1514 N BLUE JAY WAY 90069
Certificate Information: 1514 N BLUE JAY WAY 90069
- Application / Permit
- 17014-30000-00960
- Plan Check / Job No.
- B17WL01202
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add ground floor 333 sq ft to sfd/attached garage.
- Permit Issued
- Issued on 4/6/2017
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 4/6/2017
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 3/7/2017 | APPLICANT |
| Assigned to Plan Check Engineer | 3/7/2017 | HERNAN ARREOLA |
| Plan Check Approved | 4/6/2017 | HARLEN CARRAHER |
| Issued | 4/6/2017 | LADBS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/28/2017 | HARLEN CARRAHER |
| Roof/Waste drainage to street | Cleared | 3/28/2017 | ANDREW SLUSSER |
| Eng Process Fee Ord 176,300 | Cleared | 4/6/2017 | OSCAR GUTIERREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ilasin, John Lacebal; Lic. No.: C67469 | 1237 S VICTORIA AVENUE OXNARD, CA 93035 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/18/2018 | Corrections Issued | DANIEL GONZALEZ |
| Special/Order Compliance | 10/18/2018 | Corrections Issued | DANIEL GONZALEZ |
| Footing/Foundation/Slab | 3/29/2019 | Partial Approval | DANNY TOLENTINO |
| Deputy Drilled-In Anchors | 6/4/2021 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 6/8/2021 | Partial Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 6/8/2021 | Partial Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 8/16/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2022 | Partial Approval | RAUL BARAJAS |
| Green Building Rough | 8/16/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Wood Frame | 8/16/2022 | Not Ready for Inspection | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/22/2024 | Partial Inspection | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 4/22/2024 | Partial Inspection | ROY SPAULDING |
| Green Building Rough | 4/22/2024 | Not Ready for Inspection | ROY SPAULDING |
| BUILDING-Rough-Frame | 4/29/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 4/29/2024 | Partial Approval | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/4/2024 | Partial Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2024 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 10/4/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| HVAC-Rough | 1/28/2025 | Corrections Issued | RAUL BARAJAS |
| Special/Order Compliance | 7/6/2026 | Corrections Issued | BRENDAN MORELLI |