Order Compliance 9/15/2020 Partial Inspection DAVID CHAN
Footing/Foundation/Slab 12/20/2021 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 1/19/2022 Partial Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 6/27/2022 SGSOV Not Ready THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/2/2022 SGSOV Not Ready THOMAS LOGRASSO
ELECTRICAL-Final 8/4/2022 Corrections Issued THOMAS LOGRASSO
HVAC-Final 8/4/2022 Corrections Issued THOMAS LOGRASSO
PLUMBING-Final 8/4/2022 Corrections Issued THOMAS LOGRASSO
BUILDING-Rough-Frame 8/10/2022 Not Ready for Inspection THOMAS LOGRASSO
Final 8/10/2022 Corrections Issued THOMAS LOGRASSO
Footing/Foundation/Slab 8/10/2022 Not Ready for Inspection THOMAS LOGRASSO
Green Building Final 8/10/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Not Ready THOMAS LOGRASSO
Smoke Detectors 8/10/2022 Approved THOMAS LOGRASSO
Special/Order Compliance 9/27/2022 Partial Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Not Ready THOMAS LOGRASSO
BUILDING-Rough-Frame 12/2/2022 Approved THOMAS LOGRASSO
Final 12/2/2022 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 12/2/2022 Approved THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 12/2/2022 SGSOV Approved THOMAS LOGRASSO
Final 12/6/2022 OK to Issue CofO THOMAS LOGRASSO
Service/Power Release 12/6/2022 Approved THOMAS LOGRASSO