1260 N BEL-AIR ROAD 90077

Certificate Information: 1260 N BEL-AIR ROAD 90077

Application / Permit
17014-20001-03473
Plan Check / Job No.
B18VN04839
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT FOR 17014-20000-03473 TO EXTEND 2-STORY ADDITION ON NORTH SIDE (16' X 45' ON 1ST FLR & 23' X 12' ON 2ND FLR) OF (E) 2-STORY SFD W/ ATTACHED GARAGE
Permit Issued
Issued on 4/17/2018
Issuing Office
Valley
Current Status
Permit Finaled on 5/14/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/22/2018 APPLICANT
Assigned to Plan Check Engineer 3/22/2018 NILOOFAR MEHRAIN
Corrections Issued 3/22/2018 NILOOFAR MEHRAIN
Plan Check Approved 4/17/2018 NILOOFAR MEHRAIN
Issued 4/17/2018 LADBS
Permit Finaled 5/14/2021 CHRISTOPHER WILSON

Permit Application Clearance Information

GPI Written Notices Cleared 3/22/2018 NILOOFAR MEHRAIN
Grading Pre-Inspection Cleared 3/22/2018 NILOOFAR MEHRAIN
BHO/Hillside ordinance Cleared 3/30/2018 JOHN LIN
BHO/Hillside ordinance Cleared 3/30/2018 JOHN LIN
BHO/Hillside ordinance Cleared 3/30/2018 JOHN LIN
CPC Cleared 3/30/2018 DENNIS CHEW
Eng Process Fee Ord 176,300 Cleared 3/30/2018 JOHN LIN
Hydrant and Access approval Cleared 3/30/2018 JOHN DALLAS
Private street Cleared 3/30/2018 DENNIS CHEW
Sewer availability Cleared 3/30/2018 JOHN LIN
ZI Cleared 3/30/2018 DENNIS CHEW
Low Impact Development Cleared 4/10/2018 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 4/10/2018 KAYLA PEJI

Contact Information

Architect Hersey, John P; Lic. No.: C25560 8067 WILLOW GLEN ROAD      LOS ANGELES, CA 90046
Contractor Owner-Builder       ,
Engineer Zhuang, Wenbin; Lic. No.: S5236 184 S ALTADENA DRIVE      PASADENA, CA 91107

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/1/2018 Partial Approval MATT KELLERMAN
Deputy Reinf. Concrete 6/7/2018 Conditional Approval JOEL LAUNCHBAUGH
PLUMBING-Rough 8/8/2019 Partial Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 9/3/2019 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 9/3/2019 Partial Inspection CHRISTOPHER WILSON
Drywall Nailing 1/10/2020 Approved CHRISTOPHER WILSON
Green Building Rough 1/10/2020 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 5/14/2021 Approved CHRISTOPHER WILSON
Final 5/14/2021 Permit Finaled CHRISTOPHER WILSON
Footing/Foundation/Slab 5/14/2021 Approved CHRISTOPHER WILSON
Green Building Final 5/14/2021 Approved CHRISTOPHER WILSON