2334 N VESTAL AVE 90026
Certificate Information: 2334 N VESTAL AVE 90026
- Application / Permit
- 17014-30000-00991
- Plan Check / Job No.
- B17WL01247
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition and 2nd floor addition to (E) 2-Story SFD with attached garage. Include interior remodel to kitchen, bathrooms, bedrooms and layout of dwelling.
- Permit Issued
- Issued on 8/10/2017
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/13/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/8/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/23/2017 | KAVIAN REFAHI |
| Corrections Issued | 3/28/2017 | DIEGO BAUTISTA |
| Quality Review Completed | 3/29/2017 | STEVEN KIM |
| Building Plans Picked Up | 3/31/2017 | APPLICANT |
| Green Plans Picked Up | 3/31/2017 | APPLICANT |
| Applicant returned to address corrections | 7/25/2017 | DIEGO BAUTISTA |
| Plan Check Approved | 8/10/2017 | DIEGO BAUTISTA |
| Issued | 8/10/2017 | LADBS |
| CofO in Progress | 12/7/2022 | THOMAS LOGRASSO |
| Permit Finaled | 12/13/2022 | DEROLD HAUFF |
| CofO Issued | 12/13/2022 | DEROLD HAUFF |
| Permit Finaled | 12/13/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 6/28/2017 | SEVAK ISAKHAYAN |
| Hydrant and Access approval | Cleared | 6/28/2017 | JOHN CONNEALLY |
| Sewer availability | Cleared | 6/28/2017 | SEVAK ISAKHAYAN |
| Low Impact Development | Cleared | 7/11/2017 | RYAN HUDSON |
| Roof/Waste drainage to street | Cleared | 7/11/2017 | ADRIAN SANCHEZ |
| Green Code | Cleared | 7/13/2017 | BRYAN MEYER |
Contact Information
| Architect | Lin, Juintow; Lic. No.: C33054 | 34586 CALLE NARANJA CAPISTRANO BEACH, CA 92624 |
| Contractor | Create R E Inc; Lic. No.: 999515-B | 909 NORTH SEPULVEDA #385 EL SEGUNDO, CA 90245 |
| Engineer | Melchor, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/18/2017 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Excavation/Setback/Form/Re-Bar | 12/20/2017 | Partial Approval | DAVID CHAN |
| PLUMBING-Rough | 12/28/2017 | Partial Approval | DAVID CHAN |
| Excavation/Setback/Form/Re-Bar | 1/3/2018 | Corrections Issued | DAVID CHAN |
| PLUMBING-Rough | 1/3/2018 | Not Ready for Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 1/8/2018 | Not Ready for Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2018 | Partial Approval | DAVID CHAN |
| Footing/Foundation/Slab | 1/26/2018 | Corrections Issued | DAVID CHAN |
| BUILDING-Rough-Frame | 6/4/2018 | Partial Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 10/9/2018 | Partial Inspection | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2018 | Corrections Issued | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2018 | Partial Approval | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2019 | Corrections Issued | DAVID CHAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/25/2019 | Not Ready for Inspection | DAVID CHAN |
| HVAC-Rough | 5/20/2019 | Conditional Approval | DAVID CHAN |
| PLUMBING-Rough | 5/20/2019 | Approved | DAVID CHAN |
| BUILDING-Rough-Frame | 6/18/2019 | Corrections Issued | DAVID CHAN |
| Rough-Elec/Plmb/HVAC | 6/18/2019 | Corrections Issued | DAVID CHAN |
| Interior/Exterior Lathing | 8/23/2019 | Partial Approval | RUBEN SALAS |
| Interior/Exterior Lathing | 9/3/2019 | Not Ready for Inspection | DAVID CHAN |
| Shower Pan | 9/3/2019 | Not Ready for Inspection | DAVID CHAN |
| Insulation | 9/9/2019 | Approved | DAVID CHAN |
| Drywall Nailing | 10/3/2019 | Approved | DAVID CHAN |
| Green Building Rough | 10/3/2019 | Approved | DAVID CHAN |
| Interior/Exterior Lathing | 10/3/2019 | Approved | DAVID CHAN |
| ELECTRICAL-Final | 2/4/2020 | Not Ready for Inspection | AJA COLLAY |
| Special/Order Compliance | 3/3/2020 | Partial Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 3/19/2020 | Not Ready for Inspection | RUBEN SALAS |
| Final | 3/19/2020 | Not Ready for Inspection | RUBEN SALAS |
| Footing/Foundation/Slab | 3/19/2020 | Not Ready for Inspection | RUBEN SALAS |
| Green Building Final | 3/19/2020 | Not Ready for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 3/19/2020 | SGSOV Not Ready | RUBEN SALAS |
| Smoke Detectors | 3/19/2020 | Not Ready for Inspection | RUBEN SALAS |
| Special/Order Compliance | 5/19/2020 | Corrections Issued | DAVID CHAN |
| Special/Order Compliance | 9/15/2020 | Partial Inspection | DAVID CHAN |
| Footing/Foundation/Slab | 12/20/2021 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 1/19/2022 | Partial Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| ELECTRICAL-Final | 8/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Final | 8/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Final | 8/4/2022 | Corrections Issued | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 8/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Final | 8/10/2022 | Corrections Issued | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 8/10/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Final | 8/10/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 8/10/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| Smoke Detectors | 8/10/2022 | Approved | THOMAS LOGRASSO |
| Special/Order Compliance | 9/27/2022 | Partial Inspection | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 10/17/2022 | SGSOV Not Ready | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 12/2/2022 | Approved | THOMAS LOGRASSO |
| Final | 12/2/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 12/2/2022 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 12/2/2022 | SGSOV Approved | THOMAS LOGRASSO |
| Final | 12/6/2022 | OK to Issue CofO | THOMAS LOGRASSO |
| Service/Power Release | 12/6/2022 | Approved | THOMAS LOGRASSO |