22150-22152 W NAPA ST 91304
Certificate Information: 22150-22152 W NAPA ST 91304
- Application / Permit
- 17014-20001-01495
- Plan Check / Job No.
- B18VN00189
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 17014-20000-01495, TO REVISE THE SCOPE OF WORK AND CREATE A NEW ACCESSORY DWELLING UNIT PER AB494 AND SB229. WORK PER ENGINGEERING.
- Permit Issued
- Issued on 2/5/2018
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 5/31/2019
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2018 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2018 | JOHNNY WU |
| Corrections Issued | 1/5/2018 | JOHNNY WU |
| Plan Check Approved | 2/5/2018 | JOHNNY WU |
| Issued | 2/5/2018 | LADBS |
| Permit Finaled | 5/30/2019 | PETER FOLLING |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2018 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 1/5/2018 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/5/2018 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 1/25/2018 | MATTHEW JIMENEZ |
| Roof/Waste drainage to street | Cleared | 1/26/2018 | EDUARDO PEDROZA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mroczka, Peter J; Lic. No.: C42648 | 9301 DARBY AVE APT 1 NORTHRIDGE, CA 91325 |
| Engineer | Zhong, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/20/2018 | Approved | PETER FOLLING |
| PLUMBING-Rough | 2/20/2018 | Partial Approval | PETER FOLLING |
| BUILDING-Rough-Frame | 5/17/2018 | Partial Approval | PETER FOLLING |
| Green Building Rough | 5/17/2018 | Not Ready for Inspection | PETER FOLLING |
| Floor/Roof Diaphrgm/Shear Wall | 7/12/2018 | Approved | PETER FOLLING |
| Green Building Rough | 7/12/2018 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Rough | 8/20/2018 | Not Ready for Inspection | PETER FOLLING |
| Interior/Exterior Lathing | 8/20/2018 | Partial Approval | PETER FOLLING |
| ELECTRICAL-Rough | 9/24/2018 | Approved | PETER FOLLING |
| Green Building Rough | 9/24/2018 | Approved | PETER FOLLING |
| HVAC-Rough | 9/24/2018 | Approved | PETER FOLLING |
| Shower Pan | 9/24/2018 | Approved | PETER FOLLING |
| Gas Test | 10/30/2018 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 10/30/2018 | Not Ready for Inspection | PETER FOLLING |
| BUILDING-Rough-Frame | 11/9/2018 | Approved | PETER FOLLING |
| Gas Test | 11/9/2018 | Approved | PETER FOLLING |
| PLUMBING-Rough | 11/9/2018 | Approved | PETER FOLLING |
| Insulation | 11/15/2018 | Approved | PETER FOLLING |
| Service/Power Release | 11/15/2018 | Not Ready for Inspection | PETER FOLLING |
| Drywall Nailing | 12/20/2018 | Approved | PETER FOLLING |
| Sewer | 12/20/2018 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 3/15/2019 | Not Ready for Inspection | DONALD SUNSERI |
| ELECTRICAL-Final | 5/1/2019 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 5/1/2019 | Not Ready for Inspection | PETER FOLLING |
| PLUMBING-Final | 5/1/2019 | Not Ready for Inspection | PETER FOLLING |
| Service/Power Release | 5/1/2019 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 5/14/2019 | Not Ready for Inspection | PETER FOLLING |
| Final | 5/14/2019 | Not Ready for Inspection | PETER FOLLING |
| Green Building Final | 5/14/2019 | Approved | PETER FOLLING |
| HVAC-Final | 5/14/2019 | Approved | PETER FOLLING |
| PLUMBING-Final | 5/14/2019 | Approved | PETER FOLLING |
| Smoke Detectors | 5/14/2019 | Approved | PETER FOLLING |
| ELECTRICAL-Final | 5/17/2019 | Approved | PETER FOLLING |
| Final | 5/17/2019 | Not Ready for Inspection | PETER FOLLING |
| HVAC-Final | 5/17/2019 | Approved | PETER FOLLING |
| PLUMBING-Final | 5/17/2019 | Approved | PETER FOLLING |
| Service/Power Release | 5/17/2019 | Not Ready for Inspection | PETER FOLLING |
| Final | 5/30/2019 | Permit Finaled | PETER FOLLING |
| Service/Power Release | 5/30/2019 | Approved | PETER FOLLING |