17082 W BOLLINGER DR 90272

Certificate Information: 17082 W BOLLINGER DR 90272

Application / Permit
17014-30000-00676
Plan Check / Job No.
B17WL00815
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Major remodel and 2nd -story addition with roof deck above to the existing 1 -story SFD. Fully sprinklered per NFPA 13D. Deferred roof trusses and spiral stairway (under supplemental permit). "COMPLY WITH DEPARTMENT ORDER effective date 06/27/2017. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 2/14/2019
Issuing Office
Metro
Current Status
CofO Issued on 9/8/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 2/17/2017 APPLICANT
Assigned to Plan Check Engineer 3/16/2017 JOSE RODRIGUEZ
Corrections Issued 3/28/2017 JOSE RODRIGUEZ
Quality Review Completed 3/29/2017 STEVEN KIM
Building Plans Picked Up 3/31/2017 APPLICANT
Green Plans Picked Up 3/31/2017 APPLICANT
Applicant returned to address corrections 2/2/2018 JOSE RODRIGUEZ
Applicant returned to address corrections 3/5/2018 JOSE RODRIGUEZ
Applicant returned to address corrections 12/19/2018 JOSE RODRIGUEZ
Plan Check Approved 2/14/2019 JOSE RODRIGUEZ
Issued 2/14/2019 LADBS
CofO in Progress 8/27/2020 ANDREW NAVE
CofO Issued 9/8/2020 VINCENT COTTON
Permit Finaled 9/8/2020 VINCENT COTTON

Permit Application Clearance Information

GPI Written Notices Cleared 3/5/2018 JOSE RODRIGUEZ
Grading Pre-Inspection Cleared 3/5/2018 JOSE RODRIGUEZ
BHO/Hillside ordinance Cleared 2/13/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 2/13/2019 MARKOS PEREZ-BRAN
BHO/Hillside ordinance Cleared 2/13/2019 MARKOS PEREZ-BRAN
Coastal Zone Cleared 2/13/2019 RINA LARA
Eng Process Fee Ord 176,300 Cleared 2/13/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 2/13/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/13/2019 MARKOS PEREZ-BRAN
Green Code Cleared 2/14/2019 DONALD CRICHLOW
Low Impact Development Cleared 2/14/2019 SARAH YOUSSEF

Contact Information

Contractor Construction & Designers Inc; Lic. No.: 432369-B 1534 N MOORPARK RD #350      THOUSAND OAKS, CA 91360
Engineer Dreckmann, Luis Adrian; Lic. No.: L8919 333 N KALORAMA ST 301B      VENTURA, CA 93001
Engineer Reith, David Lee; Lic. No.: C72122 1319 FEATHER AVE      THOUSAND OAKS, CA 91360
Engineer Shubeck, Robert James; Lic. No.: GE773 60 HACKAMORE LANE      BELL CANYON, CA 91307

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/17/2019 Partial Approval ANDREW NAVE
ELECTRICAL-Rough 6/27/2019 Partial Inspection ANDREW NAVE
Footing/Foundation/Slab 6/27/2019 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 7/9/2019 Conditional Approval ANDREW NAVE
BUILDING-Rough-Frame 7/25/2019 Partial Approval ANDREW NAVE
Green Building Rough 7/25/2019 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 7/25/2019 Partial Inspection ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 7/30/2019 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 8/13/2019 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/10/2019 Partial Approval ANDREW NAVE
Deputy Wood Construction 9/11/2019 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/30/2019 Approved ANDREW NAVE
Interior/Exterior Lathing 12/23/2019 Partial Approval ANDREW NAVE
PLUMBING-Rough 12/23/2019 Approved ANDREW NAVE
HVAC-Rough 12/26/2019 Corrections Issued ANDREW NAVE
ELECTRICAL-Rough 12/30/2019 Approved ANDREW NAVE
BUILDING-Rough-Frame 12/31/2019 Corrections Issued ANDREW NAVE
BUILDING-Rough-Frame 1/14/2020 Approved ANDREW NAVE
ELECTRICAL-Rough 1/14/2020 Approved ANDREW NAVE
Green Building Rough 1/14/2020 Approved ANDREW NAVE
HVAC-Rough 1/14/2020 Approved ANDREW NAVE
PLUMBING-Rough 1/14/2020 Approved ANDREW NAVE
Insulation 1/16/2020 Approved ANDREW NAVE
Drywall Nailing 1/24/2020 Approved ANDREW NAVE
Gas Test 1/24/2020 Approved ANDREW NAVE
Shower Pan 2/12/2020 Approved ANDREW NAVE
Interior/Exterior Lathing 2/19/2020 Partial Approval MICHAEL TEMPLE
ELECTRICAL-Final 6/22/2020 Corrections Issued ANDREW NAVE
ELECTRICAL-Final 7/1/2020 Approved ANDREW NAVE
PLUMBING-Final 7/1/2020 Conditional Approval ANDREW NAVE
Final 7/13/2020 Not Ready for Inspection ANDREW NAVE
Footing/Foundation/Slab 7/13/2020 Approved ANDREW NAVE
Green Building Final 7/13/2020 Corrections Issued ANDREW NAVE
HVAC-Final 7/13/2020 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 7/13/2020 SGSOV Not Ready ANDREW NAVE
Smoke Detectors 7/13/2020 Not Ready for Inspection ANDREW NAVE
ELECTRICAL-Final 7/29/2020 Approved ANDREW NAVE
Green Building Final 7/29/2020 Approved ANDREW NAVE
HVAC-Final 7/29/2020 Approved ANDREW NAVE
PLUMBING-Final 7/29/2020 Approved ANDREW NAVE
Final 8/11/2020 Corrections Issued ANDREW NAVE
SGSOV-Seismic Gas S/O Valve 8/11/2020 SGSOV Approved ANDREW NAVE
Smoke Detectors 8/11/2020 Approved ANDREW NAVE
Final 8/27/2020 OK to Issue CofO ANDREW NAVE
Service/Power Release 8/27/2020 Approved ANDREW NAVE